13.10.1390. Method to be used for sampling

About this text

  • As published by Municode, current through 2026-05-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

and testing.

A. All sampling, measurements, tests and analyses of the characteristics of waters and wastes to which reference is made in this article shall be

determined in accordance with 40 CFR 403, 40 CFR 136 and amendments thereto, and the latest edition of "Standard Methods for the Examination of Water and Wastewater", published by the American Public Health Association, and shall be

determined at the control manhole provided, or upon suitable samples taken at said control manhole. In the event that no special manhole has been required, the control manhole shall be considered to be the nearest downstream manhole to the public sewer to the point at which the building

sewer is connected. Sampling shall be carried out by customarily accepted methods to reflect the effect of constituents upon the sewage works and to determine the existence of hazards to life, limb and property. In case of laboratory procedural conflict, 40 CFR, Part 136 takes precedence. When 40 CFR, Part 136 does not contain sampling or analytical techniques for the pollutant in question, or where the director determines that the Part 136 sampling and analytical techniques are

inappropriate for the pollutant in question, sampling and analysis shall be performed by using validated analytical methods or any other applicable sampling and analytical procedures suggested by the POTW or other parties approved by the director.

B. The samples collected shall be representative of daily operations. At least four grab samples must be used for pH, cyanide, total phenols,

F.O.G., sulfide, and volatile organics. For all other pollutants, a continuous 24-hour composite sample collected during production hours must be obtained through flow proportional composite sampling techniques where feasible. If conditions warrant, additional consecutive 24-hour sampling periods may be required by the county. The director may waive flow proportional composite sampling for any user that demonstrates that flow proportional sampling is infeasible. In such cases,

samples may be obtained through time proportional composite sampling techniques or through a minimum of four grab samples where the user

demonstrates that this will provide a representative sample of the effluent being discharged.

C. Samples should be taken immediately downstream from pretreatment facilities, if such exist, or immediately downstream from the regulated

process if no pretreatment exists. If other wastewaters are mixed with the regulated wastewater prior to pretreatment, the user should measure

the flows and concentrations necessary to allow use of the combined wastestream formula of 40 CFR 403.6(e) in order to evaluate compliance with all pretreatment standards and requirements.

Where an alternative concentration or mass limit has been calculated in accordance with 40 CFR 403.6(e), this adjusted limit along with supporting data shall be submitted to the county.

History

The history line the source prints at the end of the section.

(Res. of 1-8-09(1), §§ 1, 2(Exh. A))

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hall-county/code/13.10.1390@2026-05-28-6adda46f69

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.