Whitfield County · Code of Ordinances

Chapter 14 - SITE DESIGN / Article IV - ROAD STANDARDS

Sec. 14-49. Minimum right-of-way and pavement widths.

About this text

  • As published by Municode, current through 2026-05-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The minimum widths for right-of-way and pavement are as follows and are to be on the construction drawings:

Type Traffic volume (AADT) Number of lanes Right-of-way Width Local 0 — 4,999 1 lane each direction 50 (60 feet if no curb) Collector 5,000 — 9,999 1 lane each direction 80 Arterial 10,000 - 2 lanes each direction 100 or greater Minimum pavement width for any lane on any road is 12 feet.

On any existing street having a right-of-way less than the minimum which abuts a property being developed, one-half of the required width of right-of-way shall be dedicated at no cost to Whitfield County along the entire property boundary abutting the existing street.

Additional road right-of-way width may be required to be dedicated at intersections or other locations fronting the property where turning lanes, storage lanes, medians, islands, or realignments are required for traffic safety and minimum right-of-way standards would be inadequate to

accommodate the improvements.

If presented with a proposal that evaluates site-specific circumstances for new construction of local streets that will be part of an approved planned unit development (PUD, as defined in the Unified Zoning Ordinance), the county engineer, in his or her professional discretion, may allow a reduction in the required right-ofway width. Additionally, the county engineer, in his or her professional discretion, may allow

utility easements as substitution for rights-ofway. In such cases, the utility easement(s) shall be a minimum of 15 feet if provided along one

side of the right-of-way or a minimum of ten feet if provided along both sides of the right-of-way.

Utility construction shall occur outside the rightof-way and only within the provided easement(s). The county reserves the right to place equipment and facilities within the utility easement(s). Additionally, the county reserves the right to enter onto the utility easement(s) for the

purposes of maintenance and repair.

History

The history line the source prints at the end of the section.

(Res. of 6-9-03, § 4-4; Ord. No. 2019-090919, § 1, 9-9-19)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:whitfield-county/code/14-49@2026-05-11-efa405af9c

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Whitfield County Code of Ordinances, Sec. 14-49. Minimum right-of-way and pavement widths | Georgia Commons