Sec. 44-291. Infrastructure impact study.

Sobre este texto

  • As published by Municode, current through 2026-09-15
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A power, water, and broadband impact study shall be submitted with any site plan or special use application for a data center, including the following:

(1) Projected utility demand at build-out.

(2) Proposed phasing.

(3) Identification of necessary off-site infrastructure improvements or extensions.

(4) Documentation from each affected utility provider confirming service capacity and applicable efficiency requirements.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. No. 26-001, 6-16-26)

Leer este código donde se publica (Municode) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:mcduffie-county/zoning/44-291@2026-09-15-43a0bc5aee

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

McDuffie County Zoning Ordinance, Sec. 44-291. Infrastructure impact study | Georgia Commons