Sec. 15-36. Stormwater drainage.

About this text

  • As published by Municode, current through 2026-05-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(1) The subdivider/developer shall provide adequate stormwater drainage in accordance with these regulations. The subdivider/developer shall also provide for adequate drainage all surface water drainage.

(2) The drainage system for a subdivision, residential, commercial, or manufacturing, shall be designed in accordance with sound engineering principles and procedures such that all marketable lots or parcels upon the plat are

positively drained.

(3) The drainage system shall be designed to accommodate drainage from adjacent lots or parcels which naturally drain to or through the lands being subdivided. The drainage system shall be designed such that it does not affect the natural drainage onto adjacent parcels unless an agreement is obtained by the developer/subdivider from the owner of such adjacent parcels. A copy of any such agreement shall be submitted to the Whitfield County Engineer.

(4) Drainage facilities which are designed to accommodate flowing waters shall be hydraulically designed to function when subjected to the maximum flow rate which may be expected to

occur no more often than once in ten years.

(5) Drainage facilities which are designed to handle water accumulations shall be designed to accommodate the maximum water level which may be expected to occur no more often than once in 25 years. Necessary drainage facilities including, but not limited to, culverts, rights-ofway, and easements, shall be offered for dedication to Whitfield County.

(6) All drainage systems discharging into any state waters, including but not limited to wetlands, as determined by the U.S. Army Corps of Engineers, shall pass through an approved sedimentation and detention pond prior to such discharge.

(7) A master drainage plan shall be submitted to the Whitfield County Engineer simultaneously with the submittal of a preliminary plat.

History

The history line the source prints at the end of the section.

(Ord. of 9-24-01, § 3-3; Res. of 5-13-02)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:whitfield-county/code/15-36@2026-05-11-61dced406a

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.