Harris County · Zoning Ordinance

Appendix A - UNIFIED DEVELOPMENT CODE / Article 9 - PROJECT DESIGN AND CONSTRUCTION STANDARDS / Division II - PROJECT CONSTRUCTION STANDARDS

910.02. Development phase inspections.

About this text

  • As published by Municode, current through 2023-12-05
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Requests for inspections shall be made by the owner or contractor to the Community Development, Public Works or Water Works Department in accordance with the listing of inspection

responsibilities established by Harris County.

Such requests shall be made at least 24 hours prior to when the inspection is needed. Inspections shall be made and passed prior to continuation of further activity or proceeding into new phases of development. Inspections are required

of each of the following phases, as applicable to the actual work to be performed under the development permit:

(a) Prior to clearing or clearing and grubbing of the property or any portion included under the development permit,

inspection of erosion and sedimentation control measures and protective devices for undisturbed areas. Inspection of erosion and sedimentation control measures will be conducted on a continuing basis.

(b) Upon completion of street grading, inspection and approval shall be required prior to trenching or continuation with subgrade preparation.

(c) Upon installation of storm drainage pipe, detention, or other storm water facilities.

(d) Of street curbing and gutter (if provided).

(1) Inspection shall be requested after the forms or string line have been set.

(2) Street width and vertical and horizontal alignment may be spotchecked.

(e) Of sub-grade of streets. The sub-grade may be roll tested in accordance with Section 913.

(f) Of street base.

(1) The base may be string-lined for depth and crown.

(2) The street base will be tested for depth and compaction in accordance with Section 913 and may be rolltested in accordance with Section 913 at the discretion of the County

Inspector.

(g) Of paving.

(1) A County Inspector may be on site during the paving process to check consistency, depth, and workmanship, as applicable.

(2) For asphalt paving, the temperature of the material will be monitored, the asphalt will be tested for depth and compaction in accordance with Section 913 and may be roll-tested in accordance with Section 913, at the discretion of the County Inspector.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:harris-county/zoning/910.02@2023-12-05-d69c3100bd