11.2.2. Care should be taken to

About this text

  • As published by Municode, current through 2026-05-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

observe the schedule, as unnecessary delay and additional expense may result if the construction is

varied substantially from the schedule.

Table 11.2.2. Construction Inspections Type Responsibility Soil Erosion Control County Engineering Department Clearing and Grubbing County Engineering Department Subsurface Drainage Installation County Engineering Department Wet Weather Springs, Soft Spots and Swamps County Engineering Department Street Grading and Staking County Engineering Department Water System Installation County Engineering Department Subgrade Stabilization County Engineering Department Sanitary Sewer Installation Utility owner, County Health Department, County Engineering Department Curb and Gutter Form and Work Lines County Engineering Department Curb and Gutter Installation County Engineering Department Base Course Application County Engineering Department Asphalt Pavement Installation County Engineering Department Sidewalk Form Work* County Engineering Department Sidewalk After Pouring and Finishing* County Engineering Department Sidewalks Poured on a Lot by Lot Basis County Building Inspection Department Shaping and Backfilling+ County Engineering Department Grassing of Shoulder and Slope County Engineering Department Shoulder Shaping and Backfilling+ County Engineering Department Re-grassing+ County Engineering Department Sign Installation County Engineering Department Table Notes:

* For instances when sidewalks are constructed as a single unit.

+ As applicable or required by the county.

23. Completion of water and sewer Installations. All underground water and sewer installations, including sewer cross taps to individual lots, must be completed prior to the application of the base course.

24. Inspection Required. The inspection of all construction is required.

The subdivider is responsible for notification of the inspection authority 24 hours prior to the covering of the work. Before reinspection of

any subdivision development site by the county, the developer of such site must pay the reinspection fee as established in the Hall County Plan Review and Inspection Fee Schedule if the reinspection is necessitated by the developer's failure to comply with these regulations. From

time to time, upon the recommendation of the Director of Public Works and Utilities of Hall County, Georgia,

and approval of the Board of Commissioners of Hall County, Georgia, said schedule may be revised as

deemed necessary.

25. Stages for notification of county engineering department. The county Engineering Department must be notified:

a. At completion of clearing and grubbing and prior to grading;

b. Prior to covering stormwater drainage pipe;

c. At completion of grading and restaking the centerline prior to setting curb forms and line;

d. For subgrade and curbing inspection prior to application of base course;

e. At completion of the base course and prior to the application of the prime coat;

f. At completion of the prime coat and prior to the application of the paving course in order to schedule the presence of a county inspector during application of plant mix;

g. Upon construction of sidewalk formwork, prior to pouring of concrete. (Note: Inspections on sidewalks poured on a lot-bylot basis are handled by county building inspections.)

h. After pouring and finishing of sidewalks. (Note: Inspections on sidewalks poured on a lotby-lot basis are handled by county building inspections.)

i. At completion of shoulder reconstruction and shaping, prior to final seeding;

j. At completion of construction and final plat;

k. Fifteen months from acceptance of the maintenance bond or 75 percent build-out, whichever occurs last; (publicly maintained residential subdivisions);

l. One year from acceptance of maintenance bonds for paving only in any subdivision with roads built to industrial standards (depths of base and asphalt only);

m. One year from acceptance of the maintenance bond in privately maintained subdivisions and;

n. At such other times as the Director of Engineering should specify.

26. Private Utility Inspection Schedule. The owner of any utility serving a subdivision must set its own inspection schedule.

27. Inspection of Community Water or Sewer System. The inspection of any community water system or any community sewer system must be as required by the Director of Engineering and the applicable state agency.

28. Use of Testing Agency. If tests of materials or construction are required, a recognized testing agency must be used, and the owner of the subdivision bear any expense.

29. Final Plat Approval; generally.

Whenever the provisions of these regulations have been complied with and while the certificate of preliminary plat approval is in effect, the subdivider may submit to the Director of Planning and Zoning, for final plat review and approval, the following items in subsections 30 and 31 below.

30. Final Plat Application. The subdivider must submit an application signed by the subdivider, stating:

a. Total acreage.

b. Number of lots.

c. Minimum lot size.

d. Proposed use of each lot.

e. Water supply system.

f. Sewer system.

g. Length of proposed roads.

h. Phasing of the subdivision.

i. Estimated time for completion.

j. An outline of any proposed organizations to control a portion or all of the tract, such as a homeowners' association or

equivalent body; and

k. Notice of intent to dedicate any portion of the property to the public.

