1. Any underground utilities shall be installed with the surface having the same compaction as that of the paved way and marked on the plat to indicate the location.

2. The facilities for underground utilities, such as sewer, water and gas, including sewer and water laterals to each lot line when laid in streets, shall be in place prior to final surfacing of streets. All facilities for utilities shall, where possible, be placed in easements provided for that purpose in the subdivision, if public utilities are available.

3. Streetlights are required along subdivision streets and shall be installed according to city department standards.

4. All public utility services are required to be underground in all proposed subdivisions, excluding minor subdivisions.

5. All underground utilities will be installed according to city department standards.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:sylvester/zoning/402.6@2022-12-19-de0de1f092

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.