Skip to content
Georgia Commons
Menu

City: Alpharetta

Alpharetta City Council regular meeting, September 14, 2026

6:30 PM · 20 pages

These are the minutes as Alpharetta City Council posted them, read from the file on its own website. Georgia Commons is independent and is not affiliated with Alpharetta City Council.

Copy for LLM, View as markdown, and Send to AI use the Markdown version: the summary Georgia Commons wrote, under a heading that names it, then the record as posted. View raw is the record alone.

Records of this meeting

Each link opens the body's own website or meeting portal.

Summary

Written by an AI model (claude-sonnet-5-5) from the minutes below. It is not the record: the minutes are.

Council approved a change of zoning conditions allowing an enclosed rooftop restaurant at 116/126 North Main Street, plus landscape contract extensions, cloud services, and a lower Canton Street speed limit.

The council approved a consent agenda and then a change of conditions for 116 and 126 North Main Street that raises the allowed building height to four stories and 60 feet so a rooftop restaurant can be partly enclosed. A data center substation item was deferred by staff. Under new business, the council approved a right to enter agreement at 1325 Mid Broadwell Road for storm cleanup, two one-year landscape maintenance contract extensions, a $342,160 Microsoft cloud services addition through Dell Marketing LP, a speed limit reduction on Canton Street from 30 to 25 mph, and a $300,000 Lowe's Community Impact Grant agreement for the Old Rucker Farm house. In a work session, members discussed a possible Rotary winter parade without a vote. All votes were 7-0.

Topics taken up: 116/126 North Main Street rooftop restaurant; Royal 400 data center substation deferral; Right to Enter Agreement, 1325 Mid Broadwell Road; landscape maintenance contract extensions; Microsoft cloud services agreement; Canton Street speed limit reduction; Lowe's Community Impact Grant; Old Rucker Farm house renovation; Rotary winter parade discussion; Webb Bridge Park tunnel mural.

Decisions the minutes record (8)

Each decision is followed by the sentence of the minutes that records it, copied word for word.

  1. Approved change of zoning conditions at 116/126 North Main Street allowing a four-story, 60-foot building with an enclosed rooftop restaurant

    Adopted7-0

    The minutes: “Mayor Pro Tem Merkel offered a motion to approve PH-26-16 116/126 North Main Street”

    Read this item in the minutes

  2. Approved two one-year landscape maintenance contract extensions with Russell Landscape ($704,638.98) and Georgia Green ($186,213.70)

    Adopted7-0

    The minutes: “Council Member Reeves offered a motion to approve Russell Landscape's Contract No. 22 104/22 105 in the amount of $704,638.98 and Georgia Green's Contract No. 22 111 in the amount of $186,213.70 in the form of two one-year (12 month) renewals, and to authorize the Mayor to execute all necessary documents.”

    Read this item in the minutes

  3. Approved adding cloud services to the Microsoft Enterprise Agreement through Dell Marketing LP for $342,160.00

    Adopted7-0

    The minutes: “Council Member DeRito offered a motion to approve the addition of Cloud Services to the current three-year Enterprise Agreement with Microsoft from Dell Marketing LP for the amount of $342,160.00 using state contract number 9999-SPD-SPD0000060-0006, and authorize the Mayor to execute all necessary documents.”

    Read this item in the minutes

  4. Approved reducing the Canton Street speed limit north of Milton Avenue from 30 to 25 mph and petitioning GDOT

    Adopted7-0

    The minutes: “Council Member Driskell offered a motion to approve reducing the speed limit on Canton Street - North of Milton Avenue - from 30 miles per hour to 25 miles per hour and to petition”

    Read this item in the minutes

  5. Approved agreement with Points of Light for a $300,000 Lowe's Community Impact Grant for Old Rucker Farm

    Adopted7-0

    The minutes: “Council Member Hipes offered a motion to approve the ratification of an agreement between Points of Light (Lowe's Community Impact Grant Partners) and the City of Alpharetta for the award of grant funds in the amount of $300,000, and to authorize the Mayor to execute all necessary documents.”

    Read this item in the minutes

  6. Approved Right to Enter Agreement for storm cleanup at 1325 Mid Broadwell Road

    Adopted7-0

    The minutes: “Council Member Reeves offered a motion to approve a Right to Enter Agreement between Judith M. McDaniel, Sole Trustee of the Burton and Judy McDaniel Revocable Trust and the City of Alpharetta and to authorize the Mayor to execute all necessary documents.”

    Read this item in the minutes

  7. Approved consent agenda: prior minutes, Webb Bridge Park tunnel mural, and July 2026 financial report

    Adopted7-0

    The minutes: “Mayor Pro Tem Merkel offered a motion to approve the consent agenda.”

    Read this item in the minutes

  8. Royal 400 Data Center master plan amendment and conditional use for a Georgia Power substation deferred by staff

    Tabled

    The minutes: “DEFERRED: This item has been deferred by Staff, and it will not be considered at this meeting.”

    Read this item in the minutes

Agenda items (19)

Found in the minutes by their headings. Where an outcome is shown, it was read by rule from the item's own words: a guide to the text, not part of the record.

