Sec. 22-98. Inspections.
About this text
- As published by Municode, retrieved 2026-11-23
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Existing buildings. Before issuing a permit, the building official may examine or cause to be examined any building or electrical, gas, mechanical or plumbing system for which an application has been received for a permit to enlarge, alter, repair, move, demolish, install or change the occupancy. He shall inspect all buildings, structures and electrical, gas, mechanical and plumbing systems from time to time during and upon completion of the work for which a permit was issued. He shall make a record of every such examination and inspection and of all violations of the technical codes.
(b) Manufacturers and fabricators. When deemed necessary by the building official, he shall make or cause to be made an inspection of materials or assemblies at the point of manufacture or fabrication. A record shall be made of every such examination and inspection and of all violations of the technical codes.
(c) Use of private inspection services. The building official may make or cause to be made the inspections required by subsection (f) of this section. He may accept reports of inspectors of recognized inspection services provided that after investigation he is satisfied as to their qualifications and reliability. A certificate called for by any provision of the technical codes shall not be based on such reports unless the certificate is in writing and certified by a responsible officer of such service.
(d) Periodic and final inspections. The building official shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required and a final inspection shall be made of every building, structure and electrical, gas, mechanical or plumbing system upon completion, prior to the issuance of the certificate of occupancy or completion.
(e) Posting of permit. Work requiring a permit shall not commence until the permit holder or his agent posts the permit card in a conspicuous place on the premises. The permit shall be protected from the weather and located in such position as to permit the building official or representative to conveniently make the required entries thereon. This permit card shall be maintained in such position by the permit holder until the certificate of occupancy or completion is issued by the building official.
(f) Required inspections. The building official, upon notification from the permit holder or his agent, shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or his agent of any violations which must be corrected in order to comply with the technical code:
(1) Building inspections.
a. Foundation inspection. To be made after trenches are excavated and forms erected, after the foundation walls are erected and before the backfill is placed.
b. Slab inspection. To be made after trenches are excavated, forms are erected, plumbing lines are backfilled, gravel is in place and the vapor barrier is in place.
c. Frame inspection. To be made after the roof and all framing, fire blocking and bracing are in place, all concealed wiring and all pipes, chimneys, ducts, vents and three-quarter siding are complete.
d. Final inspection. To be made after the building is completed and ready for occupancy.
(2) Electrical inspections.
a. Temporary power pole inspection. To be made after the pole is in place.
b. Underground inspection. To be made after trenches or ditches are excavated and conduit or cable is installed and before any backfill is put in place.
c. Rough-in inspection. To be made after the roof, framing, fire blocking, threequarter siding and bracing is in place and prior to the installation of wall or ceiling membranes.
d. Permanent power inspection. To be made after all required electrical fixtures are in place and properly connected or protected and the meter base is set and properly secured to the structure.
e. Final inspection. To be made after the building is complete, all required electrical fixtures are in place and properly connected or protected and the structure is ready for occupancy.
(3) Plumbing inspections.
a. Underground inspection. To be made after trenches or ditches are excavated and piping installed and before any backfill is put in place.
b. Rough-in inspection. To be made after the roof, framing, fire blocking, threequarter siding and bracing is in place and all soil, waste and vent piping is complete and prior to the installation of wall or ceiling membranes.
c. Final inspection. To be made after the building is complete, all plumbing fixtures are in place and properly connected and the structure is ready for occupancy.
d. Required tests. See section 417 of the Standard Plumbing Code for required tests.
(4) Mechanical inspections.
a. Underground inspection. To be made after trenches or ditches are excavated and underground ducts and fuel piping are installed and before any backfill is put in place.
b. Rough-in inspection. To be made after the roof, framing, fire blocking, threequarter siding and bracing are in place and all ducting and other concealed components are complete and prior to the installation of wall or ceiling membranes.
c. Final inspection. To be made after the building is complete, the mechanical system is in place and properly connected and the structure is ready for occupancy.
(5) Gas inspections.
a. Rough piping inspection. To be made after all new piping authorized by the permit has been installed and before any such piping has been covered or concealed or any fixtures or gas appliances have been connected.
b. Final piping inspection. To be made after all piping authorized by the permit has been installed and after all portions which are to be concealed by plastering or otherwise have been so concealed and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test.
c. Final inspection. To be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes, to ensure compliance with all the requirements of this article and to ensure that the installation and construction of the gas system is in accordance with reviewed plans.
(6) Energy inspections.
a. Frame inspection. To be made before the exterior wall insulation is concealed by wall board to check installation of exterior wall insulation and to inspect that all holes and cracks through the structure envelope have been sealed in an appropriate manner so as to restrict air passage.
b. Final inspection. To be made after the building is completed and ready for occupancy, to verify installation and R-value of ceiling and floor insulation and to verify correct SEER ratings on appliances.
(g) Written release. Work shall not be done on any part of a building, structure or electrical, gas, mechanical or plumbing system beyond the point indicated in each successive inspection without first obtaining a written release from the building official. Such written release shall be given only after an inspection has been made of each successive step in the construction or installation as indicated for each of the inspections described in this section.
(h) Concealed work. Reinforcing steel, structural frame, insulation or plumbing, mechanical or electrical system work on any part of any building or structure shall not be covered or concealed without first obtaining a release from the building official.
(i) Application of plaster used for fire protection. In all buildings where plaster is used for fire protection purposes, the permit holder or his agent shall notify the building official after all lathing and backing is in place. Plaster shall not be applied until the release from the building official has been received.
History
(Ord. of 11-25-1997(2), att. A, § 3.8)