31. Final plat approval; agency approvals and surveyor's certificate. The subdivider must submit copies of the final plat, drawn according to this Sec. 11.2, having affixed to them the stamps or signatures of the following applicable agencies or firms. A letter from an applicable agency may be submitted in lieu of a plat stamp:

a. Approval of the Director of Utilities if to be served by a public water system;

b. Approval of the Department of Natural Resources and Director of Engineering if to be served by a community water

system;

c. Approval of the Director of Utilities if to be served by a public sewer system;

d. Approval of the Department of Natural Resources and Director of Engineering if to be served by a community sewer

system;

e. Approval of the county health department;

f. Preliminary engineering certificate, signed and sealed by an engineer, surveyor or landscape architect registered in Georgia;

g. Approval for construction by the Director of Engineering.

32. Final Plat Approval; copy of improvement guarantee. The subdivider must submit a copy of any improvement guarantee for which provision is made in Article 9.

33. Final Plat Review; review by Planning and Zoning Director.

The Director of Planning and Zoning must review the final plat for compliance with these regulations, the zoning regulations, conditions of

zoning, and the regulations of other county departments and state agencies, as appropriate.

34. Final plat review; compliance responsibility. The subdivider is responsible for compliance with all appropriate regulations.

35. Final plat review; approval requirements and maintenance bond.

a. Bonding instrument requirement. Final approval by the Director of Planning and Zoning

must not be shown on the final plat until all requirements of these regulations have been met and until the Hall County Engineering Division has certified by letter or endorsement on the plat that a maintenance

bond (either in the form of a guaranty bond or cash deposited in escrow for the county) or an irrevocable letter of credit has been received which adequately and sufficiently provides for the maintenance of all installations and improvements required by these regulations

for a period of 24 months following the date of final plat approval for base, paving, grassing, storm water management facilities, sidewalks, and any

other necessary infrastructure within that subdivision.

b. Bonding and maintenance agreement. All bonding instruments must be valid for a minimum of 24 months from

the date of issuance. The guarantee bond, escrowed cash, or irrevocable letter of credit must also be accompanied by completed forms provided by the Hall County Engineering Division, and must also be accompanied by a fully executed Maintenance Agreement by which the developer agrees to maintain all such facilities and infrastructure for a period of not less than 24 months from the date of final platting. All bonding instruments must be issued by a company with a minimum A rating (or better), and which is licensed to do business in the State of Georgia and with a principal office and registered agent located in the State of Georgia.

c. Storm water bonding release.

Storm water management facilities will need to be cleaned of accumulated silt and properly maintained as provided in Sec.

10.5, prior to release of issued bonds.

d. Bonding instrument amount.

The amount of the bonding mechanism must equal 30 percent of all completed infrastructure including base, paving, grassing, storm water management facilities, sidewalks, and any other necessary infrastructure plus 100 percent of the cost of all

incomplete infrastructure such as remaining sidewalks and asphalt topping. The unit cost data used in the initial calculations will be based upon the latest Georgia Department of

Transportation (GDOT) Item Mean Summary plus up to ten percent per year, or the latest county contract data, whichever is higher. The county is also authorized to require yearly increases in the face amount of required bonds based upon the consumer price index in order to cover the increasing cost of construction and maintenance of infrastructure due to economic inflation.

e. Transfer of land ownership during the bonding period. No person, firm, partnership, association, corporation, estate, trust, developer, subdivider, or any other owner or agent may transfer title of a property which is the subject of any active maintenance or performance bonds without first providing to the county, as beneficiary, a newly executed bonding instrument for the new owner or developer. The newly executed bonding instrument must be presented to and approved by the Hall County Board of Commissioners.

f. Bonding instrument collection fee. Hall County may impose a collection fee $1,000.00 for any bonding instrument that is presented to the Hall County Board of Commissioners for collection, which fee the Board of Commissioners reasonably

believes to be related to the costs associated with collection on such a bond. The Director of Public Works and Utilities is granted authority to initiate

collection efforts at their discretion. Staff must commence collection efforts at least 90 days prior to the expiration of the

bond in order to allow sufficient time for collection. The developer must deposit

$1,000.00 at the time of submission of the bond to the county, and the $1,000.00 will be

refunded once bonded work is completed more than 45 days prior to the expiration of the bond or the bond is renewed more than 45 days prior to its expiration.

g. Request for final acceptance and release of bonds. Roads within a development are not accepted into the Hall County road system until there has been a request for acceptance by the developer and a favorable vote by the Hall County Board of Commissioners to accept the roads and to release all bonding mechanisms relating to the development. Likewise, the

county may release bonding mechanisms only upon a favorable vote by the Hall County Board of Commissioners.