  1. 1. CALL TO ORDER
  2. 2. ROLL CALL
  3. 4. CONSENT AGENDA
  4. A. City Council Meeting Minutes (Meeting of 08/24/2026) Consideration and approval of the City Council meeting minutes from the meeting of August 24, 2026.
  5. B. Public Art Application — Webb Bridge Park Tunnel Mural Consideration and approval of a mural in the Webb Bridge Park Tunnel.
  6. C. Financial Management Report (Month Ending July 31, 2026) Consideration and approval of the Financial Management Report for the month ending July 31, 2026.Adopted
  7. 5. PUBLIC HEARING
  8. A. Announcement of Public Hearing ProceduresPublic comment
  9. B. PH-26-16 116/126 North Main Street – Change of ConditionA vote
  10. C. MP-26-13 / CU-26-11 Royal 400 Data Center
  11. 6. NEW BUSINESS
  12. A. Agreement: Right to Enter at 1325 Mid Broadwell RoadAdopted
  13. B. Landscape Maintenance Contract Extensions — Citywide by Russell Landscape and SR 400 by Georgia GreenAdopted
  14. C. Microsoft Enterprise Agreement Addition for Cloud Services with Dell Marketing LP Consideration of approval of the procurement of the addition of Cloud…Adopted
  15. D. Speed Reduction Recommendation on Canton Street - North of Milton Avenue Consideration of a motion to reduce the speed limit on Canton Street - North of…Adopted
  16. E. Agreement: Points of Light, Lowe's Community Impact Grant Partners Consideration and approval of an agreement between Points of Light (Lowe's Community…Adopted
  17. 7. WORK SESSION
  18. A. Natural Resources Commission UpdateA presentation
  19. B. Discussion regarding an Alpharetta Rotary Winter Parade
  20. 8. PUBLIC COMMENTPublic comment
  21. 9. REPORTSA presentation
  22. 10.EXECUTIVE SESSION (IF NECESSARY)Adopted
  23. 11.ADJOURNMENTAdopted

Answers are written by AI from this document, and every quotation is checked against it. Not legal advice.

The minutes

As posted on alpharettaga.api.civicclerk.com, read November 11, 2026. Nothing below is written by Georgia Commons.

1. CALL TO ORDER

• Mayor Gilvin called the meeting to order at 6:30 p.m.

2. ROLL CALL

• Council Members o Mayor Jim Gilvin o Mayor Pro Tem Dan Merkel o T. Kirk Driskell o Katie Reeves o Douglas J. DeRito o John Hipes o Fergal M. Brady

• Staff o Chris Lagerbloom, City Administrator o John Robison, Assistant City Administrator o Molly Esswein, City Attorney o Lauren Shapiro, City Clerk o Adam Montgomery, Director of Information Technology City Council Meeting & Public Hearing

SEPTEMBER 14, 2026

OFFICIAL MINUTES

Office of the City Clerk

ALPHARETTA CITY HALL

COUNCIL CHAMBERS | 2 PARK PLAZA | 6:30 PM

OFFICIAL MINUTES

The public is advised that the following minutes are not a verbatim transcription of business presented at the Council Meeting of the date shown; but are a synopsis of pertinent information. The public is further advised that the video recording for said meeting is a matter of public record and is available to be viewed at the City Clerk’s office during normal business hours or viewed online at https://www.youtube.com/user/alpharettagov.

o Brad Dekinger, Chief of Fire o Charlie Jewell, Director of Economic Development o Deanna McKay, Public Communication & Engagement Coordinator o Kathi Cook, Director of Community Development

o Pete Sewczwicz, Director of Public Works o Tom Harris, Director of Finance o Christine Young, Senior Operations Manager o Andrew Splawn, Police Captain o Scott Mechler, Deputy Police Chief

3. PLEDGE TO THE FLAG

4. CONSENT AGENDA

A. City Council Meeting Minutes (Meeting of 08/24/2026) Consideration and approval of the City Council meeting minutes from the meeting of August 24, 2026.

B. Public Art Application — Webb Bridge Park Tunnel Mural Consideration and approval of a mural in the Webb Bridge Park Tunnel.

C. Financial Management Report (Month Ending July 31, 2026) Consideration and approval of the Financial Management Report for the month ending July 31, 2026.

PUBLIC COMMENTS:

There were no public comments.

 Mayor Pro Tem Merkel offered a motion to approve the consent agenda.

o Council Member Brady seconded the motion.

o The motion was approved unanimously (7-0).

5. PUBLIC HEARING

A. Announcement of Public Hearing Procedures

• City Attorney, Molly Esswein, announced the public hearing procedures.

B. PH-26-16 116/126 North Main Street – Change of Condition

Consideration of a change of conditions to allow a portion of the rooftop to be enclosed on the building closest to North Main Street. The enclosed space and outdoor rooftop would be used for a restaurant. The enclosed space represents a 4th floor on the building. The property is located at 116 & 126 North Main Street and is legally described as being located in Land Lot 1252, 2nd District, 2nd Section, Fulton County, Georgia.

• Director of Community Development, Kathi Cook, came forward to present this item.

