(a) Setbacks.

(1) Road frontage setbacks. From public road rights-of-way, the following minimum setbacks shall apply, with required vegetative or architectural screening:

a. Major arterials, collectors, and designated corridor roads: 150 feet.

b. Local industrial access roads: 100 feet.

(2) Buffer standards. The following buffer requirements shall apply and shall be read in conjunction with the applicable buffer and screening requirements of the county zoning ordinance, with the more restrictive requirement controlling:

a. A minimum 250-foot-wide natural buffer shall be required along all property lines constituting the exterior boundary of the development unless a greater buffer is required under [subsection b. below].

b. Where adjacent to property zoned for residential or agricultural use, a minimum 500-foot-wide natural buffer shall be required. This requirement may be reduced to 250 feet if the applicant installs a planted berm that provides a minimum visual screen blocking the line of sight from the highest point at adjacent property lines and roads to the highest point of proposed structures.

c. Where adjacent to property zoned for compatible industrial or data center use, no buffer shall be required along that shared property line. A 50-foot setback from the property boundary shall still be necessary.

d. Along interstate highway frontage only, the buffer may be reduced to a minimum of 50 feet.

e. All required buffers shall remain undisturbed to the maximum extent practicable, except for necessary access points and utility crossings, which shall cross the buffer in as horizontal a manner as feasible.

f. Where existing vegetation is insufficient to provide effective screening, the buffer shall be planted to a condition that provides screening per the applicable landscaping standards of the county zoning ordinance.

g. Where a buffer reduction is proposed through use of a berm, a visual survey showing line of sight to the highest point of proposed structures from adjacent property lines and roads shall be submitted for review during the rezoning or special use process.

History

The history line the source prints at the end of the section.

(Ord. No. 26-001, 6-16-26)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:mcduffie-county/zoning/44-262@2026-09-15-bb39bb6cb0

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

McDuffie County Zoning Ordinance, Sec. 44-262. Setbacks and buffers | Georgia Commons