Sec. 22-105. Approval or denial notification.

About this text

  • As published by Municode, current through 2025-05-06
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

If, on or before the 11th day as described in 2(b), an application is deemed complete, the county shall approve or deny an application within ten calendar days unless a joint meeting between the applicant and Carroll County is deemed as necessary.

(1) If a joint meeting is deemed necessary, the joint meeting must occur within 15 calendars days of notification of completion and the joint meeting shall include:

a. Where applicant is going to conduct work;

b. When the work will be conducted;

c. What type of work will be done;

d. Who Carroll County can contact for specific details or related questions; and

e. Any permit seeking approval under application.

f. Following a joint meeting between the applicant and Carroll County, the County shall deny or approve the application within ten calendar days.

(2) Upon final approval, any required permit permitted shall be deemed issued.

History

The history line the source prints at the end of the section.

(Ord. of 5-4-21(1), § 4)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:carroll-county/code/22-105@2025-05-06-f02ae7a18c

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Carroll County Code of Ordinances, Sec. 22-105. Approval or denial notification | Georgia Commons