• The applicant, Joshua Stallworth, is requesting changes to conditions of zoning to allow for rooftop space to be enclosed resulting in a four (4) story building. Changes to conditions of zoning are requested to allow for a rooftop restaurant in the building closest to North Main Street. The rooftop restaurant includes enclosed, occupiable space which constitutes a fourth (4th) story. The subject property is located at 116 & 126 North Main Street on the west side of North Main Street across from Cumming Street.

• Staff recommends that Mayor and Council approve PH-26-16 116/126 North Main Street – Change of Condition, subject to the following conditions (Original conditions are included below with amended and new conditions depicted in RED):

1. The site, consisting of approximately 1.43 acres, shall be zoned DT-MU and developed substantially similar to site plan prepared by AEC, dated 4/28/2022, except for modifications required to comply with the conditions below. Uses shall be limited to office, retail, restaurant and ‘For-Sale’ residential.

2. Maximum building height shall be no greater than 3 4 stories and 46’ 60’, as submitted.

3. Building ‘B’ shall be limited to office and residential uses. Rooftop shall be limited to residential amenity space.

4. A 15’ building setback shall be provided on North Main Street and shall include a minimum 5’ landscape strip located outside of any easements. A 20’ building setback, as measured from the existing right-of-way, shall be provided on Violet Garden Walk and shall include a minimum 15’ landscape strip.

5. Architecture and materials shall be developed similar to the submitted renderings prepared by Tracy Ward dated 2/28/2022, except for modifications required to comply with these conditions and in compliance with the Alpharetta Downtown Code, subject to approval by the Downtown Consultant and DRB. Openings in parking deck walls shall include decorative screens similar to Teasley Place, with final approval by DRB.

6. The historic building at 116 North Main Street shall be limited to office or restaurant use.

7. 116 North Main Street shall be saved on the property, restored, and designated under the City’s Historic Preservation Incentive Ordinance. Restoration shall be completed by the 1st TCO/CO, subject to a Certificate of Appropriateness from the Historic Preservation Commission.

8. Lot coverage shall not exceed 80%.

9. Parking deck shall be screened with a mix of landscape materials of varying heights, with final approval by DRB.

10.Decorative lighting and trees shall be placed on the upper deck, with final approval by DRB.

11.Final streetscape shall include decorative pedestrian lighting, as approved by Staff.

12.Street trees shall be required in the planter along North Main Street (as approved by GDOT) and Violet Garden Walk, as well as behind the sidewalks as a continuation of what has been previously planted or designed in the Downtown and outside of any utility easements, as approved by Staff. In lieu of tree grates, the soil area around street trees shall be planted with evergreen ornamental grasses, groundcovers and/or shrubs.

13.Amenity space shall be developed on building rooftops and limited to use by the occupants, invitees and guests of the development. The rear building rooftop amenity space shall be limited to occupants, invitees, and guests of the office and residential space within the rear building. Occupiable vertical structures shall be prohibited on the rooftops of the building closest to West of Main. Greenspace amenity areas shall

be planted with decorative landscaping, hardscape, walls and seating. The landscape shall include plant selections promoting the historic district.

14.Foundation plantings, consisting of ornamental trees, shrubs, vines and/or grasses, shall be required for buildings with frontage along North Main Street, Cumming Street and Violet Garden Walk.

15.Developer shall remove tree #787 (46” Water Oak) and #788 (37” Willow Oak) and in exchange will plant 21 – 6” caliper overstory trees on the property at final development.

16.Decorative paver aprons shall be required at project driveways, as approved by Staff.

17.10’ sidewalk requirement on Violet Garden Walk shall be reduced to 5’ with the remaining 5’ added to the landscape area.

18.Developer shall construct a minimum 5’ sidewalk along the Cumming Street extension connecting sidewalks on North Main Street and Violet Garden Walk, as approved by Staff.

19.Developer shall screen car head lights with sufficient parking deck wall height and landscaping.

20.Developer shall improve project driveway access to North Main Street based on the recommendations of the traffic study, with final approval by Staff. Access modification shall require a GDOT driveway permit, ICE study, and signal modification for both existing and future GDOT improved condition. If a CO is anticipated post GDOT construction, only final condition required).

21.Dumpster placement will be determined by Staff and Design Review Board prior to construction.

22.All vehicular access to the site, including all truck deliveries, shall be provided through a driveway off North Main Street; no vehicular access or truck deliveries to the site shall be provided from Lily Garden Place or Violet Garden Walk.

23.Rooftop space shall be developed substantially similar to the submitted floor plans and limited to the building closest to North Main Street.

24.Rooftop space shall be limited to a restaurant or amenity space for the users of the subject building.

25.In an effort to limit offsite impacts from noise, there shall be no outdoor speakers or live music in the uncovered or covered, unenclosed rooftop space.

26.Rooftop restaurant hours of operation shall not exceed 11:00 PM.

