(5) Grading outside of rights-of-way. The subgrade for areas outside of rights-of-way, which will include structures, parking lots, driveways and utilities, shall be compacted to 95 percent of maximum dry density as determined by AASHTO Method T-99 and shall be free from unsuitable materials such as organic materials and soft clays. All other areas outside of rights-of-way shall be compacted to at least 85 percent of maximum dry density as determined by AASHTO Method T-99.
(6) Maximum disturbed area. No more than 50 acres of disturbed area under development excluding road and rights-of-way shall exist on the site at one time. If proposed development disturbance exceeds 50 acres at any one time excluding roads and road rights-of-way, then the applicant shall obtain a variance, as prescribed in the Dawson County Land Use Resolution, before proceeding with the proposed development.
(Ord. of 9-16-2021(2), § 902; Ord. of 9-18-2025(1), Exh. A, § 75) Sec. 133-261. Storm drainage and plan.
A drainage system, including necessary open ditches, pipes, culverts, intersectional drains, drop inlets, bridges, etc., shall be provided for the proper drainage of all surface water. Cross-drains shall be provided to accommodate all natural water flow, and shall be of sufficient length to accommodate the full width roadway and the required slopes. All storm drainage and stormwater management systems shall meet the requirements of the latest editions of the Dawson County Stormwater Management Ordinance and the Dawson County Addendum to the Georgia Stormwater Management Manual.
(Ord. of 9-16-2021(2), § 903) Sec. 133-262. Reserved.
Sec. 133-263. Storm drainage ponds.
All stormwater facilities which will detain or retain water shall be privately maintained and have an executed maintenance agreement per Dawson County Stormwater Ordinance, section 109-143.
All detention and retention storm drainage ponds 18 inches or greater in depth will require fencing that surrounds the full length of the pond. Fencing material must be at minimum eight-gauge black coated chain link. A minimum 20-foot wide double access gate must be installed for adequate maintenance. The minimum height of the fence shall be 60 inches.
Alternative fence types: Fences are required for the safety of the general public. The public works director will review requests for an alternate type of fence if safety requirements can be met using an alternative design or due to the design of the detention/retention pond, e.g., shallow ponds may not require fencing.
(Ord. of 9-16-2021(2), § 903.2) Sec. 133-264. Installation of utilities.
After grading is completed and approved and before any base is applied, all of the underground work, water mains, gas mains, etc., and all service connections shall be installed completely and approved throughout the length of the road and across the flat section.
(Ord. of 9-16-2021(2), § 904) Sec. 133-265. Water supply system.
Public water systems shall meet the requirements of the provider unless requirements contained herein are more stringent in which case the more stringent of the two criteria shall apply. Water mains within subdivisions must be provided with connections to each lot.
Minimum diameter of water main pipes shall be eight inches. Individual connections shall be made to each lot, and pipe sizes shall not be less than three-fourths of an inch in diameter.
Dawson County Emergency Services shall be notified 24 hours prior to construction of water main. The developer must obtain Dawson County Emergency Services approval of the water system prior to approval of a final plat.
If a public water supply is not available to the subdivision at the time of development, the developer shall provide an adequate water source and an adequate water storage facility. This may be accomplished by the use of individual wells for each housing unit. Individual wells are the responsibility of the lot purchaser.
Any community (subdivision) water system shall be sanitary, and shall have a minimum adverse pressure of 30 pounds per square inch at each lot in the subdivision, and the capacity to provide 100 gal./day/capita.
Any community water system shall be approved by the appropriate health agency; and a letter of approval from the Georgia Department of Human Resources, Public Health Division or Georgia Department of Natural Resources, Water Supply Section, as appropriate, shall accompany the recording permit application.
(Ord. of 9-16-2021(2), § 905) Sec. 133-266. Water distribution plan.
A water distribution plan shall be provided for all developments having a community water system.
It shall contain the following information:
(1) Location and size of water distribution system including pipes, valves, fittings, hydrants, high pressure pumping equipment, pressure reducing valves, etc., complete to individual lots.
(2) Location and size of all wells, storage tanks, and lift stations.
(3) A certificate in the exact language set forth below, properly executed, shall be attached or affixed to the water distribution plan:
Water Supply Certificate State of Georgia, Count of Dawson "The water supply system proposed for (Name of Development or Subdivision) meets all design requirements for an acceptable water supply system based on the appropriate code of the State of Georgia."
Public Water Provider Representative or, (Dawson County Environmental Health Department) Date (Ord. of 9-16-2021(2), § 905.1) Sec. 133-267. Placement of fire hydrants and valves.
Fire hydrants shall be required for all subdivisions and water systems if public water is available.
