Sec. 46-272. Solar energy system, ground-mounted.

About this text

  • As published by Municode, current through 2024-07-16
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

In zoning districts where permitted, a "solar energy system, ground-mounted," as defined in section 46-1, shall be subject to the following regulations:

(a) Placement.

(1) A ground-mounted solar energy system shall not be located within the required front yard of a lot.

(2) A ground-mounted system shall not be located over a septic system, leach field area or identified reserve area unless approved by the health department.

(3) If located in a floodplain or an area of known localized flooding, all panels, electrical wiring, automatic transfer switches, inverters, etc.

shall be located above the base flood elevation.

(4) Panels and ground mounts shall be installed per manufacturer's specifications.

(b) Maximum area coverage. For residential properties, a ground-mounted solar energy system shall not exceed 25 percent of the footprint of the principal building served. For non-residential properties, a solar energy system shall not exceed 50 percent of the footprint of the principal building served.

(c) Height. The maximum height of a ground-mounted solar energy system shall not exceed the maximum building height for accessory buildings in the zoning district in which it is located, or 20 feet, whichever is less.

(d) Permitting. A building permit is required for any ground-mounted solar energy system and for the installation of any thermal solar energy system.

All federal, state, and utility company permits must be approved before a Heard County building permit is issued.

History

The history line the source prints at the end of the section.

(Ord. of 12-19-2017(1), § 2)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:heard-county/zoning/46-272@2024-07-16-c6374055ff

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Heard County Zoning Ordinance, Sec. 46-272. Solar energy system, ground-mounted | Georgia Commons