• The 1.43-acre property is currently under construction and has frontage on North Main Street and Violet Garden Walk. In 2022, the property was approved for a rezoning to DT-MU (Downtown Mixed-Use) allow 32,000 square feet of office, 4,000 square feet of retail, 8,000 square feet of restaurant and four (4) ‘For-Sale’ condominium units with structured parking. The development included two (2), three (3) story buildings with rooftop amenities, as well as preserving the historic structure located at 116 North Main Street. Surrounding properties are zoned C-1 (Neighborhood Commercial) to the north, O-I (Office-Institutional) to the east, DT-MU to the south, and R-10M (Dwelling, ‘For-Sale’, Residential) to the west. Cabinets To Go is located to the east, Alpharetta Center for Dentistry is located to the north, West of Main subdivision is located to the west, and 100 North Main is located to the south. The comprehensive land use plan designation of the property is ‘Mixed Use’.

• According to the application, The Whiskey Project would occupy a portion of the 3rd floor and the rooftop space on the building nearest North Main Street, which would include enclosing a portion of the rooftop. The Whiskey Project is a full-service restaurant and whiskey bar which formerly operated on Oak Street in Downtown Roswell. The restaurant serves contemporary American cuisine with a large selection of whiskey, bourbon, wine, beer, and craft cocktails. In order to allow the rooftop space to be utilized for the applicant’s restaurant, the following changes to conditions of zoning are requested to Z-22-02/V-22-08 116 & 126 North Main Street:

2. Maximum building height shall be no greater than 3 4 stories and 46’ 60’.

13. Amenity space shall be developed on building rooftops and limited to use by the occupants, invitees and guests of the development. The rear building rooftop amenity space shall be limited to occupants, invitees, and guests of the office and residential space within the rear building. Occupiable vertical structures shall be prohibited on the rooftops of the building closest to West of Main. Greenspace amenity areas shall

be planted with decorative landscaping, hardscape, walls and seating. The landscape shall include plant selections promoting the historic district.

• The submitted renderings and floor plans depict the applicant’s restaurant concept utilizing a portion of the third (3rd) floor, as well as space on the rooftop which is both enclosed and unenclosed. The 3rd floor restaurant space is approximately 3,414 square feet. The rooftop area is 8,344 square feet, of which 1,439 square feet is currently covered, but not enclosed. The applicant proposes covering 3,860 square feet of the rooftop space, of which 2,407 square feet will be enclosed, and 1,453 square feet will be covered (not enclosed). An uncovered rooftop dining area, approximately 800 square feet in size, is proposed on the east side of the rooftop adjacent to North Main Street. The remaining areas of the rooftop will be utilized for rooftop mechanical equipment.

• The use of approximately half of the third (3rd) floor and rooftop area for a restaurant will change the parking requirements for the development. 139 parking spaces are provided within the development. A total of 114 parking spaces will be required for the development with the applicant’s proposed condition (3rd floor/rooftop restaurant). The proposal would result in a surplus of approximately 25 parking spaces for the development.

• The Citizen Participation Plan Report submitted by the applicant states that letters were mailed to each property owner within 500’ of the subject property stating the applicant’s intent. The report states that public comments received at the CZIM were generally positive with some concern over the building height, safety, noise and hours of operation.

• The Community Zoning Information Meeting was held on August 12, 2026. There were public comments in support of the request that liked the restaurant concept as long as hours of operation were reasonable and noise was controlled. Those in opposition felt that the building is too tall and had concerns over fall prevention safety on the rooftop.

• Staff have reviewed the applicant’s proposal against the review criteria for a change of zoning. The proposal would not adversely affect the existing use or usability of adjacent or nearby properties and the existing zoning of the property allows up to four (4) stories or 60’, whichever is less. The 2022 rezoning request on the property contemplated

utilizing the rooftops as amenity space, which was covered but not enclosed. Therefore, the physical height of the building would not change. The proposed rooftop restaurant space is located in the building nearest North Main Street and furthest from West of Main in an effort to limit impacts on neighboring residential properties. The rear building would remain at three (3) stories with the rooftop area limited to amenity space for office and residential users of the rear building.

• The applicant, Joshua Stallworth, came forward to present on behalf of the application.

PUBLIC COMMENTS:

In Opposition:

• Dr. RJ O’Donnell, 134 North Main Street, Alpharetta, GA 30009  Mayor Pro Tem Merkel offered a motion to approve PH-26-16 116/126 North Main Street

– Change of Condition, subject to the following conditions:

1. The site, consisting of approximately 1.43 acres, shall be zoned DT-MU and developed substantially similar to site plan prepared by AEC, dated 4/28/2022, except for modifications required to comply with the conditions below. Uses shall be limited to office, retail, restaurant and ‘For-Sale’ residential.

2. Maximum building height shall be no greater than 4 stories and 60’, as submitted.

3. Building ‘B’ shall be limited to office and residential uses. Rooftop shall be limited to residential amenity space.

4. A 15’ building setback shall be provided on North Main Street and shall include a minimum 5’ landscape strip located outside of any easements. A 20’ building setback, as measured from the existing right-of-way, shall be provided on Violet Garden Walk and shall include a minimum 15’ landscape strip.

