Sec. 5.14. General.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Construction specifications for road subgrade, base and surface course. Construction specifications for roads shall be per Standard Specification, Construction of Roads and Bridges of the State of Georgia, latest edition and supplements. All references in the document meaning the state department of transportation or the state department of transportation engineer shall mean Leesburg and the Leesburg Manager of Development Services.
(b) Sampling and testing.
(1) Provide quality control testing during construction as necessary to assure the entire earthwork including all fill layers, subgrades, and bases meet specified requirements.
Remove and reconstruct, or otherwise correct work which falls below specified density or is outside other specified limits.
(2) Employ an independent testing laboratory to perform quality control testing during trenching and backfilling operations.
(3) The manager of development services may perform sampling, surveying, inspection or testing activity during construction for the city's use, but such activity does not relieve the contractor from his responsibility to achieve specified results.
(c) Quality control testing reports.
(1) After completing construction and prior to the closing of the approved permit, the contractor may be required to file copies of the quality control test results demonstrating compliance with these specifications with the manager of development services.
Which quality control tests results to be submitted shall be requested by the manager of development services at the time of application review. Such application review request period shall not limit the manager of development services from requiring additional tests during the construction process.
(2) At any time during the construction process, the manager of development services may request to review any quality control test results. The contractor shall provide all quality control test results.