Rockdale County · Code of Ordinances

Part II - CODE OF ORDINANCES / Part A - GENERAL ORDINANCES / Chapter 98 - UTILITIES / Article III - WASTEWATER SYSTEM / Division 2 - WASTEWATER APPLICATION AND CONNECTION PROCESS; FEES AND RELATED CHARGES

Sec. 98-91. Procedures to obtain wastewater service.

About this text

  • As published by Municode, current through 2026-01-27
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

No wastewater service shall be established or provided without proper application, evaluation of the requested wastewater allocation, and issuance and validation of a wastewater connection permit. The following procedures shall govern

this process. These procedures may be implemented by additional administrative rules and requirements consistent with this chapter as established by the director.

(1) Wastewater service connection application. Wastewater service shall not be connected to any property without proper

application having first been made to the department on forms provided by the department. No such application shall be tendered or accepted for initial review unless wastewater availability exists at the time of application under section 98-90. All applications shall be made by the owner of the land upon which a wastewater connection is desired, or the owner's authorized agent. The application shall be supplemented by the owner's drawings, plans, specifications, and other

such information which, in the judgment of the director, is pertinent to the desired connection in accordance with the requirements set forth in article III. Wastewater connection service charges and all other

fees and charges shall be paid as stipulated in article III. No wastewater service application may be tendered or accepted except in compliance with the procedures set forth in article III. No wastewater connection permit shall be issued or valiUTILITIES § 98-91 dated unless a wastewater allocation has been secured pursuant to article III and wastewater availability exists on the date of such allocation. Available wastewater capacity shall be allocated subject to the provisions of article III and the provisions of this chapter 98.

Validation of a wastewater connection permit shall occur upon placement of an official marking on the face of said permit

by an authorized representative of the Rockdale Water Resources engineering division indicating all fees and charges have been paid and all procedures completed,

as well as the date and time of validation.

(2) Evaluation of wastewater allocation requests and issuance of connection permits.

Wastewater allocations and connection permits shall be subject to the provisions particular to each of the project categories

as follows:

a. Process for an individual single family residential unit on a platted lot.

The procedure to obtain wastewater allocation and a connection permit for an individual single family residential unit on a lawful lot of record existing prior to March 28, 2007,

shall require the requesting party to submit a completed application for wastewater service and connection as provided by Rockdale Water Resources. Applications will not be provided to the requesting party or accepted by Rockdale Water Resources if wastewater availability does not

exist at the time of request for or submission of the application. Neither the determination of wastewater availability status nor the providing or acceptance of an application to the requesting party shall constitute

any right whatsoever to a wastewater allocation or otherwise bind the county to provide wastewater service to the project. The application must be submitted to Rockdale Water Resources for review and approval. All application fees must be § 98-91

tendered with the application. If the application is approved by Rockdale Water Resources consistent with all requirements of this chapter, a wastewater allocation will be assigned for the requesting unit. No wastewater

allocation shall be assigned unless wastewater availability exists on the date of assignment. Following assignment of allocation, and upon payment by the requesting party of all charges and fees, including CCR, the

allocation shall be finalized and the wastewater connection permit validated by Rockdale Water Resources.

b. Process for all other projects not requiring preliminary plat. The procedure to obtain wastewater allocation and a connection permit for a project

for which a preliminary plat is not required by Chapter 302 of the UDO shall require the requesting party to first obtain and submit a project description form as provided by Rockdale Water Resources. The project description form will not be accepted by Rockdale Water Resources if wastewater availability does not exist at the time of request for or

submission of said form. Upon tender of a completed project description form to Rockdale Water Resources, the requesting party will be required to attend a joint pre-design

meeting which will be scheduled by the department of public services and engineering and include Rockdale Water Resources. If the requesting party successfully completes predesign review by appropriate county departments and if wastewater availability exists for said project, the requesting party will be issued an

application form, as provided by Rockdale Water Resources, for wastewater service and connection. Neither the determination of wastewater availability status nor the providing or acceptance of an application to the requesting party shall § 98-91 ROClillALECOUNTYCODE

constitute any right whatsoever to a wastewater allocation or otherwise bind the county to provide wastewater service to the project. The completed wastewater service and connection application will be accepted by Rockdale Water Resources only

with concurrent submittal of land disturbance and construction plans and payment of all required charges and fees. If the application is approved by Rockdale Water Resources consistent with all requirements of

this chapter, a wastewater allocation will be assigned for the project. No wastewater allocation shall be assigned unless wastewater availability exists on the date of assignment.