Fire hydrants shall be located no more than 500 feet apart within a residential subdivision and no more than 300 feet apart within a commercial subdivision. Fire hydrants must also be placed at the end of each cul-de-sac. To eliminate future street openings, all underground utilities for fire hydrants, together with fire hydrants themselves and all other water supply improvements shall be installed before any base course application of a street shown on the subdivision plat. All fire hydrants shall be set plumb with outlets 18 inches above a finished concrete surface. No valves shall be located within the pavement or curb area.
(Ord. of 9-16-2021(2), § 905.2) Sec. 133-268. Sanitary sewers.
Public sewer systems shall meet the requirements of the provider, as applicable, unless requirements contained herein are more stringent in which case the more stringent of the two criteria shall apply. If the sewage disposal facilities cannot be connected to a trunk line sewer at the time of development of the subdivision, then septic tanks, an oxidation pond, or other approved method of sewage treatment shall be installed by and at the expense of the sub-divider or lot purchaser for interim use in conformity with the requirement of the appropriate health agency. Standard on-site sewage management (septic) systems shall follow the "Manual for On-Site Sewage Management Systems" (current edition) published by the Georgia Department of Community Health.
(Ord. of 9-16-2021(2), § 906) Sec. 133-269. Sanitary sewer plan.
A sanitary sewer plan shall be provided for those developments offering such service and shall contain the following information:
(1) Location of all proposed and existing wastewater treatment facilities and information concerning present and projected capacities.
(2) Location and size of all existing and proposed sewer lines in the development and tie points to other systems. Location of all sewer laterals.
(3) Direction of flow of each sewer line and average slope as built.
(4) Location of each manhole and other sewerage system appurtenances including lift stations, oxidation ponds, and treatment plants.
(5) Profile of sewage system.
(6) A certificate of the exact language as set forth below, properly executed, shall be attached to the sanitary sewerage plan:
Sanitary Sewage System Certification: State of Georgia, County of Dawson "I, , a Registered Engineer, certify that the Sanitary Sewage System shown on this drawing is properly designed; meets all local and state specifications and is adequate both in size and established depth to serve the drainage area whose sewage would normally be carried through this development or subdivision system, whether or not the total area to be served is within this subdivision. It is further certified that the information shown hereon is true and correct."
Registered Professional Engineer Number Date "I, (Appropriate Official), hereby attest to the fact that this sewage system and treatment plant is satisfactory and meets all requirements of the State of Georgia."
Public Sanitary Sewer Provider Representative or, (Dawson County Environmental Health Department) Date (Ord. of 9-16-2021(2), § 906.1) Sec. 133-270. Street pavement widths.
Street pavement widths shall meet the specifications in Road and Street Design Criteria—Chart 1.
(Ord. of 9-16-2021(2), § 907) Sec. 133-271. Street and alley improvements.
(a) Specifications. Unless otherwise specifically set forth herein, all of the materials, methods of construction, and workmanship for the work covered in reference to street construction shall conform to the latest specifications of the Georgia Department of Transportation (GDOT). See Road and Street Design Criteria—Chart 1 for reference. All curbing shall be Class "A" (as defined by GDOT) and have a minimum 28-day compressive strength of 3,000 PSI.
(b) Additional requirements for all streets.
(1) When the street is to be used for construction traffic before the paving work is completed, a layer of stone (except crusher run) shall be laid as a traffic surface. This material shall not be used as a part of the base material. It may be worked into the subgrade, or it shall be removed before the base course is set up for paving.
(2) Provisions shall be made to drain low points in the road construction when the final paving is delayed. A break in the berm section is required when the curbing has not been constructed. After installation, drainage under the curb to side slopes is required, using minimum four-inch diameter pipe sections.
(3) All drainage pipe laid under future road pavement must be installed in accordance with GDOT specifications and include at a minimum of six inches of Type II foundation backfill. A public works representative must be present during backfilling over the pipe.
(c) Project access improvement standards. For sections four feet or greater in width, the section shall comply with the construction standards for new streets, in accordance with the street's category as shown on the comprehensive plan. The base course must pass roll testing prior to paving. For sections less than four feet wide, seven inches of Class "A" concrete base (five inches on local and minor collector streets) and 1.5 inches of "E" or "F" topping shall be required.
(d) New local residential and minor residential collector streets (curbed). The base course shall consist of graded aggregate base as specified in the Road and Street Design Criteria—Chart 1. After being thoroughly compacted and brought to proper section, "B" binder shall be applied. A public works representative must inspect the base course before application of the wearing course. The wearing course shall be applied after 90 percent of the houses on the street have been built, or prior to the end of the maintenance period (but after the 11th month), whichever occurs first. Prior to applying wearing course, a tack coat shall be applied to the binder course at a rate of no less than
0.05 gallons per square yard. Type of tack shall be approved by the department prior to placement.
(e) Local residential streets (not curbed). The road base shall be extended one foot beyond the edge of pavement and the shoulders shall extend eight feet from the edge of pavement to a standard ditch section on each side (see standard drawings). Otherwise, the roadway shall comply with the standards for new residential subdivision streets, above.
