(a) Certificate of occupancy.

(1) Building occupancy. A new building shall not be occupied or a change made in the occupancy, nature, or use of a building or part of a building until after the building official has issued a certificate of occupancy. Said certificate shall not be issued until all required electrical, gas, mechanical, plumbing, and fire protection systems have been inspected for compliance with the technical codes and other applicable laws and ordinances and are released by the building official.

(2) Issuing certificate of occupancy. Upon satisfactory completion of construction of a building or structure and installation of electrical, gas, mechanical, and plumbing systems in accordance with the technical codes, reviewed plans, and specifications, and after the final inspection, the building official shall issue a certificate of occupancy stating the nature of the occupancy permitted, the number of persons for each floor when limited by law, and the allowable load per square foot for each floor in accordance with the provisions of the technical codes.

(3) Temporary/partial occupancy. A temporary/partial certificate of occupancy may be issued for a portion of a building, which may safely be occupied prior to final completion of the building.

(b) Service utilities.

(1) Connection of service utilities. No person shall make connections from a utility, source of energy, fuel, or power to any building or system which is regulated by the technical codes for which a permit is required, until released by the building official and a certificate of occupancy or completion is issued.

(2) Temporary connection. The building official may authorize the temporary connection of the building or system to the utility source of energy, fuel, or power for the purpose of testing building service systems or for use under a temporary certificate of occupancy.

(3) Authority to disconnect service utilities.The building official shall have the authority to authorize disconnection of utility, service to the building, structure of system regulated by the technical codes, in case of emergency where necessary to eliminate an immediate hazard to life or property. The building official shall notify the serving utility, and whenever possible the owner and occupant of the building, structure, or service system of the decision to disconnect prior to taking such action. If not notified prior to disconnecting, the owner or occupant of the building, structure, or service system shall be notified in writing, as soon as practical thereafter.

History

The history line the source prints at the end of the section.

(Ord. No. 2002-007, exh. A(4.9), 10-8-2002)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:mitchell-county/code/18-97@2023-08-08-e4e4e9f7d0

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Mitchell County Code of Ordinances, Sec. 18-97. Certificates | Georgia Commons