Ir al contenido
Georgia Commons
Menú

LaGrange · Ordenanza de zonificación

Title 25C - DEVELOPMENT AND PERMITTING / Chapter 25C-10 - BUFFERS, LANDSCAPE, AND TREES / Article III - TREE PRESERVATION

Sec. 25C-10-38. Standards for tree protection during construction.

Sobre este texto

  • As published by Municode, retrieved 2026-11-14
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

In the tree save area, protective measures shall be applied to the aboveground portion of a tree and to roots within the critical root zone, as follows:

(1) Damage prohibited. No person shall:

a. Cut, carve, transplant, or otherwise damage or remove any tree;

b. Attach any rope, wire, nails, advertising posters, or other contrivance to any trees;

c. Allow any gaseous, liquid or solid substance which is harmful to trees (such as concrete washout, fuels, lubricants, herbicides, paint, etc.) to come in contact with them; or

d. Set a fire or permit any fire to burn when such fire or the heat of the fire will injure any portion of any tree.

(2) Fence required. During excavation, filling, construction or demolition operations, each tree or stand of trees shall be protected against damage to bark, roots and low-hanging branches with a fence enclosing the critical root zone (four (4) feet high, two (2) inch by four (4) inch posts; with double one (1) inch by four (4) inch rails, plastic construction area fencing, or 12-gauge two (2) inch by four (4) inch wire mesh). "Tree save area" signs shall be posted on all sides of the fenced area. All tree protection fencing shall be installed prior to any clearing, grubbing or grading. Tree protection must remain in functioning condition until the certificate of occupancy is issued. Failure to comply with and/or maintain approved tree protection measures may result in a stop work order issued by the Community Development Department.

(3) Compaction prohibited. All building materials, vehicles, construction equipment, dirt, debris or other objects likely to cause soil compaction or aboveground damage shall be kept outside the critical root zone. Where a limited amount of encroachment is unavoidable and is approved by the building official, the critical root zone shall first be mulched with a four (4) inch layer of processed pine bark or wood chips or a six (6) inch layer of pine straw.

(4) Grade changes prohibited. Grade changes prohibited. There shall be no raising or lowering of the ground level within the critical root zone. Stripping of topsoil in the critical root zone shall not be permitted. Where necessary the use of moderate fill is permitted only with prior installation of an aeration system approved by the building official. Deposition of sediment in the critical root zone shall be prevented by placement of sediment barriers, which shall be backed by two (2) inch by four (4) inch wire mesh.

(5) Ditches, trenches prohibited. No person shall excavate any ditch, tunnel or trench within the critical root zone. Where such encroachment is unavoidable and is approved by the building official, tunneling rather than trenching shall be used. For installation of underground irrigation, radial trenching may be permitted.

(6) Paving prohibited. No person shall pave with concrete, asphalt or other impervious material within the critical root zone.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 21-10, § 1, 6-22-21)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:lagrange/zoning/25c-10-38@2026-11-14-52edf2bca8

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.