Appendix A - SUBDIVISIONS / Article VIII - SPECIAL PROVISIONS

89.5.1. The following information shall be

About this text

  • As published by Municode, current through 2025-03-04
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

submitted for an application to be considered complete:

a. A descriptive site plan including setbacks, panel sizes, locations of property lines, building, and road right of ways;

b. Landscaping plan to scale indicating size, spacing and type of fence, shrubbery,

trees or earthen berm as required by 89.4.3;

c. A description of the anticipated maintenance needs for the Solar Energy Farm, including frequency of service, personnel needs, equipment needs, and traffic, noise, or safety impacts of such maintenance;

d. A utilities inventor showing the locations of all water, sewage, drainage, and power line easements impacting the proposed

site.

e. Relevant studies, reports, certificates and approvals as may be reasonably requested by the department, including but not

limited to design review;

f. A storm water management study shall be provided to ensure compliance with local BMP's; and

g. Before any construction can commence on any solar energy system, the property owner must acknowledge, in writing to

the board of commissioners that he/she is the responsible party for owning and

maintaining the solar energy system.

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:monroe-county/code/89.5.1@2025-03-04-c956c11243

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Monroe County Code of Ordinances, 89.5.1. The following information shall be | Georgia Commons