(3) Residential subdivision developer's responsibility. Developers shall install sidewalks and curb ramps on abutting external streets, "passive" recreation areas, common area and open space prior to the approval of the final plat. Sidewalks on "active" recreation area lots shall be installed prior to issuance of a certificate of occupancy.

(4) Homebuilder responsibility. Homebuilders shall install sidewalks, and curb ramps not required to be installed by developers, on residential lots prior to release of the certificate of occupancy for a home.

(5) Non-residential and non-subdivision projects. Sidewalks shall be installed on new internal streets (both sides including cul-de-sac and "eyebrow" turnarounds) and on abutting external streets (abutting side) by the lot owner or developer prior to the issuance of a certificate of occupancy.

(6) Performance surety. Performance surety for sidewalks and ramps not yet installed must be approved by the public works director. The surety shall be in an amount acceptable to the city.

(7) Escrow alternative. The cost of sidewalk installation may be set aside in escrow with the Public Works Department if proposed road improvements by the city may impact the location of a sidewalk or if the sidewalk cannot be constructed due to topographic or utility constraints. Costs shall be set by the city and are subject to include construction, acquisition, and engineering costs for sidewalk projects within the city.

(c) Sidewalk design and construction standards. Sidewalks shall be constructed in accordance with the requirements of this section. The Public Works Director is authorized to grant modifications upon specific application due to topographic or drainage difficulty.

(1) Width. Sidewalks shall be at least five feet wide on new internal subdivision streets and on abutting external streets.

(2) Setback. Sidewalks shall be located at least two feet from the back of curb. The area between the curb and the sidewalk shall consist of grass or landscaping and shall be consistent with the requirements of this UDO. Where no curb exists, or if road improvements are proposed for installation by the city, sidewalks, including appropriate storm-water infrastructure, shall be constructed in a location acceptable to the city.

(3) Cross slope. Sidewalks shall be constructed with a cross slope of 0.25 inch per foot.

Sidewalks shall maintain this cross slope at driveway crossings or transition the sidewalk to a driveway with ramps and detectable warnings.

(4) Material. Class "B" concrete (as defined by Georgia Department of Transportation) with a minimum strength of 3,000 PSI at 28 days.

(5) Final stabilization. Disturbed areas resulting from sidewalk construction shall be backfilled, stabilized, and grassed or landscaped.

(6) Georgia Department of Transportation or Gwinnett County controlled roads. Sidewalks located in the right-of-way of roads under the jurisdiction of the Georgia Department of Transportation shall be constructed in accordance with Georgia Department of Transportation or Gwinnett County design and construction standards.

(7) Sidewalk curb ramp design and construction standards. Intersection radius curb ramps shall be provided at street intersections. Straight ramps may be provided at intersections of curbed driveways and at streets without sidewalks. Curb ramps shall meet the requirements of the Americans with Disabilities Act.

(8) Damage repair. Damage to roads, sidewalks, curbs, and ramps caused by construction or development activity shall be repaired at no cost to the city within 30 days or prior to issuance of a certificate of occupancy, whichever is earlier.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-47. Traffic control devices.

(a) Traffic control signs. Street signs, traffic control signs, and devices such as striping and signalization, shall be provided through payment of fees to the Public Works Department for the installation thereof.

(b) Street name signs. Public street name signs shall have a green background with white legends mounted on channelized posts. Private street name signs shall have a blue background with white legends mounted on channelized posts. Alternate post material is required in the city's historic districts. Alternate post material shall be subject to the review and approval of the Public Works Department. The posts and signs will be furnished and installed by the city at all street intersections. The developer (or homeowners association in the event an alternate signpost is chosen at a later date) shall pay the city costs.

(c) Traffic signals and signs. All traffic signals and signs shall conform to the Manual on Uniform Traffic Control Devices (no decorative traffic control devices will be allowed).

(d) Striping requirements. All newly constructed streets having four or more lanes (including auxiliary lanes) and existing streets being widened with one or more additional lanes shall be striped or the payment of said striping costs shall be required from the developer by the Public Works Department prior to the approval of development conformance for the project. Striping shall be accomplished with paint meeting Georgia Department of Transportation standards conforming to the Manual on Uniform Traffic Control Devices.

(e) Payment of fees. Payment for materials and installation of street name and traffic control signs in new developments shall be required by the Public Works Department prior to the approval of the final plat for new subdivision streets and the approval of the development conformance for all other developments.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-48. Traffic calming devices.

(a) Subdivision streets shall be designed in accordance with the City of Norcross Traffic Calming Guide.

(b) The traffic-calming plan is subject to review and approval by the Public Works Department. The Public Works Director may grant modifications.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-49. Private streets and alleys.

(a) Private streets and alleys permitted.

(1) Application for approval of private street and/or alleys shall be considered by the City Council during the rezoning or special use permit process, if necessary.

Otherwise, the City Council shall take up the use of private streets and alleys during the preliminary plat process and before a land disturbance permit is issued.

Notwithstanding other provisions of the UDO, the City Council may impose conditions on the approval of private streets and alleys to ensure the health, safety, and welfare of the general public and to mitigate potential problems with private streets.

(2) Alleys intended to serve as private access routes in the rear of buildings shall be permitted, constructed, and maintained as private driveways, and in substantial conformance with the UDO design guidelines. Application for approval of such private alleys shall be considered by the Mayor and Council in the same method as approval of private streets in subsection (1) above.

