Sec. 25C-10-38. Standards for tree protection during construction.

About this text

  • As published by Municode, retrieved 2026-11-14
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

In the tree save area, protective measures shall be applied to the aboveground portion of a tree and to roots within the critical root zone, as follows:

(1) Damage prohibited. No person shall:

a. Cut, carve, transplant, or otherwise damage or remove any tree;

b. Attach any rope, wire, nails, advertising posters, or other contrivance to any trees;

c. Allow any gaseous, liquid or solid substance which is harmful to trees (such as concrete washout, fuels, lubricants, herbicides, paint, etc.) to come in contact with them; or

d. Set a fire or permit any fire to burn when such fire or the heat of the fire will injure any portion of any tree.

(2) Fence required. During excavation, filling, construction or demolition operations, each tree or stand of trees shall be protected against damage to bark, roots and low-hanging branches with a fence enclosing the critical root zone (four (4) feet high, two (2) inch by four (4) inch posts; with double one (1) inch by four (4) inch rails, plastic construction area fencing, or 12-gauge two (2) inch by four (4) inch wire mesh). "Tree save area" signs shall be posted on all sides of the fenced area. All tree protection fencing shall be installed prior to any clearing, grubbing or grading. Tree protection must remain in functioning condition until the certificate of occupancy is issued. Failure to comply with and/or maintain approved tree protection measures may result in a stop work order issued by the Community Development Department.

(3) Compaction prohibited. All building materials, vehicles, construction equipment, dirt, debris or other objects likely to cause soil compaction or aboveground damage shall be kept outside the critical root zone. Where a limited amount of encroachment is unavoidable and is approved by the building official, the critical root zone shall first be mulched with a four (4) inch layer of processed pine bark or wood chips or a six (6) inch layer of pine straw.

(4) Grade changes prohibited. Grade changes prohibited. There shall be no raising or lowering of the ground level within the critical root zone. Stripping of topsoil in the critical root zone shall not be permitted. Where necessary the use of moderate fill is permitted only with prior installation of an aeration system approved by the building official. Deposition of sediment in the critical root zone shall be prevented by placement of sediment barriers, which shall be backed by two (2) inch by four (4) inch wire mesh.

(5) Ditches, trenches prohibited. No person shall excavate any ditch, tunnel or trench within the critical root zone. Where such encroachment is unavoidable and is approved by the building official, tunneling rather than trenching shall be used. For installation of underground irrigation, radial trenching may be permitted.

(6) Paving prohibited. No person shall pave with concrete, asphalt or other impervious material within the critical root zone.

History

The history line the source prints at the end of the section.

(Ord. No. 21-10, § 1, 6-22-21)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:lagrange/zoning/25c-10-38@2026-11-14-52edf2bca8