Sec. 44-291. Infrastructure impact study.

About this text

  • As published by Municode, current through 2026-09-15
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A power, water, and broadband impact study shall be submitted with any site plan or special use application for a data center, including the following:

(1) Projected utility demand at build-out.

(2) Proposed phasing.

(3) Identification of necessary off-site infrastructure improvements or extensions.

(4) Documentation from each affected utility provider confirming service capacity and applicable efficiency requirements.

History

The history line the source prints at the end of the section.

(Ord. No. 26-001, 6-16-26)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:mcduffie-county/zoning/44-291@2026-09-15-43a0bc5aee

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.