Section 4.44. Gas, electric and telecommunications utilities.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Responsibility. The subdivider shall make the necessary arrangements with the Manchester Gas Department, Georgia Power Department, and other appropriate utility companies for the installation of utilities to assure that all

lots have adequate gas, electrical and telecommunication services, including cable television.

B. Enforcement. The building and code enforcement department shall not issue any occupancy permits for structures in a subdivision or development until all necessary utilities have been installed.

C. Exemptions. The following specific facilities shall be exempt from the requirements of this chapter:

1. Poles used exclusively for street lighting.

2. Poles, overhead lines, and associated overhead structures owned by a utility company crossing over any portion of an area from which overhead wires are allowed.

3. Overhead lines attached to the exterior of a building by means of a bracket or similar device and extending from one location on the building, or to an adjacent building without crossing any street or right-of-way.

4. Radio antennae and associated structures and equipment used for furnishing communications service.

5. Service terminals and necessary padmounted electric transformer equipment installed above ground, used to distribute

communications service.

D. Electrical transformer substations and lift stations. Transformer substations and sewer lift stations may be required within subdivision developments to serve the proposed developments and a larger area. These facilities shall be fenced with a chain link security fence and shall

be landscaped with tree plantings and shrubs.

The utility company shall obtain an easement for these installations that shall be clearly indicated on the final plat.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:manchester/zoning/4.44@2026-11-11-6dc74e86ad

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Manchester Zoning Ordinance, Section 4.44. Gas, electric and telecommunications utilities | Georgia Commons