Sec. 18-315. Action on an application for wireless telecommunications facilities.

About this text

  • As published by Municode, current through 2026-02-17
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Within 90 calendar days of the date an application for modification or co-location of wireless telecommunications equipment is filed with the county, unless another date is specified in a written agreement between the county and the applicant, the county shall:

(1) Make its final decision to approve or disapprove the application; and

(2) Advise the applicant in writing of its final decision.

(b) Within 30 calendar days of the date an application for modification or co-location is filed with the county, the county shall determine if it is a complete application and, if it determines that the application is not a complete application, notify the applicant in writing of any information required to complete such application. To the extent additional information is required to complete the application, the time

required by the applicant to provide such information shall not be counted toward the 90 calendar day review period set forth in subsection (a) of

this section.

(c) Within 150 days of the date an application for a new telecommunications tower is filed with the county, unless another date is specified in a written agreement between the county and the applicant, the county shall:

(1) Make its final decision to approve or disapprove the application; and

(2) Advise the applicant in writing of its final decision.

(d) Within 30 calendar days of the date an application for a new telecommunications tower is filed with the county, the county shall determine if it is a complete application and, if it determines that the application is not a complete application, notify the applicant in writing of any information required to complete such application. To the extent additional information is required to complete the application, the time

required by the applicant to provide such information shall not be counted toward the 150 calendar day review period set forth in subsection (c) of

this section.

(e) Within 15 calendar days (adjusted for any tolling due to lawful requests for additional information or mutually agreed upon extensions of time) of the date an application for an "eligible facilities request," under 47 U.S.C. 1445(a), that will improve public safety by providing advanced wireless technologies to public safety agencies and first responders is filed with the county, the county shall:

(1) Make its final decision to approve the application; or

(2) Advise the applicant in writing why the application does not qualify as an eligible facilities request.

(Ord. No. 14-21, § 1(Exh. A), 12-2-2014; Ord. No.

22-04, § 1(Exh. A), 6-21-2022)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:columbia-county/code/18-315@2026-02-17-015b08a305

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Columbia County Code of Ordinances, Sec. 18-315. Action on an application for wireless telecommunications facilities | Georgia Commons