5. Architecture and materials shall be developed similar to the submitted renderings prepared by Tracy Ward dated 2/28/2022, except for modifications required to comply with these conditions and in compliance with the Alpharetta Downtown Code, subject to approval by the Downtown Consultant and DRB. Openings in parking deck walls shall include decorative screens similar to Teasley Place, with final approval by

DRB.

6. The historic building at 116 North Main Street shall be limited to office or restaurant use.

7. 116 North Main Street shall be saved on the property, restored, and designated under the City’s Historic Preservation Incentive Ordinance. Restoration shall be completed by the 1st TCO/CO, subject to a Certificate of Appropriateness from the Historic Preservation Commission.

8. Lot coverage shall not exceed 80%.

9. Parking deck shall be screened with a mix of landscape materials of varying heights, with final approval by DRB.

10.Decorative lighting and trees shall be placed on the upper deck, with final approval by

DRB.

11.Final streetscape shall include decorative pedestrian lighting, as approved by Staff.

12.Street trees shall be required in the planter along North Main Street (as approved by GDOT) and Violet Garden Walk, as well as behind the sidewalks as a continuation of what has been previously planted or designed in the Downtown and outside of any utility easements, as approved by Staff. In lieu of tree grates, the soil area around street trees shall be planted with evergreen ornamental grasses, groundcovers and/or shrubs.

13.Amenity space shall be developed on building rooftops. The rear building rooftop amenity space shall be limited to occupants, invitees, and guests of the office and residential space within the rear building. Occupiable vertical structures shall be prohibited on the rooftops of the building closest to West of Main. Greenspace amenity areas shall be planted with decorative landscaping, hardscape, walls and seating. The landscape shall include plant selections promoting the historic district.

14.Foundation plantings, consisting of ornamental trees, shrubs, vines and/or grasses, shall be required for buildings with frontage along North Main Street, Cumming Street and Violet Garden Walk.

15.Developer shall remove tree #787 (46” Water Oak) and #788 (37” Willow Oak) and in exchange will plant 21 – 6” caliper overstory trees on the property at final development.

16.Decorative paver aprons shall be required at project driveways, as approved by Staff.

17.10’ sidewalk requirement on Violet Garden Walk shall be reduced to 5’ with the remaining 5’ added to the landscape area.

18.Developer shall construct a minimum 5’ sidewalk along the Cumming Street extension connecting sidewalks on North Main Street and Violet Garden Walk, as approved by Staff.

19.Developer shall screen car head lights with sufficient parking deck wall height and landscaping.

20.Developer shall improve project driveway access to North Main Street based on the recommendations of the traffic study, with final approval by Staff. Access modification shall require a GDOT driveway permit, ICE study, and signal modification for both existing and future GDOT improved condition. If a CO is anticipated post GDOT construction, only final condition required).

21.Dumpster placement will be determined by Staff and Design Review Board prior to construction.

22.All vehicular access to the site, including all truck deliveries, shall be provided through a driveway off North Main Street; no vehicular access or truck deliveries to the site shall be provided from Lily Garden Place or Violet Garden Walk.

23.Rooftop space shall be developed substantially similar to the submitted floor plans and limited to the building closest to North Main Street.

24.Rooftop space shall be limited to a restaurant or amenity space for the users of the subject building.

25.In an effort to limit offsite impacts from noise, there shall be no outdoor speakers or live music in the uncovered or covered, unenclosed rooftop space.

26.Rooftop restaurant hours of operation shall not exceed 11:00 PM.

o Council Member Hipes seconded the motion.

o The motion was approved unanimously (7-0).

C. MP-26-13 / CU-26-11 Royal 400 Data Center

DEFERRED: This item has been deferred by Staff, and it will not be considered at this meeting.

Consideration of a request for master plan amendment and conditional use to allow a Georgia Power substation in conjunction with an expansion at an existing data center on

38.8 acres in the Royal 400 Master Plan. The applicant requests to amend the Royal 400 Master Plan to add ‘Utility Substation’ as a conditional use and a conditional use is requested to allow a ‘Utility Substation’ at the applicant’s property. The property is located at 4905 North Point Parkway and is legally described as being located in Land Lots 850, 851, 858 & 859, 1st District, 2nd Section, Fulton County, Georgia.

6. NEW BUSINESS

A. Agreement: Right to Enter at 1325 Mid Broadwell Road

Consideration and approval of a Right to Enter Agreement between Judith M. McDaniel, Sole Trustee of the Burton and Judy McDaniel Revocable Trust and the City of Alpharetta and with the authorization for Mayor to execute all necessary documents.

• City Attorney, Molly Esswein, came forward to present this item.

• After recent storm events, multiple trees have fallen on property owned by the City. In order to provide remediation after the storm, it is necessary for the City to enter upon the property located at 1325 Mid Broadwell Road, owned by the Burton and Judy McDaniel Revocable Trust. Remediation efforts will include removing multiple trees and tree stumps, and a portion of fence will need to be removed and reinstalled.

• This agreement will give the City a temporary, exclusive right to enter upon the property to perform the clean-up work.

• This agreement will expire 90 days from the execution date.