(b) General provisions.

(1) It shall be unlawful for any person, firm, or corporation to construct a new private street or alley, or alter an existing private street or alley, or to cause the same to be done without first obtaining a development permit, for such construction or alteration, from the department.

a. All private streets shall be constructed to the roadway construction standards for public streets as required by the UDO and contained herein. All alleys shall be designed and constructed as private driveways as required by the UDO. No permit for a private street or alley shall be issued unless the proposed roadway improvements are in conformity with the standards and requirements for public streets and the applicable provisions of the UDO.

b. For setback purposes, front setbacks shall be measured as if the streets were public streets, or as approved by individual variances. Rear setbacks of lots adjacent to alleys shall be a minimum of five feet measured from the rear property line of such lot.

c. The subdivider/developer shall comply with the Department of Fire and Emergency Services general order for security gate access if a gated development is proposed.

d. All provisions of the UDO regarding roadways, water lines, sewer lines, stormwater facilities and their appurtenance, including the design, submittal of plans, required improvements, etc., shall apply to all developments with private streets or alleys approved pursuant to this section.

e. The subdivider/developer shall comply with the standards and requirements of the county's department of water resources for the installation of water and sanitary sewer mains within private developments/subdivisions.

f. The subdivider/developer shall establish a mandatory property owners association, with bylaws and/or covenants which shall include the following:

1. Mandatory membership of all purchasers of lots therein and their successors.

2. Responsibility for maintenance, insurance, and taxes.

3. Equitable sharing of the cost of maintenance.

4. Authority to place liens on the real property of members who fail to pay their dues or assessments.

g. No final plat or development permit involving any private street shall be approved unless said final plat or development permit conforms to the requirements of this section.

(c) Street names and address assignments for private streets.

(1) Proposed names for private streets shall follow the same rules as for public streets.

a. The subdivider of land involving a private street shall install street signs with the street name and designation "private," as approved by the Public Works Department.

b. Address assignments will be in accordance with this UDO.

(d) Easements for private streets or alleys.

(1) Easements for private streets and/or shall be designated on preliminary and final plats as general purpose public access and utility easements, along with the name of said street. Said easement shall at minimum be of the same width as that required for the right-of-way of a public street as shown on the long range road classification map for the type of public street (local, collector, etc.) most closely resembling the proposed private street.

(2) In cases where alleys are intended to serve as private service or access route, either with or without utility easement, for more than two properties, then the alleys shall have a minimum easement width of 20 feet and shall be designated on final plats as private access and utility easement, as applicable, and on its own discrete parcel to be dedicated to a private property association.

a. Easements for private streets and alleys shall not be included in any calculation of minimum lot size as established by this UDO.

b. In the cases of private streets where roadway improvements are not required (i.e. exemption plat, minor subdivision), the general purpose public access and utility easement for the private street shall be shown in a manner on the plat such that each lot fronting the private street extends to the centerline of the private street. No lot shall be permitted to be divided by the general purpose public access and utility easement required and established for a private street.

c. In the cases of private streets where roadway improvements are required, the general purpose public access and utility easement for a private street shall be drawn as its own discrete parcel to be dedicated to a private homeowners association (i.e. not shown to be a part of any lot).

(e) Maintenance.

(1) The city shall not maintain, repair, resurface, rebuild, or otherwise improve streets, signs, drainage improvements, or any other appurtenances within general purpose public access and utility easements established for private streets or alleys.

a. The county assumes full responsibility for the repair and maintenance of the water and/or sanitary sewer mains and appurtenances, and any areas disturbed by repair or maintenance efforts will be restored to as near to its original condition as is feasible. Permanent repairs to the streets and/or alleys shall be made by the homeowners associations or other entity having maintenance responsibility for the development. Driveways and sidewalks will be repaved, sodded or landscape areas will be graded, smoothed, reseeded or resodded where appropriate. Maintenance responsibility by the county for individual sanitary sewer stubs shall extend to the end of the standard six-inch stub, and to the water meter for individual water lines.

b. A private maintenance covenant recorded with the clerk of the county superior court shall be required for any private street, alley and other improvements within general purpose public access and utility easements established for private streets and alleys. The covenant shall set out the distribution of expenses, remedies for non-compliance with the terms of the agreement, rights to the use of easements, and other pertinent considerations. The covenant shall specifically include the following terms:

1. The covenant shall establish minimum annual assessments in an amount adequate to defray costs of ordinary maintenance and procedures for approval of additional needed assessments. The covenant shall also specify that the funds from such assessments will be held by a homeowners or property owners association in cases of a subdivision fronting on a private street or containing a private alley.

2. The covenant shall specify that the property owners association shall be responsible for the maintenance and repair of the stormwater drainage system and all common areas within the development.

3. The covenant shall include a periodic maintenance schedule.

4. The covenant for maintenance shall be enforceable by any property owner served by the private street or alley.

5. The covenant shall establish a formula for assessing maintenance and repair costs equitably to property owners served by the private street or alley.

6. The covenant shall run with the land.

c. The City Council may, at its discretion, as a condition of approving private streets, require a performance bond and/or maintenance bond be submitted by the subdivider and held by a homeowners or property owners association, or the Council may require that the subdivider pay an amount of money as recommended by the Public Works Director into an escrow account or other suitable account for the construction, maintenance and repair of private streets and stormwater management improvements, to be drawn from by the homeowners or property owners association as the need may arise.

