Appendix A - UNIFIED DEVELOPMENT CODE / 9.4 - Street Construction Requirements

9.4.4. Base Course Construction

About this text

  • As published by Municode, current through 2026-05-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The base course must consist of graded aggregate of a minimum compacted thickness of eight inches placed on a stabilized subbase in accordance with these specifications and in conformity with the lines, grade, and typical section as shown on the drawings approved by the county.

A. Materials All materials shall be secured from the Georgia Department of Transportation approved sources:

1. Graded aggregate must consist of hard, durable particles of fragments of stone, and stone mortar, and must be graded as indicated on Table 9.4.1.

Table 9.4.1. Aggregate Grade Sieve Size Designation Percent by Weight Passing Square Mesh 2 inches 100 1� inches 95—100 inches 60—100 No. 10 30—50 No. 60 10—35 No. 200 7—15 Sand 20 (of material passing No 10)

B. Preparation of Subgrade All boulders, organic material, soft clay, spongy material and any other objectionable material must be removed and replaced with approved material. The

subgrade must be properly shaped, rolled and uniformly compacted to conform with

the lines, grades and typical sections as shown on the drawings approved by the

county.

C. Placing and Rolling Aggregate All base course material must be deposited and spread by means of spreader boxes,

or approved mechanical equipment, or from moving vehicles equipped to distribute the material in a uniform layer.

Each layer may be no more than two inches in thickness after compaction and must be constructed as follows:

1. Immediately following the spreading of the coarse aggregate, all mateAPPENDIX A—UNIFIED DEVELOPMENT CODE § 9.4 rial placed must be compacted to

the full width by rolling with a smooth wheel power roller weighing seven to ten tons, or an equivalent sheepsfootpacker. Rolling must progress gradually from the sides to the center, parallel with the centerline of the street and lapping uniformly each preceding track by

one-half the width of such track, and must continue until all the surface has been rolled and has been thoroughly keyed, and the interstices of the stone reduced to a minimum, and until it ceases to creep or wave ahead of the roller.

2. Any irregularities or depressions that develop under such rolling must be corrected by loosening the material at these places and adding or removing material until the surface

is smooth and uniform.

3. After the coarse aggregate has been thoroughly keyed and set by the rolling described above, screenings in an amount that will completely fill the interstices must be applied gradually over the surface and rolling must be continued while the screenings are being spread, so that

the jarring effect of the roller will cause the screenings to settle into the voids of the coarse aggregate.

4. The screenings must not be dumped in piles on the coarse aggregate but spread in thin layers, either by spreading motion with hand shovels, by mechanical spreading or directly from trucks.

5. In no case may the screening be applied so fast or thickly as to cake or bridge on the surface in such manner as to prevent the filling of all voids or prevent the direct bearing of the roller on the coarse aggregate.

6. Hand brooms must be used to sweep the screenings into unfilled voids and to distribute the stone where needed. The spreading, sweeping and rolling must continue until no more screenings can be forced into the void.

7. Shaping and rolling must be performed alternately as required to maintain a uniform compacted base until a surface or treatment has been applied to the base.

8. Along curbs, headers and walls and at all places not accessible to the roller, the base course material must be tamped thoroughly with mechanical tampers or approved hand tampers.

D. Seasonal Limits on Construction No base material may be deposited or shaped when the subgrade is frozen or thawing or during unfavorable weather conditions.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hall-county/zoning/9.4.4@2026-05-28-8ccf399b96