 Council Member Reeves offered a motion to approve a Right to Enter Agreement between Judith M. McDaniel, Sole Trustee of the Burton and Judy McDaniel Revocable Trust and the City of Alpharetta and to authorize the Mayor to execute all necessary documents.

o Council Member Brady seconded the motion.

o The motion was approved unanimously (7-0).

B. Landscape Maintenance Contract Extensions — Citywide by Russell Landscape and SR 400 by Georgia Green

Consideration of approval of the extensions for Russell Landscape's Contract No. 22 104/22 105 in the amount of $704,638.98 and Georgia Green's Contract No. 22 111 in the amount of $186,213.70 in the form of two one year (12 month) renewals, and authorize the Mayor to execute all necessary documents.

• Director of Public Works, Pete Sewczwicz, came forward to present this item.

• Ongoing roadway construction by the Georgia Department of Transportation (GDOT) along SR 9 (Main Street) and by the City's project along Webb Bridge Road between the Big Creek Greenway tunnel under Webb Bridge Road and the roundabout at Webb Bridge Way (Phase 2B) continues to affect substantial portions of the landscape maintenance areas covered under this contract.

• Roadway construction continues to disrupt routine maintenance within the areas included in the current landscape maintenance contract. Additionally, over $2,000,000 in new landscape installation is planned across multiple phases beginning in November 2026 and continuing through spring 2028. Planting locations include, but are not limited to:

o SR 9 from Milton Avenue to Windward Parkway o Webb Bridge Road Phase 2B o Roswell Street from Old Milton Parkway to Old Roswell Street

• Consistent with the City’s established practice, a single contractor is responsible for installing, maintaining, and warranting all landscape associated with annual capital projects. This approach minimizes conflicts and ensures clear accountability throughout all phases of the work.

• In addition to future landscape plantings, the contracts are associated with landscape maintenance of enhanced corridors (Rucker Road, Kimball Bridge, etc..) as well as standard mowing and edging services along other roadways like Haynes Bridge Road and Mansell Road.

• Roadway construction associated with the SR 400 Express Lanes affects all interchanges within Alpharetta city limits. Clearing and grubbing the SR 400 Interchanges in a phased manner has created a challenge regarding maintenance. The anticipated completion of the SR 400 Express Lanes project construction is in 2031. True North 400

Partners with the City (50-50) on the landscape maintenance of the SR 400 Interchanges and Encore Parkway Bridge.

• To ensure continuity of service and maintain cost stability, staff recommends extending the current contract for two consecutive one-year (12 month) renewals. The current vendor has agreed to maintain the prior fiscal year annual price of $186,213.70 for the first year of the extension, with a 3% increase applied for the second extension year.

• At the conclusion of this extension period, the City will reassess its ability to effectively advertise a new Request for Proposal (RFP). It is expected that the impacts of the interchanges will be known over the next 18 months and Public Works, in partnership with True North 400, will issue a new contract for maintenance work at the interchanges.

• Recently, Georgia Green was purchased by Russell Landscape and the extension of these contracts will be under the responsibility of Russell Landscape and the contracts will all be under Russell Landscape.

PUBLIC COMMENTS:

• There were no public comments.

 Council Member Reeves offered a motion to approve Russell Landscape's Contract No. 22 104/22 105 in the amount of $704,638.98 and Georgia Green's Contract No. 22 111 in the amount of $186,213.70 in the form of two one-year (12 month) renewals, and to authorize the Mayor to execute all necessary documents.

o Council Member DeRito seconded the motion.

o The motion was approved unanimously (7-0).

C. Microsoft Enterprise Agreement Addition for Cloud Services with Dell Marketing LP Consideration of approval of the procurement of the addition of Cloud Services to the current three-year Enterprise Agreement with Microsoft from Dell Marketing LP for the amount of $342,160.00 using state contract number 9999-SPD-SPD0000060-0006, and authorize the Mayor to execute all necessary documents.

• Director of Information Technology, Adam Montgomery, came forward to present this item.

• These agreements allow the City to operate server, storage, web hosting, networking, and security in the Microsoft Azure Government Community Cloud (GCC) and the GCC High clouds.

• Starting in 2019, the Information Technology Department engaged in a discussion with Microsoft about utilizing the Azure GCC cloud environment for public cloud infrastructure. As a new customer, Microsoft strongly recommended the City procure through a licensed Microsoft Cloud Server Provider (CSP), who could set up the environment, help monitor, and assist with any issues. In fiscal year 2020, the Council approved a contract with SHI International through state contract to have Airnet as our CSP. This relationship proved worth the investment.

• As the department matured in its ability to manage the cloud environments, the need to work through the CSP reduced. Sence the beginning of the contract, we have struggled to be able to verify costs when billed through CSP and SHI. As we need to add new features, we must go through the CSP, which can be a slower process. As a result, we are proposing to migrate the environment from the CSP to buying direct from Microsoft, through our current Enterprise Agreement.

• Over the past several months, we have again engaged Microsoft for direction on migrating from our CSP to managing our clouds directly and have a plan to conduct the work needed to accomplish this move. This new agreement and migration will allow us to be much more agile to the changing needs of the City departments, as their needs adjust, or technology evolves.

