Appendix A - ZONING / Article XXII - SOLAR PANEL USAGE

Section 22.04. Decommissioning.

About this text

  • As published by Municode, current through 2022-12-19
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) The owner of a solar electrical system is required to notify the City of Sylvester immediately upon cessation or the discontinuation of the operation. The solar electrical system shall be perceived to be discontinued or abandoned if no electricity is generated by such system for a period of 12 continuous months.

(b) The solar electrical system owner shall then have 12 months in which to dismantle and remove the system including all solar related equipment or apparatuses related thereto included but not limited to buildings, cabling, electrical components, roads, foundations and other facilities from the property. If the owner fails to dismantle and/or remove the solar electrical system within the established time frames, the municipality may complete the decommissioning at the owner's expense.

History

The history line the source prints at the end of the section.

(Ord. No. 2015-07, § 2, 8-17-2015)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:sylvester/zoning/22.04@2022-12-19-b9c7b7dd49

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Sylvester Zoning Ordinance, Section 22.04. Decommissioning | Georgia Commons