(f) Specifications for final plats involving private streets. No final plat involving a private street shall be approved by the Community Development Department for recording unless and until Mayor and Council have approved the use of private streets and it shall contain the following on the face of the plat:

(1) Deed book and page reference to the recorded covenant required in subsection (e), maintenance, as listed above.

a. "City of Norcross has no responsibility to build, improve, maintain, or otherwise service the private streets, drainage improvements, and other appurtenances contained within the general public purpose access and utility easement or easements for private streets shown on this plat."

b. "Grant of Easement. The general purpose public access and utility easement(s) shown on this plat for private street(s) is hereby granted and said grant of rights shall be liberally construed to provide all necessary authority to the City, and to public or private utility companies serving the subdivision, for the installation and maintenance of utilities, including, but not limited to electric lines, gas lines, telephone lines, water lines, sewer lines, cable television lines, and fiber optic cables, together with the right to trim interfering trees and brush, together with a perpetual right of ingress and egress for installation, maintenance, and replacement of such lines.

Signature of Property Owner Date "

c. "Certificate of Dedication. All water and sewer lines installed within the general purpose public access and utility easement(s) shown on this plat for private street(s) are hereby dedicated to Gwinnett County."

(g) Requirement for purchaser's acknowledgement of responsibilities for private street and/or alley.

(1) Prior to the sale or as a condition of the closing of a real estate transaction involving any lot served by a private street or alley in the city, the purchaser of said lot shall execute a notarized purchaser's acknowledgement of private street and/or alley construction and drainage maintenance responsibilities set forth below. A copy of the purchaser's acknowledgement shall be retained by the subdivider or seller and shall be required to be submitted as a condition of a building permit for a principal building on said lot:

"Purchaser's Acknowledgement of Private Street and/or Alley and Drainage Maintenance Responsibility."

(I) (We) have read the Declaration of Covenant which pertains to the lot that is the subject of this real estate transaction (insert address or attach legal description). (I) (We) understand that the Declaration of Covenant applies to the lot that (I am) (we are) purchasing and requires (me) (us) to provide a specified percentage or amount of the financing for the construction and maintenance of any private street (and/or alleys) and drainage facilities serving the lot which (I am) (we are) purchasing, and that owners of other lots in this plat may sue and recover for those costs which this covenant requires (me) (us) to pay, plus their damages resulting from (my) (our) refusal to contribute, plus reasonable attorney's fees. (I) (we) further understand that the City has no obligation to assist with the maintenance and improvement of the private street or alley, drainage facilities, and other appurtenances within the general purpose public access and utility easement for the private road serving the lot in question. (I) (we) understand that a copy of this purchaser's acknowledgement shall be required as a condition of the issuance of a building permit for a principal building on the lot (I am) (we are) purchasing.

Purchaser Date Purchaser Date (Ord. No. 06-2025, § I, 9-2-2025)

DIVISION 7. DEVELOPMENT CONFORMANCE, SURETIES, AND MAINTENANCE

Sec. 401-50. Development conformance, sureties and maintenance, in general.

(a) Prerequisite to final plat, certificate of completion, or certificate of occupancy. The submittal and acceptance of a certificate of development conformance shall be a prerequisite to the approval of a final plat or issuance of a certificate of occupancy or certificate of completion for any project, or portion thereof, included in a land disturbance permit, except for single-family and two-family structures. The approval shall reflect the certification by the owner, being the subdivider or developer, that all site work and construction has been accomplished according to the terms of the approved plans and permits, and that all improvements intended for maintenance, supervision and/or dedication to the public are in compliance with appropriate standards, regulations, codes, and ordinances. Such approval shall be revoked in cases of fraud or whenever unauthorized changes are made to the site without the benefit of required permits.

(b) Submission requirements. Upon completion of the project as authorized for construction by the land disturbance permit, the subdivider/developer, shall file the following items with the city engineer:

(1) A certificate of development conformance in a form as required by the city engineer, accompanied by an executed development performance and maintenance agreement and related surety bonds, or other surety forms, as appropriate and acceptable to the director.

(2) Record drawings of all stormwater management facilities.

(3) Modifications to the limits of the 100-year floodplain (if any).

(4) An "as-built" hydrology study for the project with the actual parameters from the record drawing of the stormwater management facilities.

(5) A record drawing of the sanitary sewer facilities shall also be prepared and submitted to the county for review and approval. If the owner is a corporation or LLC, the documents shall be executed by the president, or vice-president, or LLC manager/member as appropriate and be affixed by a corporate seal, and either the corporate secretary shall attest to the signature and affix the corporate seal, or a certificate of corporate resolution shall also be submitted.

(c) Certificate of development conformance approval process.

(1) Following final inspection and approval of all record drawings, the City Engineer shall require an executed certificate of development conformance from the subdivider/ developer.

(2) Final approval by the City Engineer shall not be shown on the certificate of development conformance until all requirements of these and other applicable regulations have been met.

(3) Once the City Engineer has approved the certificate of development conformance and after all maintenance and performance bonds are released, the Community Development Director or designee shall certify by signature on the original of the certificate of development conformance that all of the requirements of this UDO and the conditions of zoning approval have been met, and that all other affected departments have approved the development or final plat.

(4) For developments with private streets, all required improvements and installations must be completed in accordance to the applicable rules and regulations of the city.

(d) Project closeout and continuing maintenance.

