Polk County · Code of Ordinances
Chapter 33 - DATA CENTERS
Sec. 33-6. Water, electrical, and energy standards for data centers.
About this text
- As published by Municode, current through 2026-06-02
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Prior to issuance of permit, written verification from Polk County Water Authority must be provided to the building inspector confirming the facility will not impair local water supply during droughts or peak demand times.
(b) Prior to issuance of permit, written verification from the electrical utility provider must be provided to the building inspector confirming sufficient grid capacity for peak-hour demands, including redundancy for outages.
(c) All electrical equipment shall be housed in electrically grounded structures with fire-rated enclosures, with a minimum of 30-minute resistance, and automatic fire baffles.
History
(Res. No. 2026-180, § 1, 3-3-2026)