Following assignment of allocation, and upon payment by the requesting party of all charges and fees, including CCR, the allocation shall be finalized and the wastewater connection permit validated by Rockdale Water Resources.

c. Process for projects requiring preliminary plat. The following wastewater allocation and connection permit procedures shall apply to all projects for which a preliminary plat is required

by Chapter 302 of the UDO:

1. The requesting party shall obtain and complete a project description form as provided by Rockdale Water Resources. The

project description form will not be accepted by Rockdale Water Resources if wastewater availability does not exist at the time of request for or submission of said form.

2. Upon tender of a completed project description form to Rockdale Water Resources, the requesting party will be required to attend a joint predesign meeting which will be scheduled by the department of

public services and engineering and include Rockdale Water Resources. The project description form shall be submitted no later than 48 hours prior to the

scheduled pre-design meeting.

3. If the requesting party successfully completes pre-design review by appropriate county departments and if wastewater availability exists for said

project, the requesting party will be issued an application form, as provided by Rockdale Water Resources, for wastewater service and connection. Neither the determination of wastewater availability status nor the providing or acceptance of an application to the requesting party shall constitute any right whatsoever to a wastewater allocation or otherwise bind the county to provide wastewater service

to the project.

4. Upon successful completion of steps 1. through 3. above, the requesting party shall proceed with the process necessary to secure a preliminary plat as provided by Chapter 302 of the UDO. The preliminary plat shall be submitted to the public services and engineering department in accordance with Chapter 302. Technical review of the preliminary plat is required

from both public services and engineering and Rockdale Water Resources. Upon approval of technical review of the preliminary plat by all departments and prior to the submission of the preliminary plat to the Conyers Rockdale Planning

Commission for hearing and action, the requesting party shall submit the completed application form referenced in paragraph (iii) above to Rockdale Water Resources. If the application is approved by Rockdale

Water Resources consistent with all requirements of this chapter, a wastewater allocation will be assigned for the project. No wastewater allocation shall be assigned unless wastewater availability exists on the date of assignment. Following assignment of allocation, and upon payment by the requesting party of all charges and fees, including CCR, the allocation shall be finalized and the wastewater connection permit validated by Rockdale Water Resources. The validated wastewater connection permit shall be immediately transmitted by the requesting party to the department of public services

and engineering. Said transmittal must occur prior to the meeting of the Conyers Rockdale Planning Commission for which

the preliminary plat is presented for approval. Failure by the requesting party to secure and transmit the validated wastewater connection permit prior to the planning commission meeting in question will result in automatic termination of the wastewater allocation and the wastewater connection permit and denial of the preliminary plat, provided

that the planning commission shall have the authority to defer final action on the preliminary plat for good cause shown until its next regularly scheduled meeting and provided further that no more than one such deferral shall be authorized and that the 60 day refund period set forth in subsection 98-94(a) shall be tolled for the period of said deferral.

5. The decision on the final preliminary plat approval shall be made by the Conyers Rockdale Planning Commission in accordance with the applicable requirements of Chapter 302 and this chapter.

6. In the event the preliminary plat is not approved by the Conyers Rockdale Planning Commission, the wastewater allocation and the wastewater connection

permit shall be immediately terminated and all charges and fees paid by the requesting party to Rockdale Water Resources for issuance of the wastewater connection permit shall be refunded except for the application fee attributable to processing said application.

d. Process for projects within incorporated Rockdale County. The following wastewater allocation and connection permit procedures shall apply to all projects partially or completely

geographically located within the limits of the City of Conyers:

1. All of the procedures set forth in subsection 98-91(b)(l), (2) or

(3) shall be followed according to the type of project requested, with the exception that required pre-design review meetings shall be conducted by appropriate city personnel rather than the Rockdale Department of Public Services and Engineering, and the transmittal of validated wastewater connection permit shall also be to said appropriate city personnel.

History

The history line the source prints at the end of the section.

(Ord. No. 2007-07, § 1, 3-27-2007)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:rockdale-county/code/98-91@2026-01-27-2d757c0a0c