(f) New nonresidential local streets and minor collectors.
(1) Asphalt. The base course shall consist of at least seven inches of graded aggregate base.
After being thoroughly compacted and brought to proper section "B" binder shall be applied.
If a delay in paving is reasonably expected by the developer or the department, the base shall be primed with 0.25 gallon of R.C. 70 per square yard the same day it is compacted, and cured for seven days prior to paving. A public works representative must inspect the base course and before application of the wearing course (or top course). The final one inch of type "E" or "F" wearing course shall be applied after 90 percent of the buildings on the street have been built, or prior to the end of the maintenance period (but after the 11th month), whichever occurs first. Prior to applying wearing course, a tack coat shall be applied to the binder course at a rate of no less than 0.05 gallons per square yard. Type of tack shall be approved by the department prior to placement.
(2) Concrete. Seven inches of Class "A" 3,500 psi concrete is to be applied on a stabilized subgrade consisting of at least 150 pounds of stone per square yard mixed in four inches deep and compacted. The design and construction of the street shall comply with the Portland Cement Association standards.
(g) New major thoroughfares. Major collectors, minor arterials and major arterials shall be constructed with designs prepared by Dawson County or GDOT depending on the jurisdiction. If no design is provided for a Dawson County road, the criteria in Road and Street Design Criteria—Chart 1 shall apply.
(h) Curb and gutter requirements.
(1) Curb and gutter required. All streets within subdivisions shall provide curbs and gutters constructed with either precast concrete curb, or integral concrete curb and gutter conforming to Road and Street Design Criteria—Chart 1.
(2) Curb and gutter shall be set true to line and grade, horizontal shall be field staked, and finished to the section shown on the plans. Along the project access improvements of a road which the department of transportation has identified for resurfacing within one year of the new construction, the grade of the new gutter shall be placed one inch above the project access improvement pavement grade in areas where drainage will not be adversely affected.
(3) Line and grade shall be set by developer's engineer or surveyor on grade less than two percent and over 12 percent, and within 100 feet in both directions from all low points.
(4) One-half inch expansion joints or pre-molded bituminous expansion joint material shall be provided at all structures and radius points and at intervals not to exceed 250 feet in the remainder of the curb and gutter.
(5) Inferior workmanship or unprofessional construction methods resulting in unacceptable curb and gutter will be cause for rejection of the finished work.
(6) Disturbed areas along all curbing shall be backfilled, stabilized, and grassed.
(i) Exemption from curb and gutter requirement. All residential subdivisions and developments where lot sizes are 1.5 acres or greater shall be exempt from the provision of curb and gutter. All other street requirements must be met.
(j) General requirements for road construction. Defects shall be remedied as soon as they are discovered. New material shall be added if necessary, and defective portions shall be entirely removed.
(1) The base course shall be maintained under traffic and kept free from ruts, ridge and dusting, true to grade and cross-section until it is primed.
(2) No based material shall be deposited or shaped when the subgrade is frozen or thawing or during unfavorable weather conditions.
(3) Sealing of joints. Care and precaution shall be taken that all joints between the surface and mixture and such structures as manholes and curbs are well sealed.
(Ord. of 9-16-2021(2), §§ 908—908.9; Ord. of 9-18-2025(1), Exh. A, § 76) Sec. 133-272. General requirements for county acceptance into maintenance program.
For a street to be eligible for county maintenance, all of the following guidelines must be applicable:
(1) Said street must originate and end at either a state route or county-maintained road.
(2) County will only accept collector roads inside developments, and must follow the provisions in these regulations.
(3) Street and associated storm system within the right-of-way must meet Dawson County design standards.
(Ord. of 9-16-2021(2), § 909; Ord. of 9-18-2025(1), Exh. A, § 76) Sec. 133-273. Existing roads for county acceptance.
The process described in this section shall be followed for the consideration of the possible acceptance of existing private roads as public roads by the county. Notwithstanding compliance with this process, the county is not obligated to accept the dedicated roads, which acceptance shall be considered in the sole discretion of the board of commissioners.
(1) The existing private road will require corings. Corings shall be performed every 300 feet of the roadway and these cores shall be tested by a geotechnical engineering firm licensed in the State of Georgia. This firm will provide the county with a report containing the testing results and also provide recommendations needed so as to bring the road up to county standards. If the public works department determines that additional corings are required in order to confirm compliance with county regulations, the department will provide the locations for these additional corings. The coring and associated reports will be the responsibility of the owner(s).
(2) The public works department will inspect the road during reconstruction and repair.
(3) The existing road's storm conveyance (piped) system will be inspected by the public works department. If the inspection reveals potential safety or performance concerns, the owner(s) will be required to have the system scoped and a report of those findings provided to the public works department.
