Bartow County · Code of Ordinances
Chapter 18 - BUILDING CODE / Article II - BUILDING CODE / Division 5 - PERMITS
Sec. 18-166. Permit decision.
About this text
- As published by Municode, current through 2026-09-02
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
The building official shall act upon an application for a permit without unreasonable or unnecessary delay, within 30 days from the submission of an application deemed complete.
If the building official is satisfied that the work described in an application for a permit and the contract documents filed therewith conform to the requirements of the standard building codes and other pertinent laws and ordinances, he shall issue a permit to the applicant.
History
(Ord. of 1-3-2007(1))
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.