(1) Installation required. The developer shall install or have installed a system of water mains connected to a public water supply system in accordance with these requirements and those of the authority having jurisdiction to provide water service within the city, herein referred to as the water authority.

(2) Design policy. All water mains, fire hydrants and appurtenances shall be designed in accordance with the policies, standards, plans

and specifications of the city and the water authority.

(3) Installation timing. Water mains and appurtenances shall be installed after installation of the curbs and gutters and before paving, or

as approved by the city and the water authority.

(4) Fire hydrant requirements. Fire hydrants shall conform to AWWA C502-85 for dry-barrel fire hydrants and the following requirements:

a. Hydrants shall be traffic type with safety flange that allows the valve to remain closed when the hydrant is broken or damaged above or near grade level.

b. The design of hydrant shall be of the compression type with main valves and "O" ring seal between the operating nut and the bonnet.

c. Hydrant color shall be silver.

d. Hydrant inlet shall be six-inch, mechanical joint with harnessing lugs.

e. Hydrant main valve opening shall be five and one-quarter-inch.

f. Valve seats shall be bronze to bronze.

g. Operating nut shall be solid Pentagon, one and one-half inches measured flat at point (31/32 on side). Operating nut shall turn counter clockwise to open.

h. Hydrant shall have two, two and one-halfinch diameter and one, four and one-halfinch diameter nozzle. Nozzles threads shall be the standard adopted by NBFU.

Nozzles shall all have gasketed caps fitted with chain.

i. The following fire hydrants are approved for installation on development projects within the city, other models may be acceptable when dedicated to and approved by the utility provider:

Table 12.3-1 Acceptable Fire Hydrant Models Manufacturer Model American AVK 2700 and 2780 Mueller Centurion and Improved Kennedy K81-A M&H 129 and 929 Clow Medallion American-Darling B-62B

U.S. M-94

j. Materials shall conform to AWWA Standard C-502, latest revision.

(5) Water mains and fire hydrants on private property and subdivisions. In addition to the other requirements of these regulations water mains installed on private property and within subdivisions shall also comply with the following requirements:

a. Water main size.

1. Water mains of at least eight-inch pipe shall be installed; six-inch pipe may be used only where it completes a gridiron and then only up to 600 feet in length between interconnecting mains of approved diameter, unless otherwise approved by the public works director and the

fire marshal.

2. No main line smaller than eight inches shall serve more than one fire hydrant and automatic extinguishing system or one fire hydrant on any dead-end main more than

300 feet in length. All water mains shall be sized in accordance with NFPA 24, as adopted by the State of Georgia.

b. Fire hydrant spacing. Fire hydrants shall be spaced not more than 500 feet apart, with additional fire hydrants located as necessary to comply with the requirements of the International Fire Code and Appendices as adopted by the city

and approved by the fire marshal.

c. Private fire hydrants. Hydrants that are not maintained by Atlanta-Fulton County Water Department and on a dedicated meter or loop system shall be considered private fire hydrants. These private hydrants shall have general maintenance

performed annually in accordance with the currently adopted edition of NFPA

25. These maintenance records shall be maintained on the premises for inspection, or sent directly to the city fire marshal's office for review and filing. All maintenance shall be performed by a qualified company that is familiar with NFPA 25's

guidelines. These private hydrants shall also be painted red and a three-foot perimeter shall be maintained free and clear at all times.

d. Clearance around fire hydrants. A minimum of three feet of clearance shall be provided around all fire hydrants.

e. Water main material. Water mains shall be of ductile iron or copper or a type listed for this service by a nationally recognized testing laboratory and approved for use by the water authority.

f. Minimum cover. Water mains shall be installed at least 12 inches below the frost depth. In areas where frost is not a factor the water main shall be installed to a minimum depth of 42 inches below grade. When the water main is installed under a driveway or roadway it shall be installed 48 inches below grade or 48 inches below railroads.

g. Hydrostatic testing. Water mains shall be hydrostatically tested at not less than 200-psi or 50-psi greater than the system working pressure, whichever is greater, and shall maintain that pressure, ± five-psi, for two hours in the presence of a representative of the city. Pressure loss shall be determined by a loss in gauge pressure or visual leakage.

h. Fittings and valves. Hydrants, fittings, valves and fire department connections shall be approved by the fire department. Fire department connections shall be not less than 18 inches or more than

36 inches above the level of the adjoining ground or paving. The thread of such connections shall be uniform with that

used by the fire department.

i. Timing of installation. Water mains and fire hydrants shall be installed, under water pressure and ready for fire fighting before any construction with combustible material begins onsite.

j. Dead end mains. In no case shall dead end mains exceed 600 feet in length for main sizes less than ten inches.

(6) Sub meters required. The county water department provides water service to residential multi-unit buildings. These services are billed by the utility on a master meter basis and the

landlord or property owner is responsible for paying the utility for all charges contained in such bills. All new multi-family buildings shall be billed by the owner or landlord or by a third party based on sub-unit meters which will be installed at the time of construction.

(7) Commercial car wash water recycling. All new commercial conveyor car washes, permitted and constructed after January 1, 2011, must install operational recycled water systems, regardless of the water source. A minimum of 50% of water utilized will be recycled. This

regulation does not apply to self-service car washes or in-bay car washes.

(8) Rain sensor shut off switches on new irrigation systems. Pursuant to O.C.G.A. § 12- 5-6, all new landscape irrigation systems for both residential and nonresidential properties will require rain sensor shut off switches. This regulation does not apply to either landscape irrigation systems installed on golf courses, or any system dependent upon a non-public water source.

(Ord. No. 2009-06-18, (12.3), 6-29-2009; Ord.

No. 2011-03-06, § 2, 3-28-2011)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:johns-creek/zoning/113-143@2026-11-11-66b7752afb

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Johns Creek Zoning Ordinance, Sec. 113-143. Water system and fire hydrants | Georgia Commons