(4) The existing storm conveyance system (whether open-ditched or piped) must be reviewed by a civil engineer licensed in the State of Georgia. The engineer will provide a report as to the operation and function of the existing system. Any deficiencies reported by the engineer or found by the public works department must be repaired by the owner.
(5) Once the public works department has confirmed that the road and storm conveyance systems have been reconstructed and/or repaired to county standards, the owner(s) can submit a request to the board of commissioners for acceptance of the road and approval of the road to be brought into the county's road maintenance program.
Deed of dedication and acceptance. Subdivision streets and rights-of-way and other lands to be dedicated to the public shall be considered for acceptance by Dawson County only upon the delivery to the board of commissioners of a warranty deed conveying fee simple title of such rights-of-way and lands, in a form acceptable to the public works director. The deed acceptable to the public works director shall be accompanied by an attorney's certificate of title and a tax transfer form addressed to the Dawson County Board of Commissioners, certifying that the grantor in such deed is vested with marketable fee simple title to the property conveyed thereby, that the property is free and clear of all liens, and further that the individual executing such deed has full authority to do so. The attorney's certificate of title must also identify and describe all encumbrances affecting the property.
If the subdivisions streets and rights-of-way and other lands to be dedicated to the public are subject to encumbrances, the board of commissioners, in its sole discretion, may determine whether such encumbrances result in the dedication being unacceptable for acceptance by Dawson County. In any event, acceptance of any proposed dedication of subdivision streets, rights-of-way, and other lands to Dawson County shall only be accomplished by the board of commissioner's approval of a resolution at a public meeting, a certified copy of which resolution shall be attached to the deed of dedication.
(Ord. of 9-16-2021(2), § 909.1; Ord. of 6-5-2025(1), § 1) Sec. 133-274. New developments for county acceptance.
Prior to approval of the final plat for a major subdivision with public roads and facilities, the developer shall submit a copy of a completed certificate of development conformance (CDC package) and post a guaranty bond or other surety as approved by the governing body in an amount equal to 100 percent of the development costs of the streets, curbs, storm sewer conveyances and other public facilities. Said bond shall be payable to Dawson County and shall, at a minimum guarantee that said streets, curbs, sidewalks and storm sewer conveyances will be installed in a workmanlike manner, and that same will be free from defects caused by faulty material or workmanship. Said bond or other surety shall be subject to call by the county, and shall not be released, until at least 85 percent of the homes in the subdivision have received certificates of occupancy and the public works director has performed an inspection and determined that the streets, curbs and storm sewer conveyances meet all county requirements.
In addition, the developer shall also post a guaranty bond or other surety as approved by the governing body in an amount equal to 100 percent of the reasonable cost of maintenance of the streets, curbs, sidewalks and storm sewer conveyances, as reasonably estimated by the public works director, payable to Dawson County and guarantying that said street, curb, and storm sewer conveyances will remain in acceptable condition for a period of 18 months following the release of the performance bond described above (upon final completion of the streets, curbs, and storm sewer conveyances as determined by the public works director) and subject to passing a further inspection to ensure compliance with county regulations. If, before the end of the 18-month period, the streets, curbs, or stormwater conveyances are found to have settled or be otherwise unacceptable because of faulty workmanship or material or are otherwise not in an acceptable condition, said defective street, curb, and stormwater conveyances shall be repaired by the developer. If the repair is not performed by the developer, the county may, but shall not be required to, call the bond and perform the required maintenance.
Following the 18-month period and release of the maintenance bond, the public works director shall add the new public streets to the county's road maintenance program. The public works director shall give notice to the board of commissioners regarding final approval of the street or streets.
Prior to release of bonds for construction and maintenance of public roads, curbs and storm sewer conveyances in a new major subdivision, the developer shall provide the county with the following:
(1) Developer will provide the public works director with soil compaction reports and proof roll approvals before filling and for the subgrade. Four out of five tests shall exceed 95 percent standard proctor type testing. Contractor must also perform core sampling every 300 feet of the road to be accepted. Dawson County may require cores to be delivered to the county prior to being sent to a testing facility to be tested and be sent by either the contractor or Dawson County or have the contractor send the cores directly to the testing facility at the discretion of the public works director. All testing must be done in accordance with GDOT specifications and standards. Compaction tests shall be performed at every utility crossing and must pass Dawson County requirements. Copies of all reports will be provided to the public works director and planning director. Developer will hire a licensed testing and engineering facility to carry out the testing required in this paragraph when inspections are not provided by the county.
(2) As-builts of roads and stormwater facilities as referenced in Dawson County's Stormwater Ordinance.
(3) Stormwater pond certification forms (if applicable).
(Ord. of 9-16-2021(2), § 909.2) Sec. 133-275. Street lights.
Street lights may be provided by the developer in new subdivisions which propose the construction of a new street to be dedicated to the county. Street lights may be required under certain conditions such as the land use resolution, master plan or any conditional use approved by the planning commission or board of county commissioners.