Release of bonds can occur after all asphalt road construction has been in place for a minimum of one year, and all infrastructure is installed to the satisfaction of Hall County's Engineering Division. In order for the county's Board of Commissioners to release bonding mechanisms Hall County's

Engineering Division must confirm that:

i. All improvements and installations to the subdivision required for approval of the final plat under the rules and regulations of the county have been completed in accordance with the appropriate specifications;

and ii. All of the drainage and retention facilities, grading, water and sewer utilities, street base and curbing construction, and

grassing required for approval of the final plat have been completed.

36. Final plat review; certification of approval. When the Director of Planning and Zoning has approved the final plat, and other affected departments and agencies of government as required have certified compliance and signed the original,

the Director may certify by signature on the plat that all of the requirements of these regulations, the zoning regulations, and the conditions of zoning approval have been met. The final plat will not be

deemed approved until it has been signed by the Director and duly authorized representatives of the Engineering Department, Water Department and Health Department.

37. Issuance of certificates of occupancy. Where an improvement guarantee has been required for a subdivision, no certificate of

occupancy for any building on any lot fronting a proposed road in the subdivision may be issued prior to completion of improvements under the guarantee.

38. Final Plat; Revisions. No change, erasure, or revision may be made on any preliminary or final plat, nor on accompanying data sheets, after approval of the county has been endorsed in writing on the plat or sheets, unless authorization for such changes has been granted in writing by the Director of Planning and Zoning. In no case may the Director

approve a revision thereof unless the fact that it is a revised plat is clearly stated thereon.

39. Final Plat; filing for recordation.

a. An approved final plat must be filed for recording by the subdivider in the office of the Clerk of Superior Court within 60 days after final approval thereof. Otherwise, such approval may be void. No Clerk of Superior Court shall file or record a plat of a subdivision until such plat has been approved by the Director of Planning and Zoning.

b. The approval of a plat will not be deemed to constitute or effect acceptance by the county of any street or other ground shown on the plat.

40. Final Plat; Recordation. The Clerk of Superior Court must file and record in their office maps or plats relating to real estate in the county.

41. Specifications for maps and plats. Maps or plats to be filed and recorded in the office of the Clerk of Superior Court must be prepared in accordance with the following minimum standards and specifications:

a. Material. Any such maps or plats must conform to the Georgia Plat Act, as amended.

b. Caption. The maps or plats must have a title or name which must be contained in the caption, and the caption must also provide the following information:

i. The county, city, town, or village, land district and land lot, and subdivision, if the property lies within a particular subdivision.

ii. The date of plat preparation.

iii. The scale, stated and shown graphically.

iv. The name of the land surveyor and their registration number.

c. Size. Maps or plats must not be less than 8� inches by 11 inches and not larger than 17 inches by 23 inches.

d. Data. Maps or plats must be made in a professional manner and in accordance with the standards of good drafting procedures and must show the following information, as specified:

i. All maps or plats must show the direction and distance from a point of reference to a point on the boundary of the individual survey, and such additional data as may be required to relocate the boundary point from the point of reference with the same degree of accuracy required of the parcel surveyed. The point of reference must be an established monument position which can be identified or relocated from maps, plats, or other documents on public record.

ii. All maps or plats of boundary surveys or subdivision surveys must show bearings and distances of

all lines, and area of the parcels expressed in acres and square feet.

iii. All maps or plats of boundary surveys must show the closure precision of

the field survey as the ratio of one foot to the traversed distance in which an error of one foot would occur and a statement as to the method of adjustment. The closure

may be stated as follows:

"The field data upon which this map or plat is based has a closure precision of one foot in feet, and an angular error of per angle point, and was adjusted using rule."

iv. All maps or plats of boundary surveys must show the closure precision of

the data shown on the map or plat. The closure may be stated as follows:

"This map or plat has been calculated for closure and is found to be accurate within one foot in feet."

v. All maps or plats must show the width, and the former widths if pertinent, of all rights-of-way adjacent to or crossing the property or adjacent to any point of reference.

vi. All maps or plats must show easements and apparent encroachments, if pertinent.

vii. In the case of curved lines, pertinent data must be given for regular curves.

