Sec. 3-222. Driveway culverts.

About this text

  • As published by Municode, current through 2022-10-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Where a wet weather drainage ditch exists between the proposed road and 20 feet into the lot, the design professional shall size the driveway culvert as if the driveway were at the lowest point on that lot. The construction plans shall show the minimum driveway pipe size required.

(b) Driveway culverts may be any of the types of pipe materials approved for longitudinal pipe installation.

(c) The inlet and outlet end of all driveway culverts shall have either flared-end sections or concrete headwalls that meet the standards of Georgia Department of Transportation 1120 or 1125.

History

The history line the source prints at the end of the section.

(Ord. of 5-17-2021(1))

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:woodbury/zoning/3-222@2022-10-28-a2c4f5a4e2

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Woodbury Zoning Ordinance, Sec. 3-222. Driveway culverts | Georgia Commons