(1) Prior to the approval of a final plat, the developer shall submit a copy of the approved preliminary plat to the power company having jurisdiction. The power company shall prepare a street light design drawn on the preliminary plat based upon AASHTO recommendation. The developer shall pay the power provider the appropriate cost for materials and installation. Proof of payment to the power provider shall be required prior to final plat approval.
(2) All fixtures and poles shall meet the requirements of the county and all maintenance shall be the responsibility of the power provider. All street lights shall be shaded so that light shall be directed downward and not visible horizontally. Fixtures shall be mounted a minimum of 16 feet above the ground and each fixture shall have appropriate arm length to illuminate the street. Streetlights shall be required at street intersections within the development.
(3) Upon acceptance of the street light installation by the county, the power provider shall submit monthly bills to the property owner's association.
(Ord. of 9-16-2021(2), § 910) Secs. 133-276—133-292. Reserved.
ARTICLE X. RESERVED
Secs. 133-293—133-327. Reserved.
ARTICLE XI. VARIANCES*
Sec. 133-328. Purpose.
The purpose of a variance is to provide relief when a strict application of the subdivision regulations would impose unusual practical difficulties or unnecessary physical hardships on the applicant. Practical difficulties and unnecessary hardships may result from the size, shape or dimensions of a site or the location of existing structures thereon; from geographic, topographic, or other conditions on the site or in the immediate vicinity. No variance shall be granted to allow the use of property for a purpose not authorized or in a manner not authorized by the subdivision regulations.
Variances may be granted to modify a numeric value; variances shall not be granted to eliminate a requirement.
(Ord. of 4-21-2022(2); Ord. of 9-18-2025(1), Exh. A, § 77) Sec. 133-329. Conditions.
Reasonable conditions may be imposed in connection with a variance as deemed necessary to protect the best interests of the surrounding property or neighborhood, and otherwise secure the purpose and requirements of this article and the subdivision regulations. Guarantees and evidence may be required to show compliance.
(1) The planning commission is responsible for considering and making recommendations or decisions (as applicable) on applications for variances, per chapter 121, article IX and section 121-340(2).
(2) The variance request shall specify which requirements are to be varied and shall specify alternative standards and requirements to be met.
(Ord. of 4-21-2022(2)) Sec. 133-330. Criteria for granting variances.
(a) Variances may be granted only if, on the basis of the application, investigation, and evidence submitted by the applicant, all four expressly written findings below are made:
(1) That a strict or literal interpretation and enforcement of the specified standard or requirement would result in practical difficulty or unnecessary hardship and that there are exceptional or extraordinary circumstances or conditions; and
(2) Applicable to the property involved or to the intended use of the property which do not apply generally to other properties; and
(3) That the granting of the variance will not be detrimental to the public health, safety, or welfare; and
(4) That the granting of the variance would support the general objectives contained within this chapter.
(b) Variances in accordance with this article should not ordinarily be granted if the special circumstances on which the applicant relies are a result of the actions of the applicant or owner or previous owners.
(c) A variance may be granted only for dimensional standards, excluding standards establishing minimum lot size, except as permitted by the family density exception variance set forth in section 133-337.
(d) No variance may be granted for the development of a major subdivision that is applicable to more than 35 percent of the proposed lots.
(Ord. of 4-21-2022(2)) Sec. 133-331. Variance procedures.
The following procedures apply:
(1) Application for variance shall be filed with the community development director or his or her designee on the form prescribed by the county, by any person with a legal interest in the property. The application shall specify the requirement(s) from which the applicant seeks a variance, the reasons said variance is necessary, the numeric change proposed (increase or decrease), applicable site plan and exterior architectural renderings, and other information required by the application in order to aid the decision makers.
(2) Before the planning commission may act on a variance; it shall give notice of a public hearing in the manner prescribed in chapter 121, article XII, section 121-373.
(3) The planning commission shall review the application and investigation report at the public hearing. The planning commission shall determine whether the evidence supports a finding that the required criteria have been met and approve, approve with conditions (if applicable), or deny of the application accordingly. If the planning commission fails to take action within 30 days after the public hearing, the request shall be deemed to have been denied.
(4) Decisions on variance requests shall be the responsibility of the planning commission and shall become final after an elapsed period of 30 days from the date of decision.
(5) The planning commission's decision, with findings, shall be sent by electronic or hard copy format to the applicant within five working days of the date of action.
(6) From time to time the planning commission may find it necessary to require a variance request to also meet approval of the board of commissioners. In doing so the variance request must follow the public hearing procedures prescribed in chapter 121, article XII, section 121-373. An application of a variance which is not acted upon by the board of commissioners within 90 days from the receipt of application may be deemed denied.
(7) Appeals may be processed in accordance with sections 133-407 and 133-408 of this chapter.
