The following procedures must be completed before a building permit will be issued by the city building inspector for any construction project within the MCD.

(1) Pre-application conference. Prior to filing for a building permit with the inspections department, the applicant (developer) must confer with the city building inspector and the zoning administrator regarding the general character of the proposed construction project. The MCD Project Planning Guide outlining suggested building designs, roof lines, construction materials, site design elements, and ordinances affecting the scope of the proposed project will be given to the applicant (developer) at this time. This planning guide will assist in the development of the preliminary project design package.

(2) Preliminary project design package. The preliminary project design package must contain the following items:

a. Plats and topo of the construction area.

b. Site layout drawings including building location, curb cuts, ingress/egress, parking lot dimensions, green space, and stormwater containment.

c. Architectural overview.

(3) Architectural overview. The architectural overview should include conceptual drawings of the proposed building(s), accessory buildings, landscaping buffers, refuse receptacles, signage, and external lighting of the proposed project and shall be included with the submission of the preliminary project design package.

(4) Application conference. The applicant (developer) shall present the completed preliminary project design package for review at the application conference. After review (generally seven to ten days) the city building inspector shall confer with the applicant (developer) as to the cities finding regarding the proposed project.

Additional information may be requested by the city before the project is approved for a final building permit application package.

(5) Building permit application package. If the proposed project is found to be within the permitted uses of this article and in compliance with subsections (1), (2), and (3) of this section, then a written approval for a building permit application package will be issued to the applicant (developer) by the city building inspector. The requirements for a building permit application in the MCD is the same as outlined in sections 102-284 and 102-285, planned development mixed-use for a P-M application. The building inspector and zoning administrator shall outline the required information in that code section that must be included in the application package.

(6) Building permit. A building permit and notice to proceed will be issued to the applicant upon final approval of the building permit application package by the zoning administrator and city building inspector.

History

The history line the source prints at the end of the section.

(Ord. of 3-7-2011)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:lavonia/zoning/102-308@2026-11-11-90ad2343bb

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Lavonia Zoning Ordinance, Sec. 102-308. Plan review and approval procedures | Georgia Commons