A. Generally. Sidewalks shall be constructed within a single-family residential subdivisions on both sides of all streets within the public right-of-way. The Mountain Springs zoning district shall be exempt from the above sidewalk requirements upon provision of a Pedestrian Mobility Plan by the developer which may include a combination of sidewalks, paved walking trails, unpaved walking trails, hiking trails, bike paths, golf cart paths, and/or equestrian trails. The Pedestrian Mobility Plan shall be provided to the Community Development Director at the time of a final subdivision plat and must provide for a sidewalk, paved walking trail, unpaved walking trail, hiking trail, bike path, golf cart path, or equestrian trail within 300 feet of a property line of each residential lot. A distance of more than 300 feet from a residential lot to pedestrian mobility infrastructure shall be allowed based on topographic circumstances or site constraints.

B. Construction specifications. Sidewalks shall be 4 feet in width and 4 inches in thickness and shall be constructed of Portland cement concrete.

Sidewalks shall be installed no closer than 2 feet to the back of curb line and shall not be constructed over any underground gas, electric, communications, or water and sewer utilities.

Sidewalks and curbs, at street intersections, shall be designed to permit handicapped access (see construction standard detail for location of sidewalks). Construction specifications of the pedestrian mobility facilities within the Mountain Springs zoning district shall be exempt from the above provision and shall be as established by a Pedestrian Mobility Plan provided by the Mountain Springs developer.

C. Installation. Typically, sidewalks shall be installed by the builder before the issuance of a certificate of occupancy. However, all sidewalks are required to be complete throughout the subdivision (by the developer) before the end of the 2-year maintenance period. Broken curbing and sidewalk after this 2-year period will be repaired by the builder before the issuance of a certificate of occupancy. Installation scheduling for the pedestrian mobility facilities within the Mountain Springs zoning district shall be exempt from the above provision and shall be as established by a Pedestrian Mobility Plan provided by the Mountain Village developer.

History

The history line the source prints at the end of the section.

(Ord. of 07-16-2023(1), 7-16-2023)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:manchester/zoning/4.43@2026-11-11-cf4fd81bfd

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Manchester Zoning Ordinance, Section 4.43. Sidewalks | Georgia Commons