A. Submittal of construction plans shall include the following lift station information:
1) Capacity calculations.
a. Use one gpm capacity per house on residential developments of less than 200, except that the minimum pump capacity shall be 30 gpm.
b. System head calculations; tabulated and plotted on the pump curve. Include a plot of force main velocity.
2) Standard drawings, details and specifications sufficient to ascertain compliance with these regulations.
3) Wet well volume calculations and cycle time at design conditions.
4) Storage volume.
a. Calculations showing volume of storage available in the event of a power outage.
b. The storage zone shall be delineated on plan and profile drawings of the sewer system. (See standby power paragraph below)
5) Surge relief calculations showing whether surge control valves are necessary.
6) Buoyancy computations showing that structures are protected against flotation.
B. Shop drawings. After construction plan approval but before purchasing any lift station equipment, shop drawings shall be submitted including the following information:
1) Manufacturer's catalog sheets, performance curves, installation drawings, specifications and list of options for the specific pump that is offered for approval.
2) Similar catalog data for controls, valves, hatches, yard hydrants, precast wet well and other manufactured items.
C. Certification.
1) After installation and before placing the system into full operation, the work must be inspected by the developer's engineer who must then issue a certification to the city verifying that all work has been done in accordance with approved plans.
2) After acceptance of the work by the city engineer, a factory representative shall inspect and start up the system certifying rotation, capacity; amperage draw, lack of vibration and other standard check points.
3) This certification shall state the beginning date of the warranty and include a copy of the warranty.
D. Operations and maintenance manuals.
1) On or before the date of start-up, five sets of factory operations and maintenance manuals shall be delivered to the city.
2) These shall include the name of the contractor (or whoever's name the purchase was under), the serial numbers of pumps, telephone number and address for purchase of parts and detailed wiring schematics.
E. After construction is complete "as-built" drawings shall be furnished, as follows:
1) Provide electronic files in pdf format and in a "Cad" format that is compatible with the city's GIS system.
2) Provide four sets of full size prints and one set of half-size prints.
History
(Ord. No. 2014-18, § 2, 8-21-2014)