(Ord. of 4-21-2022(2); Ord. of 9-18-2025(1), Exh. A, § 78) Sec. 133-332. Compliance with conditions approval.
Compliance with conditions imposed in the variance, and adherence to the submitted plans, as approved, is required. Any departure from these conditions of approval and approved plans constitutes a violation of this chapter or ordinance, whichever is applicable.
(Ord. of 4-21-2022(2)) Sec. 133-333. Vested interest in approved variances.
A valid variance supersedes conflicting provisions of or amendments to this chapter unless specifically provided otherwise by the provisions of this article or the conditions of approval to the variance.
(Ord. of 4-21-2022(2)) Sec. 133-334. Investigations and reports.
The planning development director shall make or cause to be made an investigation to provide necessary information to insure that the action on each application is consistent with the variance criteria. Any report of such investigation shall be included in the application file.
(Ord. of 4-21-2022(2)) Sec. 133-335. Revocation.
Variances shall be automatically revoked if not exercised within one year of the date of approval unless an extension is sought and obtained from the planning commission.
(Ord. of 4-21-2022(2)) Sec. 133-336. Limitations of reapplication.
Applications for which a substantially similar application has been denied shall be heard by the planning commission only after a period of 12 months has elapsed from the date of denial.
(Ord. of 4-21-2022(2)) Sec. 133-337. Family density exception.
(a) Upon application, the community development director or his or her designee may grant a family density exception for the creation of not more than five total lots (including the parent tract) for a bona fide intra-family transfer such that adherence to the minimum lot dimensions for the land use category or zoning district where the lots are located is not required. For example, a family density exception may be granted such that a five-acre parcel, zoned RA residential agriculture, may be subdivided into a three-acre lot and a two-acre lot for a bona fide intra-family transfer. If the proposal is in the RA district, the parent lot/parcel must be a minimum of five acres in size prior to subdividing.
(b) Bona fide intra-family transfer is hereby defined as follows:
(1) Conveyance of property by warranty or quit claim deed with consideration recited in the deed as "love and affection," and
(2) The grantee is 18 years of age or older; and
(3) The grantor and grantee are related as follows:
a. Parent and child; or
b. Brother and brother, sister and sister and/or brother and sister; or
c. Grandparent and grandchild; or
d. Aunt/uncle and niece/nephew; and
e. The conveyance meets all other applicable criteria for an exception under this resolution; and
f. The purpose of the conveyance is not to subdivide property for sale, resale, or rental to persons not listed in subsection (b)(2) of this section or otherwise circumvent the provisions of this resolution and the applicant so states by sworn verification.
(c) Documentation satisfactory to the community development director, or his or her designee, reflecting the relationship between the grantor and any grantee(s) of any bona fide intra-family transfer, as well as the age of any such grantees, shall be provided upon application for a family density exception.
(d) A family density exception shall not be approved within a platted subdivision when such approval would increase the density within the subdivision beyond the density otherwise permitted for the subdivision.
(e) The community development director or his or her designee shall approve a family density exception if the proposed bona fide intra-family transfer meets the requirements of this subsection and otherwise complies with all applicable laws and ordinances.
(f) Upon approval of a family density exception, no subsequent approval for a family density exception may be granted for further division of any portion of the property (including newly created lots or the parent tract).
(g) The subdivision of property pursuant to a family density exception shall conform to the following standards:
(1) Any lots created shall be conveyed as part of a bona fide intra-family transfer and no more lots may be created than are approved in accordance with the family density exception.
(2) Each lot shall be a minimum of 11 /2 acre.
(3) The creation of a lot wholly within the regulatory 100-year floodplain is prohibited.
(4) If any lot abuts a publicly maintained road that does not conform to the right-of-way specifications provided or adopted by reference in these regulations, the owner may be required to dedicate the right-of-way width necessary to meet the minimum design standards as a condition of approval.
(5) Buffer zones of at least 50 feet in width along all perennial and intermittent streams shall be required.
(6) Each lot shall front on a paved private road, a publicly maintained road, or an easement. If an easement is utilized:
a. The easement shall connect to a publicly maintained road and have a minimum width of 30 feet; and
b. Road name signs for the easement shall be installed in accordance with applicable county regulations; and
c. The easement shall comply with the Federal Emergency Management Agency (FEMA) regulations and county floodplain management regulations; and
d. The following notation shall be included on the plat: Dawson County is not obligated to maintain the easement.
(7) All other requirements of the Code of Dawson County and the Dawson County Comprehensive Plan shall apply.
(Ord. of 4-21-2022(2); Ord. of 9-18-2025(1), Exh. A, § 79) Secs. 133-338—133-362. Reserved.
ARTICLE XII. INSPECTION
Sec. 133-363. Inspection.
The board of commissioners, the planning director and the public works director each shall have the power to conduct or cause to be conducted such investigation as they may reasonably deem necessary to carry out the duties as prescribed in these regulations, and for this purpose to enter at reasonable time upon any property, public or private, for the purpose of investigating and inspecting the sites of subdivision activities.