(1) Development performance and maintenance agreement. Based on the approved certificate of development conformance, the owner shall file a development performance and maintenance agreement with the department, along with any required certificate of corporate resolution and performance or maintenance surety, as a prerequisite to the approval of a final plat or issuance of a certificate of occupancy for any part of a project included in the development permit, except for single-family and two-family residential structures. The development performance and maintenance agreement shall be in a form as required by the City Engineer, and shall include the following:

a. Maintenance surety shall be filed to warrant to the city that all newly completed street improvements including but not limited to street pavement, curbing, sidewalks, water and sewer lines, appurtenances, stormwater facilities, wall(s), berms, and required landscaping within the right-of-way shall be maintained in compliance with the standards and rules and regulations of the city. Such surety shall:

b. Be conditioned upon the faithful maintenance by the principal, being the subdivider, owner or developer of the public streets and drainage facilities within public streets or easements, in compliance with this UDO and all other applicable rules and regulations within a specified time, not less than 18 months;

c. Be payable to, and for the indemnification of the city;

d. Be an amount equal to 50 percent of the cost of construction of the work required, as calculated based on yearly contract prices or city contracts, where applicable;

e. Be with a surety company entered and licensed to do business in the state; and

f. Be in a form acceptable to the City Engineer or to the City Attorney.

(2) Performance surety. A performance surety shall be filed to warrant to the city that all improvements and installations required for the land disturbance permit or final plat approval, but not yet completed, shall:

a. Be conditioned upon the faithful performance by the principal, being the subdivider, owner or developer of all work required to complete all improvements and installation for the development, or approved portion thereof, in compliance with this UDO and all other rules and regulations within a specified time, not to exceed 12 months, unless an extension for additional time is granted;

b. Be payable to, and for the indemnification of, the city;

c. Be in an amount equal to the cost of construction of the work required plus an additional 50 percent of said costs, as calculated based on the yearly contract prices or city contracts, where available;

d. Be with surety by a company entered and licensed to do business in the state;

and

e. Be in a form acceptable to the City Engineer or the City Attorney.

(3) Continuing maintenance. The surety principal, being the subdivider, owner, or developer, shall be responsible for maintaining the public streets and drainage facilities within public rights-of-way or easements for the surety period after the date of approval of the certificate of development conformance. Repairs shall be made for any deficiencies identified within the surety period or the bonds shall be called to complete same.

(4) Indemnification. Indemnification of the city against any and all liability for damages arising as a result of errors or omissions in the design or construction of the development for a period of ten years. If liability is subsequently assigned or transferred to a successor in title or other person, a copy of such legal instrument shall be filed with the Clerk to Superior Court.

(5) Transfer of land ownership during the maintenance and/or performance agreement time period. No person, firm, partnership, association, corporation, estate, trust, developer, subdivider or any other owner or agent shall transfer title of any property by reference to, exhibition of, or any other use of any map or plat illustrating the subdivision of land of which there are active maintenance or performance bonds without first providing to the city, as beneficiary, a newly executed development performance and maintenance agreement from the new owner or developer. All required performance or maintenance sureties acceptable to the city shall accompany the new agreement as deemed necessary.

(e) Maintenance and performance surety.

(1) The maintenance surety and the performance surety, required from the subdivider, owner/developer or the contractor employed by the owner/developer, may be in the form of cash deposited with the city, or a surety bond, or letter of credit from a bank or other financial institution in a form acceptable to the City Engineer or City Attorney.

a. The surety bond shall be issued by a surety company authorized by law to do business in the state pursuant to a current certificate of authority to transact surety business by the Commissioner of Insurance.

b. The letter of credit shall be an irrevocable letter of credit issued by a bank or savings and loan association, as defined in O.C.G.A. § 7-1-4.

c. The cash escrow shall be in the form of cashier's check issued to the city by a bank or savings and loan, as defined in O.C.G.A. § 7-1-4.

(2) The performance surety and maintenance surety shall, in all cases, be provided in an amount as required in [this section] as applicable. All cost estimates which form the basis of the bond value shall be as prepared by or acceptable to the City Engineer.

(3) The maintenance bond period shall not be less than 18 months from the date of approval of the certificate of development conformance for the installation of the public streets and drainage facilities improvements within the right-of-way unless an extension for an additional 12 months is requested by the subdivider or developer and granted by the City Engineer. The performance bond period of application shall not exceed 12 months unless an extension of an additional 12 calendar months has been requested by the subdivider or developer and granted by the City Engineer.

(4) If a period of 18 months elapses from the commencement of the maintenance period for any subdivision and defects, noncompliance, or violations still exist to the extent that the subdivision has not been accepted by the city, the city is authorized to withhold issuance of any and all permits or to refuse inspections to any subdivider/person on the project in dispute or any other project in which the subdivider/person may have a financial interest, or both, who violates or fails to comply with this UDO.

(f) Maintenance agreement for water and sanitary sewer installation. An owner and developer agreement required from the subdivider, owner/developer or the contractor employed by the owner/developer, for sanitary sewer installation and water main installation is required by the county department of water resources. The owner and/or developer agree that they or their contractor will maintain the installation for a period of one year from the date of final approval by correcting all defects or deficiencies in material and workmanship. The owner and/or developer further agree that the warranty period shall be extended an additional four years when the defects are a direct result of the installation of nonspecified materials or the application of non-specified construction practices or methods.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-51. Warranty, surety and maintenance for trees and landscape materials.

