Section 6.02. Inspection procedures.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The subdivider is responsible for making requests for inspections before beginning any of the stages indicated below. No grading shall commence without an approved soil erosion and sedimentation control plan and a development permit. Soil erosion prevention measures shall be installed prior to grading as required by the Manchester Soil Erosion and Sedimentation Control Ordinance.

1. Inspection notification. The subdivider shall notify the building and code enforcement department at least 24 hours before any stage of construction begins. If

construction during any phase is stopped or delayed due to inclement weather or

other reasons, the subdivider shall notify the building and code enforcement department 24 hours before commencing construction activity again.

2. Clearing and grubbing. After providing the required notice to the building and

code enforcement department, clearing of the right-of-way may begin. All work is to be in accordance with section 4.24 of this ordinance.

3. Street grading. Following inspection and approval of the street clearing and grubbing by the development inspector, and street grade stakes have been set by the project's engineer, the contractor may

proceed with the grading of the streets.

All work is to be in accordance with section 4.24. Compaction tests shall be made as required by the city engineer to determine that the required 95 percent

maximum dry density is being achieved.

At least one test shall be made over each storm drain pipe when it has been covered with 18 inches of backfill material.

4. Subgrade compaction. Following the completion and approval of the street grading and installation of curb and gutter the contractor may proceed with the

preparation of the subgrade in accordance with section 4.24. Compaction tests shall be made at the direction of the city

engineer to determine that the required 100 percent maximum dry density is being achieved.

5. Curb and gutter. Following the installation of all proposed sanitary sewer and water lines and acceptance of the street grading the contractor may proceed with

the construction of the curb and gutter.

All work and materials shall be in accordance with section 4.24.

6. Base preparation. After the street subgrade has been inspected and approved, the contractor may proceed with the

construction of the street pavement base.

All work and materials shall be in accordance with section 4.24 and table 4-1 or table 4-2. Compaction tests shall be made as directed by the city to assure that the required 100 percent maximum

dry density has been achieved. Cores shall be taken as directed by the city to determine the constructed thickness of

the base course.

7. Paving. After the road base has been approved and accepted by the development inspector, the contractor may proceed with the construction of the asphaltic

concrete binder and/or surface courses.

All work and materials shall be in accordance with section 4.24 and table 4-1 and table 4-2 of this ordinance.

Compaction tests shall be made as directed by the city to assure that the required 98 percent maximum has been achieved.

8. Street core tests. Street core test results shall be submitted to the building and

code enforcement department prior to the recording of a final subdivision plat.

These cores shall be taken as directed by the development inspector immediately

upon completion of the surface course.

Refer to section 4.24.

9. Soil erosion and sedimentation control.

During all of the stages of inspection, soil erosion, and sedimentation control

measures shall be inspected. The subdivision shall be subject to soil erosion and sedimentation control inspection at any

other times determined necessary to assure compliance with the approved plan. The subdivider is responsible for continued maintenance of all soil erosion and sedimentation control measures as

required by the Manchester Soil Erosion and Sedimentation Control Ordinance.

10. Work stoppage. A stop work order may be issued at anytime if it is determined to be necessary due to failure of the

subdivider to comply with any of the requirements of this ordinance, the zoning ordinance or, the soil erosion and

sedimentation control ordinance. A stop work notice shall be posted on the site and the subdivider shall be notified in writing concerning the reasons for the stop work order. Any work that proceeds in violation of a stop order shall subject the subdivider to penalties as prescribed in section 8.03 of this ordinance.

11. Work delays. If construction during any phase of development is delayed due to

inclement weather or for other reasons, the subdivider shall notify the building and code enforcement department prior

to resuming construction activities.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:manchester/zoning/6.02@2026-11-11-2d15633751

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Manchester Zoning Ordinance, Section 6.02. Inspection procedures | Georgia Commons