Sec. 18-315. Action on an application for wireless telecommunications facilities.

Sobre este texto

  • As published by Municode, current through 2026-02-17
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Within 90 calendar days of the date an application for modification or co-location of wireless telecommunications equipment is filed with the county, unless another date is specified in a written agreement between the county and the applicant, the county shall:

(1) Make its final decision to approve or disapprove the application; and

(2) Advise the applicant in writing of its final decision.

(b) Within 30 calendar days of the date an application for modification or co-location is filed with the county, the county shall determine if it is a complete application and, if it determines that the application is not a complete application, notify the applicant in writing of any information required to complete such application. To the extent additional information is required to complete the application, the time

required by the applicant to provide such information shall not be counted toward the 90 calendar day review period set forth in subsection (a) of

this section.

(c) Within 150 days of the date an application for a new telecommunications tower is filed with the county, unless another date is specified in a written agreement between the county and the applicant, the county shall:

(1) Make its final decision to approve or disapprove the application; and

(2) Advise the applicant in writing of its final decision.

(d) Within 30 calendar days of the date an application for a new telecommunications tower is filed with the county, the county shall determine if it is a complete application and, if it determines that the application is not a complete application, notify the applicant in writing of any information required to complete such application. To the extent additional information is required to complete the application, the time

required by the applicant to provide such information shall not be counted toward the 150 calendar day review period set forth in subsection (c) of

this section.

(e) Within 15 calendar days (adjusted for any tolling due to lawful requests for additional information or mutually agreed upon extensions of time) of the date an application for an "eligible facilities request," under 47 U.S.C. 1445(a), that will improve public safety by providing advanced wireless technologies to public safety agencies and first responders is filed with the county, the county shall:

(1) Make its final decision to approve the application; or

(2) Advise the applicant in writing why the application does not qualify as an eligible facilities request.

(Ord. No. 14-21, § 1(Exh. A), 12-2-2014; Ord. No.

22-04, § 1(Exh. A), 6-21-2022)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:columbia-county/code/18-315@2026-02-17-015b08a305

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Columbia County Code of Ordinances, Sec. 18-315. Action on an application for wireless telecommunications facilities | Georgia Commons