9.4.7. Installation of Utilities

About this text

  • As published by Municode, current through 2026-05-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Underground utilities, including sewer services, all water lines and any cable

conduits under the pavement, shall be placed in the ground before the base material is in place.

B. All trenches shall be thoroughly compacted in six-inch layers with mechanical

compacting equipment.

C. All fire hydrants, utility poles, streetlights, transformer boxes and pedestals shall be set at a distance not less than six feet from the back of the curb.

D. The subgrade shall be scarified to a minimum depth of six inches and compacted to at least 98 percent maximum dry density immediately prior to the

placing of the base material.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hall-county/zoning/9.4.7@2026-05-28-7d1e22b4d7

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Hall County Zoning Ordinance, 9.4.7. Installation of Utilities | Georgia Commons