Chord distances and directions must be given for irregular curves.

viii. All land lot lines, land district lines, land section lines and city and county boundaries intersecting or adjacent to the surveyed property must be indicated by lines drawn upon the map or plat with appropriate words and figures.

ix. All corner markers and markers of pertinent reference points must be fully described and indicated

as to their material or types and must be constructed of a permanent material such as iron, steel, concrete, or stone.

x. An arrow must be shown on the map or plat to indicate the principal meridian, and a notation made as to the reference of bearing to magnetic north, astronomic north, or grid north. A grid north reference must indicate the zone.

xi. All linear distances shown on maps or plats must be horizontal.

xii. All angular directions shown on maps or plats must be represented in degrees and minutes.

Where plats state or surveys require accuracy in excess of one in 5,000, the angular direction must be represented in degrees, minutes, and seconds. All angular direction must be referenced to the principal meridian.

xiii. A statement must be shown on the map or plat to indicate the type of equipment used to obtain the linear and angular measurements used in the preparation of the map or plat.

B. Plat Specifications

1. Plat Requirements, generally.

Plats submitted to the county must contain the following information as specified in this section.

2. Preliminary Plat Contents. All applications for a certificate of preliminary plat approval for a subdivision must be accompanied by copies of the plat setting forth the proposed design of such subdivision. The scale of such plats may be no less than 100 feet to the inch.

Such plats must contain the following information:

a. Proposed name of subdivision

b. Name and address of the owner of record.

c. Name, address, telephone number, seal, and signature of the registered engineer, surveyor or landscape architect responsible for the construction plans and surveyor responsible for the boundary

survey.

d. Name, address, and telephone number of the subdivider.

e. Date of survey, north point and graphic scale, source of datum, date of plat drawing, and space for revision dates.

f. Natural features within the proposed subdivision, including drainage channels, bodies of water, wooded areas and

other significant features. On all water courses leaving the tract, the direction of flow must be shown.

g. Cultural features within the proposed subdivision, including right-of-way and pavement widths, and names of existing

and platted streets adjoining or abutting the subdivision, all easements, city and county lines and other significant information. Location and dimensions of bridges, utility lines and

structures, buildings, culverts, cemeteries, and other features must also be indicated.

h. Location (land district and land lot) and acreage.

i. Location sketch locating the subdivision in relation to the surrounding area with regard to well-known landmarks such as major thoroughfares, railroads or others. Sketches may be drawn in freehand and at a scale sufficient to show clearly the information required, but not less than one inch to 2,000 feet. U.S. Geological Survey maps may be used as a reference guide for the

location sketch.

j. Name of former subdivision, and the plat book and page numbers where it was recorded, of any or all of the preliminary plat that has been previously subdivided.

k. The location and specifications of proposed streets, including right-of-way lines, proposed roadbed type, roadbed width, and proposed grades.

l. Exact boundary lines of the tract indicated by a heavy line giving lengths and bearings.

m. Proposed layout, including lot lines with rough dimensions, lot numbers, block letters, street lines with letter designations for proposed street names, right-of-way widths, and sites reserved through covenants, easements, dedication or otherwise for public uses, for single-family dwellings, for nonresidential uses, and for multi-family dwellings.

n. Contour lines based on sea level datum. These must be drawn at intervals of five feet for hilly terrain (slopes greater than ten percent), two feet for rolling terrain (two percent to ten percent) and one foot for flat terrain (slopes less than two percent). Contour lines must be based on field surveys.

Topographic data based on geological survey maps which have been adjusted by field survey data may be accepted if the Director of Engineering determines that such data will be adequate to evaluate the layout of lots and streets, drainage and other service requirements.

o. The preliminary plan of any existing and proposed water lines, sanitary sewers and storm sewers. Such plans must include the proposed size of the pipe to be installed and the proposed percent grades of the lines of all sewers.

p. The distance and direction to public water lines and sanitary sewer lines.

q. Location of drainage easements for all storm drain facilities, outlets, and subsequent drainage ways, streams and at other locations as required.

r. Proposed unit division or stage development, if any, as proposed by the subdivider.

s. Location and results of percolation tests for lots which will not be served by a public or

community sanitary sewer system, as required by the health department.

t. Location or statement of flood hazard areas.

u. Any other information as may be required by the health department and Director of Planning and Zoning to determine whether or not the proposed design of the subdivision will conform to the design requirements of these regulations.

