Chapter 33 - DATA CENTERS

Sec. 33-7. Environmental standards for data centers.

About this text

  • As published by Municode, current through 2026-06-02
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) For facilities over 100,000 square feet, prior to issuance of building permit, a written report from a licensed environmental engineer must be submitted to the county evaluating water withdrawal, energy demands, and storm-water runoff.

(b) No emissions (air, dust, smoke, glare, heat, or humidity) is permitted beyond property lines.

History

The history line the source prints at the end of the section.

(Res. No. 2026-180, § 1, 3-3-2026)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:polk-county/code/33-7@2026-06-02-cd6ebd646e

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Polk County Code of Ordinances, Sec. 33-7. Environmental standards for data centers | Georgia Commons