(a) Requirement. Upon final installation of new trees, shrubs or other landscape material planted to meet the requirements of this UDO, and following acceptance by the City Arborist in accordance with the procedures set forth herein, the owner shall either provide proof of warranty or post a maintenance bond or other acceptable surety, warranting the new trees, shrubs, or landscape material for a period of no less than one year. This section shall not apply to individual residential lot trees or street trees.

(b) Inspection.

(1) The City Arborist shall perform an inspection of the plantings and landscape materials required by this UDO prior to expiration of the one-year warranty or maintenance period. The owner shall be notified of any replacements or restoration that must be made to maintain compliance with this UDO.

(2) Required landscape material found to be dead or near death shall be replaced prior to release by the City Arborist of the warranty or maintenance surety. In no case shall replacement be delayed greater than 30 days from notification unless a performance bond is posted with the city.

(c) Performance surety.

(1) Compliance prior to certificate of occupancy or final plat approval. In the event that new trees proposed to be planted to achieve the tree density standard as set forth in the tree regulations contained herein, or other trees or landscape material required to be planted as set forth in this chapter, are not installed upon application for a certificate of occupancy or final plat approval as appropriate to the project, then a performance bond or other acceptable surety shall be posted with the city in accordance with the performance bonding requirements and provisions of this

UDO.

(d) Compliance upon permit completion or expiration. Properties where a permit is issued to conduct land-disturbing activities that do not require the issuance of a certificate of occupancy or the approval of a final plat, or said activities as authorized are completed or the permit expires, shall comply with the tree density standard of article V of chapter 200, and as follows:

(1) Clearing, clearing and grubbing, or grading only permits.

a. Replacement trees proposed to be planted to achieve the tree density standard of article V of chapter 200 which are not planted upon completion or prior to expiration of a clearing, clearing, and grubbing, or grading permit, shall be planted within 30 days of the completion or expiration of said permit unless a performance bond is posted with the department.

(2) Development permits.

a. Replacement trees proposed to be planted to achieve the tree density standard of article V of chapter 200 which are not planted upon expiration, as opposed to completion, of a development permit shall be planted within 30 days of expiration of said permit unless a performance bond is posted with the department.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-52. Reserved.

DIVISION 8. INSPECTIONS

Sec. 401-53. Initiation of development activities.

(a) Initial activities required.

(1) Following the issuance of any permit authorizing clearing, grubbing, grading or development of a site, a preconstruction conference shall be mandatory for all phases of construction and conducted before erosion and sediment control installation or any land disturbance takes place. Utility construction permits and retaining wall permits shall be issued prior to scheduling a pre-construction conference.

(2) The development and ES&PC inspectors shall be contacted no less than two business days prior to scheduled start of construction to schedule the mandatory pre-construction conference. Attendees to include owner's representative, engineer, site work contractors, and utility contractors.

(3) Site development related activities prior to this required pre-construction conference shall be a violation of the permitted scope of work. A notice of violation and a stop work order may be issued on site and all work must stop until the preconstruction conference has been completed and all work prior to the preLAND DEVELOPMENT § 401-53 construction conference inspected for compliance with the rules, appropriate standards, regulations, codes, and ordinances, then, if warranted corrections to illegal work completed before the work associated with the approved permit can proceed.

(b) Erosion and sediment control measures. Required preliminary erosion and sediment control measures must be installed in the field per the developer's authorized plans and inspected by the ES&PC inspector prior to actual grading or removal of vegetation. All erosion and sediment control measures shall be in place per state and city regulations as soon as or in conjunction with the commencement of activities and in continual coordination with the progress of the project and as per the authorized erosion, sedimentation and pollution control plan.

(1) Preliminary erosion and sedimentation control measures must be installed and operational prior to major grading operations.

(2) Buffer areas required to be undisturbed per this UDO, conditions of zoning approval, per the Metropolitan River Protection Act, or any other applicable ordinance, or regulation shall be designated by approved protective tree fencing and shall be inspected by the ES&PC inspector prior to the commencement of any clearing, grubbing, grading, or development activities.

(c) Tree protection areas. Prior to the initiation of land-disturbing activities and throughout the clearing, grubbing and grading process the following must be accomplished for a designated tree protection area in accordance with any approved buffer and landscape plan or tree protection plan for the property, as set forth in this UDO:

(1) For trees which are not to be disturbed or removed, required protective fencing, and tree protection area signage shall be established and maintained in place. These barriers must be maintained throughout the land disturbance process and shall not be removed until the final landscaping phase has begun.

(2) The tree protection areas shall not be encroached for any reason or be used for storage of earth and other materials resulting from or used during the development process.

(3) Construction site activities such as parking, materials storage, concrete washout, burning, etc., shall be arranged to prevent disturbance or damage within or to the tree protection areas.

(c) Stabilization for erosion control. If for any reason a lapse of 14 days occurs after initial land clearing, grubbing, and grading, or development activities have commenced, the developer and/or builder shall be responsible for re-establishing temporary vegetation cover of the site. If the lapse in construction activity extends beyond 30 days, permanent vegetative measures are required by Manual for Erosion and Sediment Control in Georgia and under the direction of the ES&PC inspector.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-54. Development inspections.

