A. Sub-grade preparation on all non-local streets shall be in accordance with GDOT specifications and these regulations. Sub-grade preparation for local streets shall meet and pass proof roll testing.

B. If any section of the sub-grade is composed of topsoil, organic, or other unsuitable or unstable material, such material shall be removed and replaced with suitable material and then thoroughly compacted as specified for fill, or stabilized with stone or a geo-textile or geo-grid.

C. Fill shall be placed in uniform, horizontal layers not more than eight inches thick (loose measurement). Moisture content shall be adjusted as necessary to compact material to 95 percent of maximum dry density except for the top twelve inches, which shall be compacted to 100 percent of maximum dry density.

D. After the earthwork has been completed, all storm drainage, water, and sanitary sewer utilities have been installed within the right-of-way as appropriate, and the back-fill in all such ditches thoroughly compacted, the sub-grade shall be brought to the lines, grades, and typical roadway section shown on the plans.

E. Utility trenches cut in the sub-grade shall be back-filled as specified herein.

Compaction tests at the rate of one per 150 feet of trench shall be provided to verify compaction.

F. The sub-grade must pass proof roll testing regardless of compaction test prior to placement of the base material. With the approval of the Kennesaw Public Works and Community Development Department, a geo-textile or grid may be used to stabilize a sub-grade that does not pass proof-rolling.

G. Provisions shall be made to drain low points in the road construction when the final paving is delayed. A break in the berm section is required when the curbing has not been constructed. After installation, drainage under the curb is required.

History

The history line the source prints at the end of the section.

(Ord. No. 2018-21, § l(Exh. B), 10-15-18)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:kennesaw/zoning/6.02.36@2026-11-11-9fd4cd78ea

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Kennesaw Zoning Ordinance, 6.02.36. Sub-Grade Preparation | Georgia Commons