(Ord. of 9-16-2021(2), § 1200) Secs. 133-364—133-384. Reserved.
ARTICLE XIII. ENFORCEMENT
Sec. 133-385. Stop work orders.
Any person failing to comply with any provision of these regulations shall be subject to a stop work order as issued by the planning director and/or the public works director or the Dawson County Marshal's Office. Upon receipt of notice of the stop work order, work on any project that is being performed in violation of these regulations shall be immediately stopped. Such notice shall be in writing and shall be given to the owner of the property, his authorized agent or the person or persons in charge of activity on the property, and shall state the conditions under which work may be resumed. Where an emergency exists, no written notice shall be required.
(Ord. of 9-16-2021(2), § 1300) Sec. 133-386. Civil penalties.
Any person violating any provision of these regulations shall be liable for a civil penalty of not less than $100.00 per day or not to exceed $500.00 per day. Each day the violation continues shall constitute a separate violation.
(Ord. of 9-16-2021(2), § 1301) Sec. 133-387. Enforcement in magistrate court.
Any person who shall do anything prohibited by these regulations or who shall fail to do anything required by these regulations shall be guilty of a misdemeanor, amenable to the process of the Magistrate Court of Dawson County, and upon conviction, shall be assessed with any penalty, including fine, confinement, or both, allowed by law for the violation of county resolutions or ordinances. Each and every day that such violation exists shall be deemed a separate offense.
(Ord. of 9-16-2021(2), § 1302) Sec. 133-388. Other penalties.
Any subdivision hereafter established shall be designed, developed, and recorded in accordance with the provisions of these regulations. Failure to comply with these regulations shall result in the county's refusal to approve the final plat for the subdivision and to maintain, grade, pave or light any street in such subdivision unless such street shall have otherwise been accepted as a public street.
(Ord. of 9-16-2021(2), § 1303) Secs. 133-389—133-406. Reserved.
ARTICLE XIV. APPEALS
Sec. 133-407. Reserved.
Sec. 133-408. Appeals.
(a) If an applicant or permittee desires to appeal any decision or action of the staff of the community development department or the public works department specific to the standards of chapter 133, the applicant or permittee may appeal the decision or action to the planning commission within ten calendar days of the date of action or decision. Only the applicant or permittee, or his or her representative, shall be eligible to submit an appeal. Any such action or decision shall remain in full force and affect pending said appeal. If an applicant or petitioner desires to submit an appeal, he or she shall submit an appeal form as provided by the staff of the community development department to the community development director or his or her designee. Upon receipt of this notice, the community development director or his or her designee shall place said appeal on the next regularly scheduled meeting agenda of the planning commission. The applicant or petitioner shall attend the planning commission meeting; failure to appear may result in the item being tabled or denied. The process by which each side presents findings shall be the same as that of a variance.
The planning commission shall render a decision at the meeting unless specific reasons are cited to table the appeal to the next scheduled meeting.
(b) If an applicant or permittee desires to appeal any decision or action of the planning commission, the applicant or petitioner shall notify the community development director or his or her designee in writing based on a form provided by the staff of the community development department within ten days of the date of decision or action of the planning commission. Upon receipt of the notice, the community development director or his or her designee shall submit the information to the board of commissioners to be placed on the next applicable meeting agenda. The applicant or petitioner shall attend the board of commissioners meeting; failure to appear may result in the item being tabled or denied. The board of commissioners shall render a decision unless specific reasons are cited to table the appeal to the next scheduled meeting.
(Ord. of 9-16-2021(2), § 1401; Ord. of 9-18-2025(1), Exh. A, § 80) Sec. 133-409. Appeals from decisions of the board of commissioners.
Any decision of the board of commissioners with respect to an appeal pursuant to this article may be appealed to the Superior Court of Dawson County.
(Ord. of 9-16-2021(2), § 1402) Secs. 133-410—133-431. Reserved.
ARTICLE XV. AMENDMENTS AND MODIFICATIONS
Sec. 133-432. Amendments and modifications.
These regulations may be amended or modified by the board of commissioners following a duly advertised public hearing.
(Ord. of 9-16-2021(2), § 1500; Ord. of 6-5-2025(1), § 2) Secs. 133-433—133-462. Reserved.
ARTICLE XVI. REMEDIES
Sec. 133-463. Remedies.
In addition to other remedies, if any land is used in violation these regulations, the planning director, the public works director, the county attorney, or the board of commissioners, may institute legal proceedings to obtain an injunction or other appropriate remedy to stop the violation or to prevent any act which would constitute such a violation.
(Ord. of 9-16-2021(2), § 1600) Secs. 133-464—133-494. Reserved.
ARTICLE XVII. PENALTIES FOR VIOLATION
Secs. 133-495—133-513. Reserved.