(a) Development inspections. The developer or contractor shall request all inspections at least two business days prior to commencement of any development or construction activity for each of the phases below as authorized by any permit for site work or development. Inspections shall be made by the development inspector and passed prior to authorization for continuation of further activity or proceeding into new phases. Newly installed underground infrastructure including but not limited to; stormwater pipes and water and sewer lines must be installed per design standards and inspected prior to cover up of any portion.

The following items refer to construction activities that require approval before the next phase of construction occurs:

(1) Development of the site. Clearing, grubbing, grading or development of the site or any portion included under the permit.

(2) Grading. Installation of slope and grade stakes, erosion controls and detention facilities.

(3) Road construction. The grading of areas for placement of the new roadway(s) shall be staked by the proper responsible parties as per the authorized plan.

(4) Installation of storm drainage pipe, detention, or other storm water facilities.

Installation of storm drainage pipe, detention, or other stormwater management facilities require a pre-construction conference before commencement.

(5) Installation of sanitary sewer and appurtenances and/or water main extensions and appurtenances. Notification shall be made by the authorized utility contractor after obtaining a utility construction permit from the county.

(6) Curbing of roadways. Inspection shall be requested before the forms have been set (if used). Roadway width will be spot checked by string line between curb stakes.

The developer or representative must be present for all "string line" related field inspections.

(7) Sub-base or subgrade of streets. After compaction, the subgrade shall be stringlined for depth and crown. The subgrade shall pass a roll test with no defects, to the satisfaction of the development inspector.

(8) Street base. The base will be string-lined for depth and crown and shall pass a roll test with no movement to the satisfaction of the development inspector.

(9) Paving. A development inspector. shall be on site during the paving process to check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material will be spot-checked, and evidence provided of quantity, thickness, and mix of installation.

(10) Water line. Shall install curb and gutter prior to installing the water lines.

(b) Responsibility for quality and design. The completion of inspections by city officials or employees and authorization for work continuation shall not transfer responsibility for the quality of the work performed or materials used from the contractor or developer, nor imply or transfer acceptance of responsibility for project design or engineering from the professional corporation or individual under whose hand or supervision the plans were prepared.

(Ord. No. 06-2025, § I, 9-2-2025)

DIVISION 9. DEVELOPMENT DESIGN STANDARDS

Sec. 401-55. Incorporation of standard drawings.

(a) Department to maintain standard drawings on file. The Public Works Department shall maintain on file for consultation and distribution a set of standard drawings, which may be updated administratively from time to time, illustrating details of construction and design of streets, stormwater management facilities, site improvements and other elements related to the development of land in accordance with this UDO and under the jurisdiction of the Public Works Department.

(b) Standard drawings to illustrate standards. The standard drawings shall illustrate minimum acceptable standards for land development activities authorized under this UDO but shall not supersede more restrictive prudent design requirements or good engineering practices as applied to specific situations on a case-by-case basis.

(c) Standard drawings incorporated as part of the unified development ordinance. The standard drawings shall be treated as though a part of this UDO for application to the minimum standards for design and construction of improvements required herein and subject to the modification and waiver provisions of this UDO.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-56. Incorporation of the Norcross Parks, Greenspaces and Trails Master Plan.

All developments shall be reviewed for conformance with the guidelines and policies of the Norcross Parks, Greenspaces and Trails Master Plan.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-57. Design of lots.

(a) Building setback conformity. Building setback lines shall conform to the minimum setback requirements of chapter 200 of this UDO except where a greater distance is required by another jurisdiction.

(b) Lots.

(1) Lots to conform to the chapter 200 of this UDO. Lots shall conform to requirements of this UDO. No lot shall be created that is of a lesser dimension than that required to meet the standards established in chapter 200 of this UDO, unless a variance is granted. However, this provision shall not apply when a conforming lot is made non-conforming as a result of public acquisition.

(2) Subdivisions shall be designed to minimize direct lot access to major thoroughfares.

a. Double frontage and reverse frontage lots shall be required for subdivisions along major thoroughfares where internal access can be provided. A noaccess easement of at least ten feet in width, across which there shall be no right of access, shall be provided along the line of lots abutting such a traffic artery. When located along a major thoroughfare, the no-access easement shall be planted and/or screened as required by chapter 200 of this UDO, when the backs of homes are oriented toward the street.

b. No-access easement planting or other screening treatments which are required by the UDO, or as a condition of zoning, shall be installed by the developer at no cost to the city.

(3) Flag lots prohibited. No plat shall be approved on which is shown a flag lot, as defined in this UDO.

(4) Side lot lines. Side lot lines generally should be at right angles (90 degrees) to straight street lines or radial to curved street lines as much as practical. Side lot lines should be radial to the radius points of all cul-de-sacs. Variations of more than ten degrees shall require modification approval from the Community Development Department and shall be approved when appropriate to the reasonable design pattern of the subdivision and efficient use of the land relative to topographic conditions.

(5) The City Engineer may require notation that a house location plan (HLP) is required to be approved prior to issuance of a building permit on certain lots when particular care in locating the house or other improvements will be necessary. Such lots include, but are not limited to:

a. A lot which presents particular or unusual difficulties for a builder to meet minimum required building setbacks;

b. A lot upon which is located an easement of unusual configuration;

c. A lot containing floodplain;

d. A lot upon which is located all or a part of a stormwater management facility;

e. A lot upon which is located a buffer which was required by chapter 200 of this UDO or as a condition of zoning approval;

f. All duplex lots; and

g. All lots within, or partially within, the Chattahoochee River Corridor, or containing a River Corridor Tributary Buffer Zone.

