Sec. 109-333. Sanitary sewerage system.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) The subdivider or land developer shall provide sanitary sewer facilities to each lot within the bounds of the subdivision, or to the land

development, in accordance with the requirements of chapter 111, pertaining to utilities, as adopted and as may be amended from time to

time, applicable specifications adopted by the city department of utilities which may be amended from time to time, and any applicable requirements of this division. All street sewers serving lots in the subdivision shall be installed by the

subdivider. A formula may be developed by the director of utilities to provide for a sharing of the costs of other sewer facilities needed to serve the subdivision or land development when certain of the required sewer facilities are necessary to serve other subdivisions or land developments in the same drainage basin.

(b) When a public sanitary sewer is not available within 100 feet of the property line of the subdivision or land development in question, the

director of utilities may in cases where sanitary sewer service is not available or reasonably accessible, may approve an alternate method of sewage disposal for each lot or the land development

subject to compliance with the standards of the county health department. If public sewerage is not available, but is expected to be accessible within a reasonable time period after completion of the subdivision or land development, an alternate method for sewage disposal for individual lots or the land development will be required on

an interim basis. In this instance, unless otherwise determined by the mayor and council, the developer will be required to construct a complete

sanitary sewer system for the subdivision or land development, including outfall lines, street sewers, and service stubs to individual lots. All sewers will be plugged and otherwise protected to ensure serviceability at the time of connection to

the public system, and will conform to the specifications of the city.

History

The history line the source prints at the end of the section.

(Ord. of 2-18-2003, § 805; Ord. of 3-16-2004(02), § IV; Ord. of 5-17-2005(02), § 18)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:cumming/zoning/109-333@2026-11-11-fb3fcba6fd

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Cumming Zoning Ordinance, Sec. 109-333. Sanitary sewerage system | Georgia Commons