ARTICLE XVIII. LEGAL STATUS PROVISION
Sec. 133-514. Validity/severability.
Should any section, clause, or provision these regulations be declared by a court of competent jurisdiction to be invalid, such adjudication shall not affect the validity of these regulations as a whole or any part thereof other than the part so declared to be invalid, each section, clause, and provision thereof being declared severable.
(Ord. of 9-16-2021(2), § 1800) Sec. 133-515. Conflict with other laws.
Whenever the provision of these regulations impose more restrictive standards than are required under any other statute, the requirements of these regulations shall govern.
(Ord. of 9-16-2021(2), § 1802) Sec. 133-516. Liability.
Neither the approval of a plat under the provisions of these regulations, nor the compliance with the provision of these regulations shall relieve any person from the responsibility for damage to any person or property otherwise imposed by law nor impose any liability upon Dawson County for damage to any person or property.
(Ord. of 9-16-2021(2), § 1803) Sec. 133-517. Effective date.
These regulations shall take effect and be in force from and after the adoption and enactment of the land development resolution of which the regulations are a part, the public and welfare demanding it.
(Ord. of 9-16-2021(2), § 1804) Sec. 133-518. Roads and streets design criteria.
The following charts establish design criteria for roads and streets:
Road and Street Design Criteria—Chart 1 Minimum Right-ofWay Required (ft.) Minimum Pavement Width (ft.)1 Shoulder Width (ft.) Intersection R/W Radius (ft.) Intersection Radius (curb) (ft.)1 Crushed Stone Base (inches) Intermediate Course Surface Course Curbing Di- mensions Cul-de-sac R/W Radius (ft.)
Cul-de-sac Pavement Radius (ft.)1 Common Driveway2 30 (private easement) 16 2 25 5 N/A 2" Type E or F N/A N/A N/A Alley 20 (private
easement) 16 2 25 5 N/A 2" Type E or F
N/A N/A N/A
Local Residential Street (curbed) 50 20 11 14 25 6 2" Type "E" 1.25" Type "F" 6"×24"×12" 57.5 47.5 Local Residential Street (not curbed) 60 24 8 17 25 6 2" Type "E" 1.25" Type "F" N/A 57.5 47.5 Local Commercial Street 60 24 11 19 30 8 3" Type B Mod.
1.5" Type E or F 8"×24"×14" 60 50 Local Industrial Street 60 26 11 29 40 8 4" Type B Mod.
2" Type "E" 8"×24"×14" 60 50 Minor Residential Collector 60 20 11 14 25 8 2" Type "E" 1.25" Type "F" 6"×24"×12" 57.5 47.5 Minor NonResidential Collector 60 26 11 29 40 8 4" Type B Mod.
2" Type "E" 8"×24"×14" 57.5 47.5 Major Collector 100 66-4 through + center 11 29 40 10 4" Type B Mod.
2" Type "E" 8"×30"×14" N/A N/A Minor Arterial 100 66-4 through + center 11 29 40 10 4" Type B Mod.
2" Type "E" 8"×30"×14" N/A N/A Major Arterial 100 66-4 through + center 11 29 40 10 4" Type B Mod.
2" Type "E" 8"×30"×14" N/A N/A 1 Measured at edge of pavement 2 Used only within Minor Subdivisions (5 lots or less) Road and Street Design Criteria—Chart 2
Minimum Design Speed (mph) Maximum Grade Stopping Sight Distance (ft.)1 Minimum Centerline Radius (ft.)
Super Elevation Allowed Minimum k (crest)2 Minimum k (sag)2 Minimum Tangent Between Curves (ft.)
Approach Distances at Major Intersections (ft.)3 Common Driveway 10 14% 60 30 No 3 10 20 N/A Alley 10 14% 60 30 No 3 10 20 N/A Local Residential Street 20 14% 115 110 No 10 20 50 50 Local Commercial Street 20 14% 115 110 No 10 20 50 50 Local Industrial Street 20 14% 115 110 No 10 20 50 50 Minor Residential Collector 30 10% 200 340 No 19 37 75 75 Minor NonResidential Collector 30 10% 200 See AASHTO Yes 19 37 75 75 Major Collector 40 10% 305 See AASHTO Yes 44 64 100 75 Minor Arterial 40 10% 305 See AASHTO Yes 44 64 100 100 Major Arterial 50 8% 425 See AASHTO Yes 84 96 125 100 1 Stopping sight distances must be adjusted to factor in road grade per AASHTO criteria 2 Adhering to minimum k values will not necessarily ensure adequate sight distance for all conditions 3 Where a street approaches a major thoroughfare, a grade not exceeding 2% must be maintained for the following distances (measured from the edge of pavement of the through street to the PVC of the intersecting street)
(Ord. of 9-18-2025(1), Exh. A, § 81) Secs. 133-519—133-540. Reserved.