Sec. 22-732. Application procedure.

About this text

  • As published by Municode, current through 2026-07-09
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Landowners or developers wishing to submit an application, must first attend a consultation meeting with Walker County for discussion of a stormwater concept plan. This meeting shall include the Planning Director, Environmental Manager, County Coordinator, and Road Supervisor from the County, as well as owner/developer and design professional.

(b) Applications for stormwater management permits must be filed with Walker County on any regular business day.

(c) A copy of this permit application shall be forwarded to the appropriate review agency for review.

(d) Permit applications shall include the following: 3 copies of the stormwater management plan, maintenance agreement and any required review fees.

(e) Walker County shall inform the applicant whether the application, stormwater management plan and maintenance agreement are approved or disapproved.

(f) If the permit application, stormwater management plan or maintenance agreements are disapproved, Walker County shall notify the applicant of the decision in writing. The applicant may then revise the permit application, stormwater concept plan, or the maintenance agreements and submit the required changes. If additional information is submitted, Walker County shall inform the applicant as to whether or not the documents are approved or disapproved. If the permit application, stormwater management plan or maintenance agreements are approved by Walker County, all appropriate land development permits may be issued and the following conditions apply:

(1) The applicant shall comply with all applicable requirements of the approved plan and this article and shall certify that all land clearing, construction, land development and drainage will be done according to the approved plan.

(2) The land development project shall be conducted only within the area specified in the approved plan.

(3) Walker County shall be allowed, after giving notice to the owner, occupier or operator of the land development project, to conduct periodic inspections of the project.

(4) The person responsible for implementing the approved plan shall conduct monitoring and submit reports as Walker County may require to ensure compliance with the approved plan and to determine whether the plan provides effective stormwater management.

(5) No changes may be made to an approved plan without review and written approval by Walker County.

(6) A certified inspection of all aspects of the structural stormwater control facility, including surface as-built surveys, and geotechnical inspections during subsurface or backfilling and compaction activities shall be required.

(7) It must be understood that in the event that the design fails, it is the responsibility of the owner/developer to get a revised plan from a design professional and to resubmit that plan to Walker County for review and approval.

History

The history line the source prints at the end of the section.

(Ord. of 12-1-2004, § 3.6)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:walker-county/code/22-732@2026-07-09-24250d079f

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Walker County Code of Ordinances, Sec. 22-732. Application procedure | Georgia Commons