Part II - CODE OF ORDINANCES / Chapter 22 - LAND DEVELOPMENT / Article VIII - POST-DEVELOPMENT STORMWATER MANAGEMENT FOR NEW DEVELOPMENT AND REDEVELOPMENT / Division 2 - POST-DEVELOPMENT STORMWATER MANAGEMENT PERMIT PROCEDURES AND REQUIREMENTS

Sec. 22-732. Application procedure.

Sobre este texto

  • As published by Municode, current through 2026-07-09
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

(a) Landowners or developers wishing to submit an application, must first attend a consultation meeting with Walker County for discussion of a stormwater concept plan. This meeting shall include the Planning Director, Environmental Manager, County Coordinator, and Road Supervisor from the County, as well as owner/developer and design professional.

(b) Applications for stormwater management permits must be filed with Walker County on any regular business day.

(c) A copy of this permit application shall be forwarded to the appropriate review agency for review.

(d) Permit applications shall include the following: 3 copies of the stormwater management plan, maintenance agreement and any required review fees.

(e) Walker County shall inform the applicant whether the application, stormwater management plan and maintenance agreement are approved or disapproved.

(f) If the permit application, stormwater management plan or maintenance agreements are disapproved, Walker County shall notify the applicant of the decision in writing. The applicant may then revise the permit application, stormwater concept plan, or the maintenance agreements and submit the required changes. If additional information is submitted, Walker County shall inform the applicant as to whether or not the documents are approved or disapproved. If the permit application, stormwater management plan or maintenance agreements are approved by Walker County, all appropriate land development permits may be issued and the following conditions apply:

(1) The applicant shall comply with all applicable requirements of the approved plan and this article and shall certify that all land clearing, construction, land development and drainage will be done according to the approved plan.

(2) The land development project shall be conducted only within the area specified in the approved plan.

(3) Walker County shall be allowed, after giving notice to the owner, occupier or operator of the land development project, to conduct periodic inspections of the project.

(4) The person responsible for implementing the approved plan shall conduct monitoring and submit reports as Walker County may require to ensure compliance with the approved plan and to determine whether the plan provides effective stormwater management.

(5) No changes may be made to an approved plan without review and written approval by Walker County.

(6) A certified inspection of all aspects of the structural stormwater control facility, including surface as-built surveys, and geotechnical inspections during subsurface or backfilling and compaction activities shall be required.

(7) It must be understood that in the event that the design fails, it is the responsibility of the owner/developer to get a revised plan from a design professional and to resubmit that plan to Walker County for review and approval.

Historia

La línea de historia que la fuente imprime al final de la sección.

(Ord. of 12-1-2004, § 3.6)

Leer este código donde se publica (Municode) La fuente es el código del condado tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:walker-county/code/22-732@2026-07-09-24250d079f

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Walker County Code of Ordinances, Sec. 22-732. Application procedure | Georgia Commons