8.20. Inspections and Responsibility During

About this text

  • As posted on the city's website, retrieved 2026-11-11

Construction

A. The developer and their Design Professional of Record have full responsibility for quality control and inspection during construction to ensure substantial conformance with the

approved construction plans, Town standards, Town regulations, and generally accepted construction practices. Town personnel are only providing construction observation to intermittently check the adequacy of the developer's quality control and inspection.

B. Any construction issues requiring an interpretation and/or change in the plans, standards, and/or regulations are to be

resolved by the Design Professional of Record and presented to the Town Engineer for

written concurrence or approval. Any design changes must be revised on the construction plans and issued as a change to the approved construction plans.

C. Following the issuance of any permit authorizing clearing and grading of a site, areas required to be undisturbed, such as natural landscape buffers or stream buffers, must be designated by survey stakes, flags, ribbon, or other appropriate markings and must be inspected and approved by the Town Inspector prior to the commencement of any clearing or grading activities.

D. Requests for inspections must be made by the owner or contractor to the Town Public Works Department in accordance with the listing of inspection responsibilities established by Town. Requests must be made at least 24

hours prior to when the inspection is needed.

Inspections must be made and passed prior to continuation of further activity or

proceeding into new phases. Inspections are required of each of the following phases, as applicable to the actual work to be performed under the development permit:

1. Prior to clearing or clearing and grubbing of the property or any portion included under the development permit, inspection of

erosion and sedimentation control measures and protective devices for undisturbed areas. Inspection of erosion and sedimentation control measures will

be conducted on a continuing basis.

2. Upon completion of street grading, inspection and approval must be complete prior to trenching or continuation with

subgrade preparation.

3. Upon installation of storm drainage pipe, detention, or other storm water facilities.

4. Street curbing and gutter (if provided).

Inspection must be requested after the forms or string line have been set. Street width and vertical and horizontal

alignment may be spot-checked.

5. Sub-grade of streets. The sub-grade may be roll tested.

6. Street base. The base may be string-lined for depth and crown. The street base will be tested for depth and compaction in

accordance with Sec. 9.11 and may be rolltested, at the discretion of the Town Engineer.

7. For asphalt paving, the temperature of the material will be monitored, the asphalt will be tested for depth and compaction in

accordance with Sec. 9.11, and may be roll-tested, at the discretion of the Town Engineer.

Read this code where it is posted (city website (Revize)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:braselton/zoning/8.20@2026-11-11-f654e7775f