Appendix A - UNIFIED DEVELOPMENT CODE / Article 10 - EROSION CONTROL AND STORMWATER MANAGEMENT / Division 3 - DAMS

1016.04. New dams which become subject

About this text

  • As published by Municode, current through 2023-12-05
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

to the requirements of the Georgia Safe Dams Act and Rules for Dam Safety.

Dams proposed to be 25 feet or more in height or proposed to have an impounding capacity of 100 acre-feet or more at maximum water storage elevation shall be subject to the following:

(a) The developer of any new dam in which development exists within the proposed

breach zone shall be subject to the requirements of the Georgia Safe Dams Act and Rules for Dam Safety adopted by the

Georgia Department of Natural Resources.

The developer shall obtain necessary approvals and permits from the Environmental Protection Division of the Georgia Department of Natural Resources

for the project and the dam prior to securing a Land Disturbance Permit from the Community Development Department. The developer of any new dam as to which development does not exist within the proposed breach zone shall submit

construction plans to Harris County for review of the project and the dam prior to securing a Development Permit from the

Department.

(b) If the developer elects to construct the new dam in accordance with the design

standards for new dams as contained in the Rules for Dam Safety, then new development shall be permitted within the dam breach zone. However, the dam shall meet the design standards for new dams as contained in the Rules for Dam Safety if development currently exists or is proposed in the dam breach zone.

(c) If the developer elects not to construct the new dam to the design standards for

new dams as contained in the Rules for Dam Safety, then a dam breach analysis for the dam shall be submit- ted along with the construction plans for review prior to securing a Land Disturbance Permit from the Community Development Department. The design engineer shall utilize the computer model entitled "DAMBRK" for the dam breach analysis.

(d) Should the new dam not meet the design standards for new dams as contained in

the Rules for Dam Safety, then only the following uses and structures shall be permitted within the dam breach easement:

(1) Agriculture which requires no structures for human habitation within the dam breach zone including forestry, livestock raising, and agricultural and forestry access

roads.

(2) Fences.

(3) Signs in accordance with Article 7 of this Development Code.

(4) Roads, driveways and parking areas.

(5) Utility poles, towers, pipelines, water treatment outfalls and facilities, or

other similar facilities and structures.

(e) For any new dam that is proposed not to meet the design for new dams as contained in the Rules for Dam Safety, the developer shall obtain a dam breach easement,

recorded with the Clerk of Superior Court, from any offsite property owner where it is proposed for the dam breach zone to

extend off the property where the dam is being constructed. The developer shall

also cause a dam breach easement to be recorded upon the property being developed.

(f) Prior to recording of a Final Plat or issuance of a Certificate of Occupancy, as appropriate, an as-built certification from a registered professional engineer shall be submitted to the Community Development Department. The certification shall state that the dam is constructed in

accordance with the provisions of these regulations as well as the authorized construction plans. If the project is for the development of a subdivision, the

developer shall also establish a legal entity, acceptable to Harris County, such as a mandatory Property Owner's Association, at time of recording of the Final Plat, responsible for the maintenance of the dam and its impoundment.

(g) In addition to State requirements, a new dam shall be on a single of land so that it is owned and maintained by a single

owner or entity.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:harris-county/zoning/1016.04@2023-12-05-8a3416d1ae

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Harris County Zoning Ordinance, 1016.04. New dams which become subject | Georgia Commons