Sec. 6.5.3. Application requirements.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

a. The application for a development permit shall be submitted to the Building Inspector and must include the applicant's civil design and construction drawings, including an erosion and sediment control plan with supporting data, as appropriate to the proposed project. Said plans shall include, as a minimum, the data specified in this Section.

b. Upon receipt of a development permit application, the Building Inspector shall refer the soil erosion and sediment control plan to the Ocmulgee Soil & Water Conservation District for its review and approval or disapproval concerning the adequacy of the erosion and sediment control plan. The results of the District review shall be forwarded to the City. No development permit will be issued unless the plan has been approved by the District, and any variances and bonding, if required, have been obtained.

c. If the applicant has had two (2) or more violations in the city of previous permits, this ordinance, or the Georgia Erosion and Sedimentation Act, as amended, within three (3) years prior to the date of filing of the application under consideration, the Building Inspector shall refer the development permit application to the Board of Commissioners.

(1) The Board of Commissioners may deny the development permit application; or,

(2) The Board of Commissioners may require the applicant to post a bond in the form of government security, cash, irrevocable letter of credit, or any combination thereof up to, but not exceeding, three thousand dollars ($3,000.00) per acre or fraction thereof of the proposed land-disturbing activity, prior to issuing the development permit. If the applicant does not comply with this ordinance or with the conditions of the development permit after issuance, the Board of Commissioners may call the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance.

d. No development permit shall be issued unless the applicant provides a statement by the City of Hawkinsville, Clerk's Office, certifying that all ad valorem taxes levied against the property and due and owing have been paid.

History

The history line the source prints at the end of the section.

(Ord. of 5-10-96)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hawkinsville/zoning/6.5.3@2026-11-11-0b8d70e1f9

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Hawkinsville Zoning Ordinance, Sec. 6.5.3. Application requirements | Georgia Commons