(6) The City Engineer may require notation that a residential drainage plan (RDP) is required to be approved prior to issuance of a building permit on certain lots where additional (site specific) engineering will be necessary to properly grade the lot or locate the building or other improvements. Such lots include, but are not limited to:

a. A lot containing floodplain where fill or other encroachment into the floodplain is planned or reasonably expected.

b. A lot containing severe topographic features intersecting the building site.

c. A lot containing a drainage easement with a pipe discharge or other facilities, or flow characteristics which may adversely affect the location of a building or other site improvement.

(7) The City Engineer may require notation that a residential drainage study (RDS) is required to be approved prior to issuance of a building permit on certain lots where particular attention to site grading will be necessary, but formal engineering is not needed. Such an RDS is conducted in the field where the effect of the site grading must be accomplished with adequate care so as not to create a drainage problem on neighboring property.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-58. Exceptions to design of lots.

(a) Signage and landscape features. The creation of an unbuildable lot in a proposed subdivision for the exclusive purpose of subdivision identification signage or subdivision entrance landscape features is authorized only under the following circumstances (modification applications from the circumstances of this exception shall not be accepted):

(1) The lot shall be located at an entrance to the subdivision as an "island" in the right-of-way of a local or minor collector street;

(2) A mandatory property owner's association shall be required for the subdivision for ownership and maintenance of the lot as common area;

(3) Right-of-way of a minimum width of 6 feet from back of curb shall be provided adjacent to the perimeter of the lot; and

(4) Landscape plantings within the right-of-way shall not extend more than 2.5 feet above the street grade.

(b) Stormwater management and utility facilities. The creation of an unbuildable lot for the exclusive purpose of providing and maintaining a stormwater management or utility facility is authorized, provided that such a lot meets all applicable requirements set forth in this UDO and under the jurisdiction of the city.

(c) Open space. The creation of an unbuildable lot for the exclusive purpose of providing and maintaining open space or conservation space for the enjoyment of the community is authorized.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-59. Access and right-of-way.

(a) Project access improvements.

(1) Every developer of land shall provide the project access improvements included in this UDO as shall be appropriate to serve the project, in accordance with these regulations and other pertinent codes, ordinances, and regulations of the city. Said improvements and associated lands shall be provided at no cost to the city, and shall be dedicated or otherwise transferred, as required, to the public in perpetuity and without covenant or reservation, except as otherwise provided herein.

(2) For all business and industrial developments fronting a state highway, no land disturbance or building permits shall be issued until the approval of the Georgia Department of Transportation (DOT) has been obtained by the applicant on the entrances and exits, curb radii, drainage and other matters that are the appropriate concern of Georgia DOT.

(b) Access.

(1) Large parcels to provide future street access. When land is subdivided into larger parcels than ordinary building lots, such parcels shall be arranged and designed so as to allow for the opening of future streets and to provide access to those areas not presently served by streets.

(2) Landlocking of adjacent property prohibited. No development shall be designed so as to completely eliminate street access to adjoining parcels of land. Every development shall be designed to facilitate access to adjoining properties which are developed or anticipated to be developed in a manner substantially similar to the subject property. Locations of inter-parcel access shall be as required by and subject to the approval of the department.

(3) Private streets to be constructed pursuant to roadway construction standards.

Private streets as may be approved under the provisions of this UDO shall be constructed to the street construction standards of the city, as contained in this

UDO.

(c) Vehicular access easements. Vehicular access easements may be provided from a public street indirectly via easement subject to the following:

(1) The easement shall be in a location and the access driveway shall have a width and alignment acceptable to the Public Works Department and the county department of fire and emergency services.

(2) The access easement serves a single-family residence on a lot which is otherwise a buildable lot of record, and which is sharing a common driveway with more than one other single-family residence.

(3) The sharing of a common driveway (or alley) by multiple residences.

(4) The access easement was lawfully established as such under the code, ordinances, or regulations of the city prior to the adoption of this UDO.

(5) The access easement coincides with a private roadway or alley approved under the code, ordinances, or regulations of the city.

(d) Dedication of street right-of-way. Right-of-way for all public streets, existing and proposed, shall be dedicated in accordance with the street classifications as shown on the officially adopted City of Norcross Long Range Road Classification Map or as required by City Public Works Director or designee.

(e) Greenway access dedication of easement and construction requirements. Access, dedication of easement and/or construction of greenway trails shall be provided in accordance with the prioritized greenway network map of the most currently approved Norcross Parks, Greenspaces and Trails Master Plan, as follows:

(1) Greenway access. Unless a waiver is granted by the City Council or an exception is provided below, all developments that adjoin designated greenways as shown on the prioritized greenway network map of the Norcross Parks, Greenspaces and Trails Master Plan shall provide at least one multi-use path to the programmed or existing greenway. The multi-use path shall be paved or constructed with materials approved by the county, and the route segment shall be a minimum of ten feet in width. Multi-use path locations shall be reviewed and approved by the Department of Community Services.