3. Preliminary Plat; supplemental information. The preliminary plat must be accompanied by the following information when same is not shown on or evident from the

preliminary plat:

a. A written summary of the proposal giving information as to the overall development plan, giving type of structure, number of dwelling units, and types of business and industry, so that the effects of the development can be determined by the Director of Planning and Zoning.

b. Source of water supply.

c. Statement of provision for sewage disposal and drainage.

d. Drainage information:

i. Location and size of all proposed drainage structures.

ii. Acreage of drainage area.

iii. Location of land subject to flooding.

e. Engineering data as listed below:

i. A ground run profile of proposed streets must show original centerline elevations. The profile must be drawn on standard plan and profile sheets with the plan section showing street layout, curvature and drainage

required.

ii. Where sanitary or storm sewers are to be installed, size of pipe and location of manholes must be indicated on the street profile.

iii. Profiles of streets that are extensions of existing streets must include elevations at 50-foot intervals for a minimum distance

of 200 feet back of beginning point and forward of ending, or such additional

distance as may be required by the Engineering Department.

iv. The above plans must be drawn to a scale no less than as follows: a horizontal scale of one inch to 100 feet, and a vertical scale of one inch to ten feet.

v. Cross-sections at all crossdrain locations extending 25 feet beyond the pipe: a

horizontal scale of one inch to ten feet, and a vertical scale of one inch to ten feet.

vi. Where a proposed street construction limits or abuts the plat boundary, cross-sections and the necessary slope easement must be submitted. A slope easement must also be submitted under such other conditions as may be required by the Director of Engineering.

vii. Municipal, county, or land lot lines tied to the lines of the subdivision by distance and angles when such lines traverse the subdivision.

viii. Exact locations, widths, and names of all streets within and immediately adjoining the plat.

ix. Street centerlines showing stations and standard curve data of intersection, radii, length of tangents and arcs, and

degree of curvature.

x. Lot lines with dimensions to the nearest foot, and minimum lot area.

xi. Lots numbered in numerical order and blocks lettered alphabetically.

xii. Name of each street.

xiii. Minimum setback lines on all lots and other sites.

xiv. Location and description of monuments.

xv. Names of recorded owners of adjoining unplatted land.

xvi. Reference to recorded subdivision plats of adjoining platted land by record name, data, and number,

when known.

xvii. Certification by a surveyor certifying to accuracy of the survey and plat.

xviii. Militia district and, when applicable, the land lot number.

xix. When lots are located on a curve or when side lot lines are at angles other than 90 degrees, the lot width at the building line must be shown.

xx. When the subdivided property abuts Buford Dam Reservoir property or easement, the 1,071- foot contour line must be shown and designated "Lake Sidney Lanier— Normal Lake Level" and the 1,085-foot contour line must be shown and designated "Lake Sidney Lanier—Maximum Lake Level."

xxi. Location, dimension and purpose of all drainage structures and of any easements, including slope easements, if required, and public utility right-ofway lines, and any areas to be reserved, donated,

or dedicated to public use of sites for other than residential use with notes stating their purpose and limitations; and of any areas to be reserved by deed covenant for common uses of all property owners.

xxii. Places for certificates and statements specified in this Sec. 11.2.

xxiii. Plans must show clearly the elevation and/or contour of the 100-year floodplain of any stream or backwater area on the site.

f. Contents of Final Plat. All applications for a recording permit must be accompanied by electronic plans and paper copies of the final plat of the subdivision to be recorded. The submitted prints of such final plat must be not greater than 17 inches by 23 inches at a scale of not less than 200 feet to the inch. Where necessary, the final plat may be on several sheets accompanied by an index sheet showing the entire subdivision. The final plat must contain the following information:

i. Name of the subdivision.

ii. Name and address of owner of record.

iii. Name and address of subdivider.

iv. Date of plat drawing, graphic scale, north point, and notation as to the reference of bearings to magnetic, true north, or grid north.

v. Location of tract (militia district, land district and land lot), giving the area of each individual lot.

vi. Primary control point to which all dimensions, angles, bearings, and similar data on the plat may be referred.

vii. Tract boundary lines, right-of-way lines of streets, easements and other right-of-way and property lines of all lots with accurate dimensions;

bearings or deflection angles, radii arcs, and central angles of all curves.

viii. Name of each street.

ix. Minimum setback lines on all lots and other sites.

x. Location and description of monuments.

xi. Names of recorded owners of adjoining unplatted land.

xii. Reference to recorded subdivision plats of adjoining platted land by record name, date, and number,

when known.

xiii. Certification by surveyor as to accuracy of the survey and plat.

xiv. Lot lines with dimensions and lot area.

xv. When the tract of land to be subdivided abuts on U.S. government property, then the final plat of the subdivided land must show a tie or ties of land lot lines conforming to U.S.

government take line descriptions.

