Sec. 33-7. Environmental standards for data centers.
About this text
- As published by Municode, current through 2026-06-02
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) For facilities over 100,000 square feet, prior to issuance of building permit, a written report from a licensed environmental engineer must be submitted to the county evaluating water withdrawal, energy demands, and storm-water runoff.
(b) No emissions (air, dust, smoke, glare, heat, or humidity) is permitted beyond property lines.
History
(Res. No. 2026-180, § 1, 3-3-2026)