(2) Greenway construction and easement dedication.

a. Within flood plains and stream buffers, greenway easements shall be dedicated and constructed to provide public access to trails as shown on the prioritized greenway network map of the Norcross Parks, Greenspaces and Trails Master Plan. Greenways shall be located so that the route is feasible for both construction and long-term maintenance. The specific location of the greenway shall be verified on the ground before approval and project release of the development. The amount of land required for greenway construction shall not exceed five percent of the land within the development excluding greenways located within a standard street right-of-way.

b. For all other locations, as established by the prioritized greenway network map of the Norcross Parks, Greenspaces and Trails Master Plan, dedication of easement shall be required for greenways lying outside of any floodplain or stream buffer or shall be reserved either for public access greenway easement, dedication and construction, or other terms negotiated with the county.

c. In coordination with the Public Works Department and Community Development and Planning Department, greenways with public access may be allowed to substitute for required sidewalks if the greenway alignment coincides with locations intended to be served by sidewalks.

(3) Limitations.

a. Single-family residential zoning districts. The dedication or construction of greenways in single-family residential zoning districts is required for subdivisions that involve the creation of a new street. Existing single-family lots are exempt from greenway easement dedication and construction.

b. All other zoning districts. Construction of the greenway is required in the following situations:

1. Whenever there is new development;

2. Whenever alterations to existing development are 25 percent or greater of the total improvements on the site; or

3. Whenever new streets are constructed.

(4) The construction and dedication of greenways shall be in accordance with the approved Norcross Parks, Greenspaces and Trails Master Plan design standards.

Any deviation or modification of the construction standards contained herein shall be subject to article IV, procedures, of chapter 100.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-60. Design of blocks.

(a) Length, width, and shape. The lengths, widths, and shapes of blocks shall be determined with regard to:

(1) Provision of adequate building sites suitable to the special needs of the type of use contemplated;

(2) Applicable zoning requirements as to maximum length of street, lot size and dimensions;

(3) Needs for convenient access, circulation, control, and safety of street traffic; and

(4) Limitations and opportunities of topography.

(b) Pedestrian access. In blocks over 500 feet long, an alley, sidewalks, pedestrian way, or pedestrian access easement, shall be provided through the block to other streets within the development.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-61. Residential amenities, open space.

(a) Residential amenities and common areas.

(1) In subdivisions where land is required for open space use in accordance with this UDO, such land shall be deeded to a qualified property owners or homeowner's association, or other legal entity incorporated under the laws of the state upon the approval of the final plat containing said land. Said land shall be deeded with a restriction that the land shall be used exclusively for recreational purposes and shall be made available to all residents of the subdivision project on an equal basis. The qualified property association shall provide for the mandatory membership of all of the owners within the subdivision, and shall be responsible for the perpetuation, maintenance and function of the recreation areas and uses or facilities therein. The association shall have the authority and duty to assess its members for such maintenance and improvements as set forth in the instrument creating the association. All covenants shall be recorded simultaneously with the final subdivision plat.

(2) In multifamily rental or condominium projects, land provided for open space in accordance with these requirements shall be held in the ownership of the owner of the project or homeowner's association.

(3) The city may lease or sell land reserved for public parks to a qualified property owners association with a deed restriction that the land be used exclusively for open space, common area or public recreational purposes in perpetuity. The organization of a qualified property owners association and its adequate financing for the discharge of its responsibilities shall be assured through acceptable private deed covenants running with the land or other such documents as approved by the Mayor and City Council.

(4) In a residential development, where usable open space is to be developed, permits for any amenities must be issued prior to 25 percent of the proposed residential units receiving a certificate of occupancy. All amenity areas must be completed prior to 75 percent of the proposed residential units receiving a certificate of occupancy.

(Ord. No. 06-2025, § I, 9-2-2025) Sec. 401-62. Additional requirements for stormwater facilities.

(a) Prior to or concurrent with the recording of a final plat for a subdivision, or issuance of a certificate of occupancy for a non-subdivision project, the developer, shall provide acceptable surety such as a bond or letter of credit, as determined by the City Engineer, providing for the stormwater management facility(ies) for a period of not less than 18 months. At the end of 18 months, the city may require the surety to be renewed due to anticipated improvements caused by such concerns as future construction activity within the project limits in the drainage basin. A renewed surety may be required up to a total maximum of ten years. The surety for a facility shall be renewed during the ten-year period until:

(1) The surface water drainage area within the project has undergone final stabilization and all planned site construction activity has been completed.

(2) All stormwater runoff in the surface water drainage area within the project is coming from undisturbed or stabilized areas.

(3) All stormwater facilities and infrastructure construction have been completed and permanent vegetation is established.

(4) If a temporary stormwater management facility is still in use at the end of the site construction, then the surety shall remain in place until the accumulation of acreage of undeveloped lots, lots with no completed permanent structure and no final stabilization, within the surface water drainage area within the project is less than ten percent of the total area of the common development draining to the facility.

(5) Two months prior to surety release, the permanent stormwater management facility shall be installed and cleaned out, as necessary. A new record survey, drawing and certification showing that the volume of the facility is equal to or greater than the volume shown in the record survey, drawing and certification when the facility was approved shall be submitted. Documentation demonstrating the required testing outlined in the Gwinnett County Stormwater Management Manual for the proposed stormwater BMP shall also be provided. As an alternative, a new record survey, drawing and certification showing that the facility complies with this UDO as specified in section 800-20.7 shall be submitted. If deficiencies are found, the developer shall be required to update the stormwater BMP to comply with the approved development plans.

(Ord. No. 06-2025, § I, 9-2-2025)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:norcross/zoning/whole@2026-11-11-c7924ef273

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Norcross Zoning Ordinance (the whole text) (Part 3 of 3) | Georgia Commons