The following sidewalk installation standards apply to all residential subdivisions.
A. Subdividers are required to construct sidewalks in accordance with one of the
following three subsections and in compliance with the final plat review requirements found in Sec. 9.8.
B. Sidewalks must be constructed to the standards detailed in Sec. 8.4.3.
C. Sidewalks are required to be installed along both sides of the street unless
granted a waiver in accordance with Sec.
8.4.5.
D. All sidewalks may be installed as a unit prior to final platting of the subdivision.
1. Subdividers choosing this option must complete the installation of the entire sidewalk system in the subdivision prior to final plat approval. The sidewalks must be constructed as one unit.
2. All sidewalk inspections in subdivisions choosing this option must be performed by the Hall County
Engineering Division. Subdividers utilizing this option must notify the Hall County Engineering Division prior to pouring in order to allow the County Engineers to inspect formwork and subgrade, and must also notify the Hall County Engineering Division after pouring and finishing of the sidewalks to allow for re-inspection by the county if the
county deems it necessary.
3. If a subdivider utilizes this option, the following items must be clearly
shown on the final plat of each such subdivision:
a. The construction details of sidewalks as shown in Plate 3A of the Hall County Standard Details.
b. The typical road section for residential streets with sidewalks as shown on the plates as set forth in the Hall County Standard Details. Plate 1A must be utilized for the final plat in subdivisions that will have sidewalks on both sides of the street. Plate 1C must be utilized for the final plat in subdivisions that will have sidewalks on a single side of the street.
c. A note that reads as follow:
"This development will utilize a sidewalk system throughout the project. The sidewalk system will be installed as a unit prior to final plat approval.
Said sidewalks shall comply with the Hall County Subdivision Regulations. The entire sidewalk system must be
completed prior to release of any maintenance bond, prior to the release of any maintenance agreement, and prior to final platting."
E. All sidewalks may be installed on a lot-by-lot basis after final platting based upon the following criteria.
1. Subdividers choosing this option must construct sidewalks in concurrence with the development of each lot and pour the sidewalks in
conjunction with the pouring of the driveway for each lot.
2. If the proposed subdivision has 35 or fewer lots, subdividers choosing this option must build sidewalks on a lot-by-lot basis within two years of final plat approval, provided that within two years all sidewalks are required to be installed. Any incomplete areas of the sidewalk system must be constructed as one unit before two years expire from the final plat approval.
3. If the proposed subdivision has more than 35 lots but less than 150 lots, subdividers choosing this option must build sidewalks on a lot-by-lot basis within three years of final plat approval or until 90 percent of platted lots have received certificates of occupancy (whichever is less),
provided that within three years all sidewalks are required to be installed. Any incomplete areas of the sidewalk system must be constructed as one unit within three years of the final plat approval.
4. If the proposed subdivision has more than 150 lots, subdividers choosing this option must build sidewalks on a lot-by-lot basis within four years of final plat approval or until 90 percent of platted lots have received certificates of occupancy (whichever is less), provided that within four years all sidewalks are required to be installed. Any incomplete areas of the sidewalk system must be constructed as one unit before four years expire from the final plat approval.
5. Sidewalks poured on a lot-by-lot basis will be inspected by the county Building Inspection Department in conjunction with other inspections.
Certificates of occupancy will not be issued for any lot until a properly constructed sidewalk is in place on that lot.
6. The Hall County Engineering Division will perform all inspections of sidewalks poured as one unit under
this option at the end of the two, three, or four-year period after final platting. Developers utilizing this option will be required to notify County Engineering prior to pouring to allow the County Engineers to inspect formwork and subgrade,
and must also notify County Engineering after pouring and finishing of the sidewalks to allow for re-inspection by the county if the
county deems it necessary.
7. If a developer utilizes this option, the following items must be clearly shown on the final plat of each such subdivision:
a. The construction details of sidewalks as shown in Plate 3A of the Hall County Standard Details.
b. The typical road section for residential streets with sidewalks as shown on the plates as set forth in the Hall County Standard Details. Plate 1A must be utilized for the final plat in subdivisions that will have sidewalks on both sides of the street. Plate 1C must be utilized for the final plat in subdivisions that will have sidewalks on a single side of the street.
c. A note that reads as follows:
"This development will utilize a sidewalk system throughout the project. The sidewalks will be installed on a lot-by-lot basis.
Therefore, property owners of parcels shown on this plat are required to construct sidewalks along the road frontage of their property. Said sidewalks shall comply with the Hall County entire sidewalk system must be completed prior to release of the maintenance bond, prior to the release of any maintenance agreement, and prior to the elapsing of the number of years required for the completion of the sidewalk system under Hall County Unified Development Code Sec.
9.4.8.E. based upon the number of lots in the subdivision."
F. All sidewalks may be installed as a unit within two years after final platting based upon the following criteria.
1. Upon the elapsing of two years after final platting the entire sidewalk system must be constructed as one unit.
2. All sidewalk inspections in subdivisions choosing this option will be performed by the Hall County
Engineering Division. Subdividers utilizing this option will be required to notify the Hall County Engineering Division prior to pouring in order to allow the county's engineers
to inspect formwork and subgrade, and shall also notify the Hall County Engineering Division after pouring and finishing of the sidewalks to allow for re-inspection by the county if the county deems it necessary.
3. If a subdivider utilizes this option, the following items must be clearly
shown on the final plat of each such subdivision:
a. The construction details of sidewalks as shown in Plate 3A of the Hall County Standard Details.
b. The typical road section for residential streets with sidewalks as shown on the plates as set forth in the Hall County Standard Details. Plate 1A must be utilized for the final plat in subdivisions that will have sidewalks on both sides of the street. Plate 1C must be utilized for the final plat in subdivisions that will have sidewalks on a single side of the street.
c. A note that reads as follow:
"This development will utilize a sidewalk system throughout the project. The sidewalk system will be installed within two years after final plat approval. Said sidewalks shall comply with the Hall County entire sidewalk system must be completed prior to release of the maintenance bond, prior to the release of any maintenance agreement, and prior to the elapsing of two years after final platting."