• We currently operate most of the infrastructure in the GCC environment. A smaller portion of the infrastructure operates in Azure GCC High.

• The infrastructure running in GCC High costs approximately 33% more than GCC, so we evaluate more closely what runs there. Both clouds are currently operated through the CSP and will be migrated.

• The attached Dell Marketing LP quote is $342,160.00. This is $2,160.00 over the budgeted amount. However, the Finance Department believes the amount can be absorbed in the current budget without a need for unallocated funds. This is also an increase over fiscal years 2025 and 2026 of $22,160.00, which is attributed to more consumption in the Azure cloud and Microsoft price increases.

• On August 8, 2026, Council approved a new three-year Enterprise Agreement, that is paid annually. For fiscal year 2027, Council approved a budget amount for the Azure cloud infrastructure of $340,000.00. In previous years this amount would have been billed monthly by SHI for the previous month’s consumption. While we could do a month-to-month billing with Microsoft, there are pricing benefits to purchasing through the current Enterprise Agreement. The caveat is that we purchase credits upfront at our annual renewal.

• The current quote, from Dell Marketing LP, which is whom we purchased the Enterprise Agreement with, shows two line-items. The first is the credits needed for the GCC infrastructure, $225,680.00. This item will be added to the current Enterprise Agreement. The second is the GCC High infrastructure, $116,480.00. Only one Azure cloud can be on an Enterprise Agreement, so paperwork is attached to this agenda item to establish an identical agreement for the GCC High environment.

• This Microsoft Enterprise Agreement addition and new agreement is funded in the fiscal year 2027 budget. A single quote using Georgia statewide contract 99999-SPD-SPD0000060-0006 is provided by Dell Marketing LP.

PUBLIC COMMENTS:

• There were no public comments.

 Council Member DeRito offered a motion to approve the addition of Cloud Services to the current three-year Enterprise Agreement with Microsoft from Dell Marketing LP for the amount of $342,160.00 using state contract number 9999-SPD-SPD0000060-0006, and authorize the Mayor to execute all necessary documents.

o Council Member Brady seconded the motion.

o The motion was approved (7-0).

D. Speed Reduction Recommendation on Canton Street - North of Milton Avenue Consideration of a motion to reduce the speed limit on Canton Street - North of Milton Avenue - from 30 miles per hour to 25 miles per hour and petition the Georgia Department of Transportation to approve the same.

• Chief of Police, Trent Lindgren, came forward to present this item.

• Based on multiple citizen complaints of speeding violations, Public Works executed a speed analysis which supports reducing the posted speed limit on Canton Street from 30 mph to 25 mph as a reasonable traffic-safety measure. North of Lily Garden Place, the 85th-percentile speed ranged from 30 to 32 mph northbound and 29–31 mph southbound, with northbound traffic consistently operating at or slightly above the existing 30-mph limit. The data also documented recurring higher-speed vehicles, including vehicles traveling in the 45–49, 50–54, and 55–59 mph ranges. The concern is more pronounced south of Lily Garden Place, where the northbound 85th-percentile speed ranged from 34 to 37 mph, with multiple vehicles recorded traveling between 50–59 mph. These findings are particularly significant given the roadway's substantial traffic volume, which ranged from approximately 5,100 to more than 10,300 vehicles per 24-hour period during the study. While the majority of motorists are traveling near the existing speed limit, the data demonstrates a recurring pattern of vehicles operating at significantly higher speeds, particularly in the northbound direction.

• The current 30-mph speed limit also presents an enforcement challenge because it provides relatively little enforcement margin when the majority of traffic is operating near or slightly above that threshold. Reducing the limit to 25 mph would establish a more appropriate operating expectation and provide a more meaningful threshold for targeted speed enforcement. Additionally, Canton Street is the only one of the four primary roadways approaching this downtown intersection that is currently posted at 30 mph; the other three approaches are already posted at 25 mph. Reducing Canton Street to 25 mph would therefore create consistency among all four approaches to the downtown intersection and establish a uniform speed expectation for motorists entering this area. Considering the documented operating speeds, significant traffic volume, recurring high-speed vehicles, enforcement considerations, and the existing 25-mph limits on the other three approaches, reducing Canton Street from 30 mph to 25 mph is a reasonable and defensible safety recommendation.

PUBLIC COMMENTS:

There were no public comments.

 Council Member Driskell offered a motion to approve reducing the speed limit on Canton Street - North of Milton Avenue - from 30 miles per hour to 25 miles per hour and to petition

the Georgia Department of Transportation to approve the same, and authorize the Mayor to execute all necessary documents.

o Mayor Pro Tem Merkel seconded the motion.

o The motion was approved (7-0).

E. Agreement: Points of Light, Lowe's Community Impact Grant Partners Consideration and approval of an agreement between Points of Light (Lowe's Community Impact Grant Partners) and the City of Alpharetta for the award of grant funds in the amount of $300,000, and with authorization for the Mayor to execute all necessary documents.

• City Administrator, Chris Lagerbloom, introduced the item.

• Senior Operations Manager, Christine Young, came forward to present this item.

