Oglethorpe County · Zoning Ordinance
Article XI - Project Design and Construction Standards / 1119 - Installation of streets and utilities.
Section 1119.01. Permit for utility installation.
About this text
- As posted on the county's website, retrieved 2026-11-23
This Section governs the installation of telephone lines, gas lines, water lines, sanitary sewer lines, gray‐water reuse lines, electrical lines, fuel lines, steam lines, T.V. cables, open storm drainage, storm sewers and other utilities within county‐maintained road or street rights‐of‐ way.
a) Application for permit; when required.
1) New facilities or extensions of existing facilities within county‐maintained road or street rights‐of‐way shall require a written application and a permit issued by the appropriate County department.
2) Service lines and maintenance and repair of existing facilities shall not require a permit unless a pavement cut is required, but all other requirements of this Development Code shall apply to said activities, whereapplicable.
3) Emergency cuts without a permit may be made when required. Such cuts shall be followed by a written application or report to the appropriate governing authority within 2 working days thereafter. Repairs to the pavement and disturbed soil and all other applicable requirements of this Development Code shall apply to such emergency cuts.
b) Application for permit;requirements.
1) Application for permit for Utility Facility Installation shall be made to the appropriate governing authority in the jurisdiction providing service. A copy of said permit shall be submitted with the application submitted to Oglethorpe County to install or extend utility facilities within a county maintained road or street right‐of‐way.
2) In the case of water lines and sanitary sewer lines, a record of approval from the appropriate governing authority in the jurisdiction providing service shall accompany a permit application.
3) In those cases where a Georgia Department of Transportation application and permit is required, a copy of the Department of Transportation application and permit along with the expected date of work commencement shall be provided to the Oglethorpe County Board of Commissioners and said copy shall satisfy the application and permit requirements herein.
c) Installation and constructionrequirements.
1) The installation of said facility as authorized shall be subject to the inspection, direction and control of the Oglethorpe County Engineer who shall be notified before work is commenced.
Such notification shall include the date and time of the commencement of the construction and/or installation and location ofsame.
2) The work shall be performed in a workmanlike manner and all installations shall be done by the utility owner in such a way as to leave free flows in drainage ditches, pipes, culverts or other surface water drainage facilities of the roadway or its connections. No part of any installation shall be attached to any portion of a bridge, culvert or other structure of the roadway without special authorization of the County Engineer after detailed information is furnished as may berequired.
3) Where breaking of pavement has been approved, a six‐inch concrete slab will be poured over the backfilled trench and will rest on undisturbed soil. If the pavement is asphalt, the surface of the 6‐inch, concrete slab will be 1½ inches below the sur‐ face of the abutting pavement. The 1½‐inch section will be paved with Type E, F, or H plant asphalt. The finished surface will be smooth and flush with abutting pavement.
4) Underground piping and wiring will be installed and located in accordance with Section 1117. Where underground piping parallels the roadway the excavated ditch edge nearest the pavement will be at least 8 feet from the pavement edge, unless otherwise authorized herein.
5) The facility trench shall be backfilled carefully after the facility has been installed, in accordance with the standard practice for installing culverts and minor structures. In crossing roadways the backfill will be made in 6‐inch layers and each layer firmly compacted.
Where roadway grass is disturbed, satisfactory replacement will be accomplished including adequate seeding of newgrass.
6) The full and entire expense and cost of the facility installation and maintenance shall be borne by the utility owner and the utility owner shall make necessary arrangements for traffic over said point during such work as may be directed by the County Engineer. The utility owner shall place the necessary barricades, warning signs, signals, lights and, if necessary, watchmen for the protection of the traveling public, and further agrees by the acceptance of the permit to keep and hold Oglethorpe County harmless from any and all damages caused by negligence on the part of the utility owner, its agents, servants, officers or employees, or contractors, engaged in doing said work, or any injuries or damages suffered by anyone as a result thereof.
d) Future relocations at utility expense. In case the Board of Commissioners should in the future decide to widen and/or relocate the existing road, the Oglethorpe County Commissioners reserve the right to require the utility owner to take up and relay such sections of the facility within the right‐of‐way as may be necessary to take up and relay from an engineering standpoint due to such widening and/or relocating; the taking up and relaying to be at the expense of the utility owner. This work shall be completed within 60 working days after notification by the Board of Commissioners or within such other time as may be approved in writing by the County Engineer or designated representative of the Board of Commissioners.