Sec. 28-81. Inspection process.

About this text

  • As published by Municode, current through 2026-02-17
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The director, using the construction drawings, shall conduct a field inspection of the subdivision or development. If there are deviations from the approved drawings deemed by the director to be significant, the director shall require the developer to submit revised drawings and/or engineering studies (as appropriate), reflecting the changes. The changes shall be further reviewed for compliance with the original approval and comments of the TRC. Once the director is satisfied that compliance has been achieved, the developer shall be notified that a final plat may be submitted. A satisfactory inspection of a site development shall cause the director to issue a certificate of completion letter to the developer, stating the development has met all applicable requirements.

History

The history line the source prints at the end of the section.

(Res. of 7-17-2007(2); Ord. of 6-25-2024(1))

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:putnam-county/zoning/28-81@2026-02-17-f5f2dcc222

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Putnam County Zoning Ordinance, Sec. 28-81. Inspection process | Georgia Commons