• The Alpharetta Community Agriculture Program models and inspires the stewardship of natural resources through sustainable practices while connecting the community through growing food and nature-based education. We create hands-on opportunities for residents to grow, prepare, preserve, and share healthy food while building practical skills, stronger community connections, and a more resilient local food system.

• Old Rucker Farm is the physical hub of Alpharetta’s Community Agriculture Program and a working community farm where residents can see food being grown using sustainable practices. The farm includes production areas, educational growing spaces, community garden plots, an orchard, pollinator habitats, an apiary, chicken coop, and outdoor learning areas. Approximately 95% of the harvest from our production areas is donated to North Fulton Community Charities.

• The Alpharetta Community Agriculture Program provides year-round opportunities for residents to grow food, learn practical food-system skills, and connect with local agriculture. Old Rucker Farm offers programs that help residents grow food at home and at the farm, including seasonal seeds and transplants and hands-on growing education.

• The Community Agriculture & Sustainability Division has applied for the Lowe’s Community Impact Grant annually for the past 4 years. It is with great celebration that in the fifth year, the City’s Community Agriculture Program has been awarded $300,000 to complete the renovation of the house at Old Rucker Farm into an

Educational Facility. Currently, the house at Old Rucker Farm consists of three bedrooms, one bathroom, and a basement. The renovation will transform the existing residential interior footprint into an open floor plan setting, including: complete replacement of flooring, updating wiring, and converting the kitchen to a teaching kitchen.

Improvements will also be made to the existing bathroom so that the current porta potties onsite will no longer be needed (unless special events require additional bathrooms).

• There is no match requirement for this grant but the proceeds must be spent on or before March 1, 2027.

• The house at Old Rucker Farm will be transformed into an Agriculture & Sustainability Education Center. The renovated farmhouse will provide a permanent indoor space for community learning, with a teaching kitchen designed for hands-on, healthy cooking, food preparation and preservation classes. Together, the farm and farmhouse will create a “seed-to-table” learning environment where participants can grow food, harvest it, prepare it, preserve it and understand how those skills contribute to a healthier and more resilient community.

• After receiving the Lowe's Community Impact Grant, the Old Rucker Farm will have generated $631,055 towards the house renovation project. The house renovation project is primarily funded through grant proceeds (including match funding by the City in the case of Food Well) and fundraising proceeds, with the intent that the house renovation scope will be constrained by these funding levels. Below is a summary of all funds raised.

o Lowe’s Community Impact Grant: $300,000 o Gift by Mr. and Mrs. Tieken: $150,000 o Food Well Alliance Grant and Capital Funds: $139,372 o Community Fundraising for House Renovation: $41,683

• Contract approval for buildout of the house renovation project will come before the City Council for approval at a later date.

• There is no funding set aside in the FY 2027 Budget for operational program expansion, if any, related to usage of the renovated house facility.

PUBLIC COMMENTS:

• There were no public comments.

 Council Member Hipes offered a motion to approve the ratification of an agreement between Points of Light (Lowe's Community Impact Grant Partners) and the City of Alpharetta for the award of grant funds in the amount of $300,000, and to authorize the Mayor to execute all necessary documents.

o Council Member Driskell seconded the motion.

o The motion was approved unanimously (7-0).

7. WORK SESSION

A. Natural Resources Commission Update

• Chair of the Natural Resources Commission, Mike Buchannon, came forward to provide an update on work being done by the Natural Resources Commission.

B. Discussion regarding an Alpharetta Rotary Winter Parade

• City Administrator, Chris Lagerbloom, introduced this item.

• Mayor Pro Tem Merkel shared additional details regarding a future parade to occur on December 2nd near Wills Park and down Roswell Street and is in favor trying to have a parade this year.

• Council Member Hipes shared that a parade would be a way to contribute to “small town Alpharetta” and support the commerce that we have in Downtown Alpharetta.

• Council Member Reeves asked about conflicts with any other city events for the proposed parade date and shared that this gives her great pause.

• Mayor Gilvin shared that he is hesitant because of history with Old Soldier’s Day Parade and cannot support an event that is not a City event.

• Council Member Brady shared that he loves parades and that this would be great for the community.

8. PUBLIC COMMENT

• There were no public comments.

9. REPORTS

• There were no reports.

10.EXECUTIVE SESSION (IF NECESSARY)

 Mayor Pro Tem Merkel offered a motion to recess the meeting.

o Council Member Brady seconded the motion.

o The motion was approved unanimously (7-0).

• Mayor Gilvin recessed the meeting at 7:43 p.m. for the purposes of litigation.

 Council Member Reeves offered a motion to reconvene the meeting.

o Mayor Pro Tem Merkel seconded the motion.

o The motion was approved unanimously (7-0).

• Mayor Gilvin reconvened the meeting at 7:43 p.m. for the purposes of litigation.

11.ADJOURNMENT

 Council Member DeRito offered a motion to adjourn the meeting.

o Mayor Pro Tem Merkel seconded the motion.

o The motion was approved unanimously (7-0).

• With there being no further items to consider or discuss, Mayor Gilvin adjourned the meeting at 9:27 p.m.

Respectfully submitted, Lauren Shapiro, City Clerk