Sec. 66-188. Action on application.

About this text

  • As published by Municode, current through 2025-09-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Upon receipt of an application for permit under this article, the county shall within five business days either issue or reject the requested permit or request additional information when warranted. When additional information is requested, the permit shall be issued or rejected within five business days from the receipt of such sufficient information.

History

The history line the source prints at the end of the section.

(Ord. of 10-27-1998, § 12)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hart-county/code/66-188@2025-09-23-14bb7ee4a1

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.