xvi. When lots are located on a curve or when side lot lines are at angles other than 90 degrees, the lot width at the building line must be shown.

xvii. Lots or sites numbered in numerical order and blocks lettered alphabetically. In general, all lots should be numbered in

numerical sequence without using block letters.

xviii. When the subdivided property abuts Buford Dam Reservoir property or easement, the 1,071- foot contour line must be shown and designated "Lake Sidney Lanier— Normal Lake Level" and the 1,085-foot contour line must be shown and designated "Lake Sidney Lanier—Maximum Lake Level."

xix. Location, dimensions and purpose of entire drainage, sewerage, water and public utilities systems

and of any easements, including slope easements, if required, and public utility right-of-way lines, and any areas to be reserved,

donated, or dedicated to public use of sites for other than residential use with notes stating their purpose and limitations, and of any areas to be reserved by deed covenant for common uses of all property owners.

xx. Places for certificates and statements specified in this Sec. 11.2.

g. Conformity of final and preliminary plat. The final plat must conform to the preliminary plat and it may constitute only that portion of the approved preliminary plat which the subdivider proposes to record and develop at any one time, provided that such portion conforms to the staging established in preliminary plat procedure and to the

requirements of these rules and regulations.

h. Preliminary Plat Certificates. Each preliminary plat submitted to the county must carry the following certificates printed or stamped thereon substantially as follows:

i. Preliminary engineering certificate.

"I hereby certify that this proposed Development Plat correctly represents construction plans completed by me on (date).

By (name), Registered P.E., Surveyor, or Landscape Architect License Number (insert) Date (insert)" ii. Certificate of preliminary plat approval.

"All requirements of the county subdivision regulations relative to the preparation and submittal of a Preliminary Plat having been fulfilled,

approval of this plat is hereby granted, subject to further provisions of said regulations. This Certificate shall expire (date).

Name (insert), Chairman, Planning Commission, or designee Date (insert)" iii. Development Plat—Not to be Recorded.

i. Final Plat Certificate. Each final plat submitted to the Director of Planning and Zoning for approval must carry the following certificates printed or stamped thereon substantially as follows:

i. Surveyors Certificate.

"It is hereby certified that this plat is true and correct and was prepared from an actual survey of

the property made by me or under my supervision;

that all monuments shown hereon actually exist or are marked as "Future," and their location, size, type, and material are correctly shown; and that all relevant requirements of

the Hall County Zoning and Subdivision Regulations have been met.

By (name), Registered Ga.

Land Surveyor License Number (insert) Date (insert) ii. Owners dedication certificate (when appropriate).

"(State of Georgia) or (County of Hall) The owner of the land shown on this plat and whose name is subscribed thereto, and in person or through a duly authorized agent, acknowledges that this plat was made from an actual survey and dedicates to the use of the public forever, all streets, parks, drains, easements, and public grounds thereon shown, which comprise a total of acres, for the purposes therein expressed.

Owner (name) Date (insert)" iii. Place for approval of Director of Engineering.

iv. Place for approval of the county health department.

v. Place of approval for the county Director of Planning and Zoning as follows:

"Pursuant to the Hall County Subdivision Regulations, this plat is given final approval by the Hall County Planning and Zoning Director. All of the conditions of approval having been completed, this document is hereby accepted and this approval granted under the authority of said Regulations.

Name (insert), Director of Planning and Zoning Date (insert)"

4. Planned Development.

a. The standards and requirements of this UDC may be modified in the case of a plan

and program for a community or neighborhood unit or planned development which is not divided into customary lots, blocks and streets, which in the judgment of the Planning Commission provides adequate public spaces and improvements for the circulation, recreation, light, air and service

needs of the tract when fully developed and populated, provided density standards for the entire tract are not exceeded, and which also provides such covenants or other legal procedures as will assure conformity to the achievement of the plan. Plans for such development must be submitted to and approved by the Planning Commission and Board of Commissioners whether or not such plat is to be recorded, and no building permit may be issued until such approval has been given.

b. Prior to processing such a planned development, the developer must indicate their willingness to increase the processing time specified.

However, in no case may the Planning Commission authorize a use prohibited in the district in which the project is to be located, or a smaller lot area per dwelling unit than the minimum required in such district.

C. Appeals All appeals must be filed in accordance with Sec. 11.2.7.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hall-county/zoning/appendix-a-11.2.2@2026-05-28-ba12dcdad5

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Hall County Zoning Ordinance, 11.2.2 (Appendix A). Care should be taken to | Georgia Commons