A. Required Approvals. The placement of wireless communications facilities and towers shall meet the following approval requirements:

1. Installation of New Antenna. The installation of new antenna(s) on existing towers, including legal non-conforming towers, and existing alternative structures (such as water towers, buildings, or church steeples) may be approved by the zoning administrator subject to all requirements of this section. Any new antenna that will add either ten percent or 25 feet, whichever is less, above the highest point of any existing tower or alternative structure shall be subject to the provisions of this chapter for the installation of new towers as described below.

2. Installation of a New Tower. The installation of any new tower(s) shall be reviewed as a special use by the planning and zoning board and the city council.

3. Installation of New Accessory Structures. The installation of new accessory structure(s), such as equipment buildings, to support the installation of additional antennas on existing towers or alternative structures may be approved by the zoning administrator.

B. Removal. Any tower unused or left abandoned for 12 consecutive months shall be removed by the property owner at his/her expense. Regardless of the tower ownership, the property owner shall be responsible for removal. Upon the request of the zoning administrator, the operator of any facility to which this article applies shall provide documentation of the use of that facility for the purpose of verifying any abandonment.

C. Interference with Public Safety Facilities. No new wireless communications facilities or tower shall result in any interference with public safety telecommunications.

D. Required Documentation for all Facilities. In addition to the requirements provided in Section 15-3 for the receipt of special use approval and/or a zoning compliance permit, applications for new towers, new antenna, and new related facilities shall include the following. Where the equipment is mounted on an existing building, the comparable information for that structure shall be provided:

1. Engineer's Report. A report from a professional engineer licensed in the State of Georgia that:

a. Describes the height and design of any new tower and/or antenna including a crosssection, latitude, longitude, and elevation;

b. Describes or updates (in the case of new antenna) the tower's capacity, including the type and number of antenna it can accommodate;

c. Certifies compliance of the construction specifications with all applicable building codes (including but not limited to, the foundation for the tower, anchors for the guy wires if used, co-location, and strength requirements for natural forces; ice, wind, earth movements, etc.);

d. Certifies that the facility will not interfere with established public safety telecommunication facilities; and

e. Includes the engineer's seal and registration number.

2. Letter of Intent. A letter of intent committing the tower owner, property owner, antenna owners, and their successors to allow the shared use of the tower.

3. Proof of Compliance. Copies of any required approvals from the Federal Communications Commission (FCC), Federal Aviation Administration (FAA) and all other appropriate state and federal agencies.

4. Removal Affidavit. A letter committing all parties, including the property owner and his/her successors, to remove the tower and all related accessory structures, fences, landscaping, and equipment if the tower is abandoned (unused for a period of 12 consecutive months). The removal affidavit shall be recorded in the Office of the Fulton County Clerk of Superior Court, with a copy of the recorded affidavit provided to the zoning administrator.

E. Determination of New Tower Need. Any proposal for a new telecommunications tower shall only be approved if the applicant submits verification from a professional engineer licensed in the State of Georgia that the antenna(s) planned for the proposed tower cannot be accommodated on any existing or approved towers or other structures within a two mile radius of the proposed tower location due to one or more of the following reasons:

1. Inadequate Structural Capacity. The antenna(s) would exceed the structural capacity of the existing or approved tower or other structure.

2. Interference. The antennas would cause interference impacting the usability of other existing or planned equipment at the tower site.

3. Inadequate Height. The existing or approved towers or structures within the search radius cannot accommodate the planned equipment at the height necessary.

4. Land Availability. Additional land area is not available (when necessary).

F. Design Requirements for new Towers and Related Facilities. All telecommunications facilities shall meet the following design requirements:

1. Lighting. Tower lighting shall only be as required for safety or security reasons or as required by the FAA or other federal or state authority. All ground level security lighting shall be oriented inward so as not to project onto surrounding properties, and shall have 90 degree cut-off luminaries (shielded downlighting).

2. Co-location. All telecommunication towers shall be designed, and engineered structurally, electrically and in all other respects to accommodate both the applicant's equipment and at least one additional user for every 50 feet in total tower height in excess of 75 feet.

a. Each additional user shall be assumed to have an antenna loading equal to that of the initial user.

b. Towers must be designed to allow for rearrangement of antennas and to accept antennas mounted at varying heights.

1. Height. All towers and antenna shall conform to all FAA tall structure requirements.

The maximum height of all accessory structures shall be 15 feet.

2. Signs. Signs for all telecommunications facilities shall be permitted up to a total of four square feet per user.

G. Site Requirements for new Towers and Related Facilities. All telecommunications facilities shall meet the following site requirements:

1. Vehicular Access. Vehicle access drives may be gravel or paved and shall be located within an access easement that is a minimum of 20 feet in width. Any portion of the entrance located in a public right-of-way shall meet the applicable public street or road design, construction, and pavement requirements.

2. Site Area. The lot (or lease area) where the tower is located shall be large enough to accommodate all future anticipated accessory structures needed by future antenna users. The size of the site shall also be of sufficient area to allow the location of one additional tower and associated support facilities.

a. The arrangement of the initial tower and the topography of the site shall be considered in determining the sufficiency of the site area.

b. At a minimum, the width and depth of the tower site shall be a distance equal to the tower height. The tower shall be placed within the property so that it is no closer to any lot line than one-half the tower height.

c. All tower supporting and stabilizing wires shall be located within the site area.

3. Setback. The required setbacks for the tower and related facilities shall be as follows:

a. Side and Rear Setback. The minimum side and rear setback for all facilities, including the security fence, shall be 25 feet.

b. Front Setback. The minimum front setback for all facilities shall be as specified by this ordinance for the zoning district in which it is located. No part of a wireless telecommunications facility, including the security fence, and any required guide wires or bracing shall be permitted in any required front setback.

c. Additional Setback from Residential Zoning Districts. No facility shall be placed closer than one and one-half times the total height of the tower or 200 feet to any property included in any residential zoning district, whichever is greater.

d. Additional Landscaping. Landscape screening in addition to the requirements of this chapter may be provided in the setback area.

4. Encroachment. No part of any telecommunications facility nor associated lines, cables, equipment, wires or braces shall at any time extend across or over any part of a public right-of-way, sidewalk, or property line.

5. Fencing. An eight-foot-high security fence shall completely surround the tower and accessory equipment building site. Barbed wire, concertina wire or sharpened stakes shall be at least six feet above grade.

a. An area ten feet in width shall remain outside of the fence for the purpose of providing the landscape screening described in subsection H, below.

b. In the single-family and multiple family zoning districts the required security fence enclosing the facility shall be 100 percent opaque and of wood, brick, or stone construction.

Opaque, eight-foot-tall gates shall be provided for access. In no instance shall the use of chain link fencing or gates with screening inserts be considered as opaque.

H. Landscape Screening. Evergreen buffer plantings shall be located and maintained around the outermost perimeter of the security fence of all wireless communications facilities. The landscape plan for the site shall provide plants in a number and design to provide a screen of the fence, all equipment and the base of the tower, as determined by the planning and zoning board and the city council.

a. If evergreen shrubs are used they shall be planted a maximum of five feet apart on center.

b. If evergreen trees are used they shall be planted a maximum of ten feet apart on center.

History

The history line the source prints at the end of the section.

(Ord. No. 2013-02, § 6, 4-1-2013)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:palmetto/zoning/15-41@2026-11-11-8ee697cdba

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Palmetto Zoning Ordinance, Sec. 15-41. Wireless communication facilities and towers | Georgia Commons