Sec. 18-166. Permit decision.

About this text

  • As published by Municode, current through 2026-09-02
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The building official shall act upon an application for a permit without unreasonable or unnecessary delay, within 30 days from the submission of an application deemed complete.

If the building official is satisfied that the work described in an application for a permit and the contract documents filed therewith conform to the requirements of the standard building codes and other pertinent laws and ordinances, he shall issue a permit to the applicant.

History

The history line the source prints at the end of the section.

(Ord. of 1-3-2007(1))

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bartow-county/code/18-166@2026-09-02-1a08031bb5

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Bartow County Code of Ordinances, Sec. 18-166. Permit decision | Georgia Commons