(a) Utility easements. When it is found to be necessary and desirable to locate public utility lines in other than street rights-of-way, easements must be shown on the plat for utility purposes. Such easements must not be less than 20 feet wide and, where possible, must be centered on rear or side lot lines. All utility easements shall comply with the minimum standards as specified by the utility provider.

(b) Water supply systems.

(1) Public water system. If available, the proposed development must be connected to a public water supply and water mains, fire hydrants and stub connections must be shown on the construction plans.

(2) Private water supply system. If public water supply is not available, the developer may install a private water system developed according to plans and specifications shown on the approved construction plans and approved by the city.

(c) Sanitary sewer disposal systems.

(1) Public sewage system. If available, the proposed development must be connected to a public sewage system and sewage mains and stub connections must be shown on the construction plans. If a lift station is required the developer must pay the cost of the station.

(2) Individual sewage system. When a public sewage system is not available the developer must carefully consider the capability and suitability of the general area of the property to support an individual sewage system (septic tanks). Such proposed sewage system must be approved by the Lamar County Health Department. The city must consider the recommendation of the Lamar County Health Department regarding any proposed private sewage systems in approval of the construction plans.

History

The history line the source prints at the end of the section.

(Ord. No. 2009-3, § 1(408), 11-16-2009)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:milner/zoning/118-467@2026-11-11-d0ec5c9191

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Milner Zoning Ordinance, Sec. 118-467. Development standards for utility installations | Georgia Commons