12.6.1. General.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) The administrator may administratively approve the uses set forth in section 12.5 of this article as provided by this section 12.6. All such uses shall comply with requirements set forth in this article and all other applicable codes and ordinances.
(b) The administrator shall respond to each application within forty-five (45) days of its receipt by either approving, approving with conditions, or denying the application. One 45-day extension of this review period may be exercised by the administrator if such additional time is deemed necessary to adequately assess the request. If the administrator fails to respond to the applicant within a maximum of ninety (90) days, the application shall be deemed to be approved.
(c) As part of any administrative approval, the administrator may administratively reduce setback requirements by up to ten (10) percent to compensate for irregularly shaped lots or parcels.
(d) Any decision by the administrator that results in the denial of a request to place, construct, or modify a telecommunications facility shall be in writing and supported by substantial evidence. In addition to the requirements set forth in subsection 12.6.4 for uses allowed by administrative approval, the administrator shall consider the applicable factors set forth in this article, to include subsection 12.7.5, in acting upon an application for administrative approval.
12.6.2 Application; contents; fee. All applications for administrative approval of a permit shall be submitted to the administrator. Each application shall contain as a part thereof detailed plans and specifications as set forth in section 12.5. An application for administrative approval of a permit shall not be accepted for processing without the information required in section 12.5 of this article. An application fee shall be charged by the administrator in an amount stated in section 12.10 of this article.
12.6.3 Co-location of antennas required. Applicants for the erection of a tower or placement of an antenna shall be required to co-locate upon an existing tower or alternative tower structure. An exception to co-location shall only be made if the applicant adequately demonstrates that an existing tower suitable for co-location does not exist in the geographic antenna placement area, and that no suitable alternative tower structure is available as set forth in subsection 12.4.3.
12.6.4 Uses allowed by administrative approval. The following uses may be approved by the administrator after conducting an administrative review:
(a) If it is adequately demonstrated that antenna co-location, as required in subsection 12.6.3 above, is not possible for a given geographic antenna placement area, construction of a new tower up to a height of three hundred (300) feet, including the placement of additional buildings or other supporting equipment used in connection with said tower or antenna, may be permitted in the following zoning districts:
(i) Agricultural (A-1);
(ii) Agricultural-Residential (AR-1); and (iii) Industrial (I-1);
Provided, however, that all structures shall meet the setback, screening and buffer requirements contained herein, together with such additional conditions which may be reasonably imposed by the administrator to minimize the adverse effects of such placement on surrounding properties.
(b) So long as the addition of said antenna adds no more than ten (10) feet to the height of the existing alternative tower structure:
(i) Installation of an antenna on an existing alternative tower structure in any zoning district, and further including the placement of additional structures or other supporting equipment used in connection with said antenna, provided that if such installation is proposed on an existing alternative tower structure located in zoning districts R-1 through R-4, the applicant shall be required to (1) place all additional structures or other supporting equipment within the existing tower compound, and (2) meet such additional conditions which may be reasonably imposed by the administrator to minimize the adverse effects of such placement on surrounding properties; or
(ii) Installation of an antenna on an existing county owned alternative tower structure in any zoning district, provided a lease or similar agreement authorizing the antenna has been approved by the governing authority.
(c) So long as the addition of said antenna adds no more than ten (10) feet to the height of the existing tower:
(i) Installation of an antenna on an existing tower of any height in any zoning district, and further including the placement of additional structures or other supporting equipment used in connection with said antenna, provided that if such installation is proposed on an existing tower located in zoning districts R-1 through R-4, the applicant shall be required to (1) place all additional structures or other supporting equipment within the existing tower compound, and (2) meet such additional conditions which may be reasonably imposed by the administrator to minimize the adverse effects of such placement on surrounding properties, or
(ii) Installation of an antenna on an existing tower located on property owned, leased or otherwise controlled by the county in any zoning district, and further including the placement of additional buildings or other supporting equipment used in connection with said antenna, provided a lease or similar agreement authorizing the tower has been approved by the governing authority.
(d) Construction of a new tower up to a height of three hundred (300) feet, including the placement of additional buildings or other supporting equipment used in connection with said tower or antenna, if placed upon property owned, leased or otherwise controlled by the county in any zoning district except R-1 through R-4, providing a lease or similar agreement authorizing the tower has been approved by the governing authority.
12.6.5 Public notice/appeal. At least fifteen (15) days prior to the issuance of a permit for the construction of a tower or antenna as an administratively approved use, except for co-location permits, the administrator shall cause a sign to be conspicuously posted on the property and the publication of a public notice in the newspaper in which sheriff's advertisements appear. Said public notice shall state the nature of the application, height of the proposed structure, street address of the proposed location, or other identifying information necessary to inform the public of the proposed location. The expense of the public notice shall be borne by the applicant.
If during the public notice period, a written objection to the permit application is filed, the validity of the application and all pertinent documentation shall be determined by the governing authority. Said objection must make reference to the specific section of the article which the objector contends is not met and provide supporting documentation therefor. The objection shall be placed on the first available agenda of a regularly scheduled meeting of the governing authority following the expiration of the 15-day appeal period. The governing authority shall dispense with the objection by either:
(a) A determination that the application is valid and meets all applicable criteria of this article, which shall result in the issuance of a permit as set forth herein.
(b) A determination that the application does not satisfy all applicable criteria of this article.
Applications so found must, as a result, be processed through the conditional use permit process set forth in section 12.7 contained herein.
(c) Review of the decision of the governing authority shall be made within thirty (30) days by writ of certiorari to the Superior Court of Liberty County, Georgia.
12.6.6 Appeal of administrative determination. If a permit application for a tower as an administratively permitted use is determined by the administrator to not meet all applicable criteria of this article, the applicant may appeal the determination of the administrator to the governing authority in accordance with sections 7.1 and 7.2 of the zoning ordinance of Liberty County, Georgia. The governing authority shall dispense with the appeal by either:
(a) A determination that the application is valid and meets all applicable criteria of this article, which shall result in the issuance of a permit as set forth herein.
(b) A determination that the application does not satisfy all applicable criteria of this article.
Applications which do not satisfy all applicable criteria must, as a result, be processed through the conditional use permit process set forth in section 12.7 contained herein.
(c) Review of the decision of the governing authority shall be made within thirty (30) days by writ of certiorari to the Superior Court of Liberty County.
History
(Ord. No. 2000-002, § I, 10-3-2000)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.